2 <br />3 <br />51 <br />5 <br />L <br />7 <br />on <br />A <br />C <br />a <br />E <br />F <br />1 Smoke Evacuation Schematic Diagram <br />Scale: NTS <br />SMOKE CONTROL SYSTEM VERIFICATION <br />INSPECTION PROCEDURES FOR SMOKE CONTROL <br />1 SCOPE <br />THE INSPECTION PROCEDURES DESCRIBED APPLY TO SMOKE CONTROL SYSTEMS THAT ARE DEDICATED <br />TO CONTROLLING SMOKE IN BUILDING ATRIUM FIRES. THESE PROCEDURES ADDRESS THE MAJOR <br />COMPONENTS OF SMOKE CONTROL SYSTEMS. THE PHRASE AS SPECIFIED IS USED TO MEAN AS <br />SPECIFIED IN ACCORDANCE WITH CONTRACT DOCUMENTS, THE FLORIDA BUILDING, NFPA 92B SMOKE <br />MANAGEMENT SYSTEMS IN MALLS, ATRIA AND LARGE SPACES, LATEST EDITION. <br />2 BARRIERS <br />a. CHECK WALLS, PARTITIONS, FLOORS, AND CEILINGS OF BARRIERS OF SMOKE CONTROL <br />SYSTEMS FOR OBVIOUS AND UNUSUAL OPENINGS THAT COULD ADVERSELY AFFECT SMOKE CONTROL <br />PERFORMANCE. <br />b. CHECK THAT GAPS AROUND DOORS DO NOT EXCEED THE LIMITS SPECIFIED. IF GASKETING IS <br />REQUIRED, CHECK THAT IT IS AS SPECIFIED. <br />G. CHECK THAT AUTOMATIC DOOR CLOSERS IN BARRIERS OF SMOKE CONTROL SYSTEMS ARE AS <br />SPECIFIED. <br />3 AIR -MOVING EQUIPMENT <br />A. CHECK DUCTS TO VERIFY THAT DUCT MATERIAL AND CONSTRUCTION ARE AS SPECIFIED, <br />B. CHECK DUCT INSTALLATION. DUCT INSTALLATION, INCLUDING THE HANGERS, MUST NOT REDUCE <br />THE FIRE -RESISTIVE RATING OF STRUCTURAL MEMBERS AND ASSEMBLIES. FREQUENTLY, <br />STRUCTURAL MEMBERS AND ASSEMBLIES HAVE FIRE -PROTECTIVE COVERINGS, SUCH AS DRY WALL <br />CONSTRUCTION OR SPRAYED -ON LAYER. CHECK THAT DUCTS ARE INSTALLED IN SUCH A MANNER <br />THAT THESE PROTECTIVE COVERINGS ARE NOT DAMAGED. CHECK THAT CLEARANCE FROM DUCTS <br />TO COMBUSTIBLE CONSTRUCTION IS AS SPECIFIED. IN ADDITION, CHECK THAT WHERE DUCTS PASS <br />THROUGH WALLS, FLOORS, OR PARTITIONS, THE OPENINGS IN CONSTRUCTION AROUND THE DUCTS ARE <br />AS SPECIFIED. <br />C. CHECK DUCT COVERINGS AND LININGS TO VERIFY THAT THEIR FIRE SAFETY REQUIREMENTS ARE <br />AS SPECIFIED. CHECK THAT DUCT COVERINGS DO NOT CONCEAL ANY SERVICE OPENING. <br />D. CHECK DIRECT ACCESS AND INSPECTION PROVISIONS. SERVICE OPENINGS AND TELESCOPING OR <br />REMOVABLE DUCT SECTIONS ARE USED FOR DIRECT ACCESS AND INSPECTION. CHECK THAT A <br />SERVICE OPENING ACCESS DOOR IS PROVIDED IN DUCTS AS SPECIFIED ADJACENT TO FIRE <br />DAMPERS, SMOKE DAMPERS, AND SMOKE DETECTORS, CHECK THAT THESE ACCESS OPENINGS <br />ARE IDENTIFIED WITH LETTERS AS SPECIFIED. CHECK THAT SERVICE OPENINGS ARE PROVIDED IN <br />HORIZONTAL DUCTS AND PLENUMS WHERE SPECIFIED. <br />E. CHECK AIR FILTERS TO VERIFY THAT THEY HAVE THE CLASSIFICATION SPECIFIED. <br />F. CHECK THAT THE LOCATION, FIRE PROTECTION RATING, AND INSTALLATION OF FIRE, CEILING, AND <br />SMOKE DAMPERS ARE AS SPECIFIED. GENERALLY, FIRE, CEILING, AND SMOKE DAMPERS SHOULD <br />BE INSTALLED IN ACCORDANCE WITH THE CONDITIONS OF THEIR LISTING AND THE <br />MANUFACTURER'S INSTALLATION INSTRUCTIONS THAT ARE SUPPLIED WITH THE DAMPER. <br />FURTHER CHECK INSTALLATION BY REMOVING THE FUSIBLE LINK (WHERE APPLICABLE) AND <br />OPERATE THE DAMPER TO VERIFY THAT IT FULLY CLOSES. IT IS DESIRABLE TO OPERATE DAMPERS <br />WITH NORMAL AIR FLOW TO ENSURE THAT THEY ARE NOT HELD OPEN BY THE AIRSTREAM. <br />REMEMBER TO REINSTALL ALL FUSIBLE LINKS THAT HAVE BEEN REMOVED DURING INSPECTION. <br />4 CONTROLS <br />a. CHECK MANUAL CONTROLS. CHECK THAT DEVICES FOR MANUAL ACTIVATION AND DEACTIVATION <br />OF THE SMOKE CONTROL SYSTEM ARE OF MATERIALS AND INSTALLATION AS SPECIFIED. <br />b. CHECK AUTOMATIC CONTROLS. CHECK THAT DEVICES FOR AUTOMATIC ACTIVATION AND <br />DEACTIVATION AND CONTROL OF THE SMOKE CONTROL SYSTEM ARE OF MATERIALS AND <br />INSTALLATION AS SPECIFIED. <br />PROCEDURES FOR SMOKE -CONTROL SYSTEM TESTING <br />1. BEFORE TESTING SMOKE -CONTROL SYSTEMS, VERIFY THAT CONSTRUCTION IS COMPLETE AND VERIFY HE <br />INTEGRITY OF EACH SMOKE -CONTROL ZONE BOUNDARY. VERIFY THAT WINDOWS AND DOORS ARE <br />CLOSED AND THAT APPLICABLE SAFING, GASKET, AND SEALANTS ARE INSTALLED. REPORT DEFICIENCIES <br />AND POSTPONE TESTING UNTIL AFTER THE REPORTED DEFICIENCIES ARE CORRECTED. REFERTO <br />INSPECTION PROCEDURES FOR SMOKE CONTROL. <br />2. MEASURE AND RECORD WIND SPEED AND DIRECTION, OUTSIDE -AIR TEMPERATURE, AND RELATIVE <br />HUMIDITY ON EACH TEST DAY. <br />3. MEASURE, ADJUST, AND RECORD AIRFLOW OF EACH SMOKE -CONTROL FAN WITH ALL FANS THAT ARE A PART <br />OF THE SYSTEM OPERATING AS INTENDED BY THE DESIGN. <br />4. MEASURE, ADJUST, AND RECORD THE AIRFLOW OF EACH FAN. FOR DUCTED SYSTEMS, MEASURE THE FAN <br />AIRFLOW BY DUCT PITOT-TUBE TRAVERSE. <br />5. MEASURE AND RECORD THE AIR FLOW VELOCITY THROUGH THE ATRIUM OUTSIDE DOORS. <br />6. AFTER AIR BALANCING IS COMPLETE, PERFORM THE FOLLOWING PRESSURIZATION TESTING: <br />a. VERIFY THE BOUNDARIES OF SMOKE -CONTROL ATRIUM ZONE. <br />b. WITH THE HVAC SYSTEMS IN THEIR NORMAL MODE OF OPERATION AND SMOKE CONTROL NOT <br />OPERATING, MEASURE AND RECORD THE PRESSURE DIFFERENCE ACROSS EACH SMOKE -CONTROL <br />ARE OF THE ATRIUM. MAKE MEASUREMENTS AFTER CLOSING DOORS THAT SEPARATE THE AREAS. <br />MAKE ONE MEASUREMENT ACROSS EACH DOOR. CLEARLY INDICATE THE HIGH AND LOW <br />PRESSURE SIDE OF EACH DOOR. <br />C. WITH THE SYSTEM OPERATING IN THE SMOKE -CONTROL MODE PERFORM THE FOLLOWING: <br />1. MEASURE AND RECORD THE PRESSURE DIFFERENCE ACROSS EACH DOOR THAT SEPARATES THE <br />SMOKE AREA FROM ADJACENT AREAS. MAKE MEASUREMENTS WITH DOORS THAT SEPARATE THE <br />ATRIUM SMOKE ZONE FROM THE OTHER AREAS CLOSED. CLEARLY INDICATE THE HIGH AND LOW <br />PRESSURE SIDE OF THE DOOR. DOORS THAT HAVE A TENDENCY TO OPEN SLIGHTLY DUE TO THE <br />PRESSURE DIFFERENCE SHOULD HAVE ONE PRESSURE MEASUREMENT MADE WHILE HELD CLOSED <br />AND ANOTHER MEASUREMENT MADE WITH THE DOOR OPEN. <br />2. THE ATRIUM AREA PRESSURE SHOULD BE LOWER (NEGATIVE) WITH RESPECT TO EACH DOOR ON THE <br />SMOKE AREA BOUNDARY. <br />7. OPERATIONAL TESTS: <br />a. CHECK THE PROPER ACTIVATION OF ATRIUM SMOKE -CONTROL SYSTEM IN RESPONSE TO ALL MEANS OF <br />ACTIVATION, BOTH AUTOMATIC AND MANUAL. <br />b. CHECK AND RECORD THE PROPER OPERATION OF FANS, DAMPERS, AND RELATED EQUIPMENT AS <br />OUTLINED BELOW FOR THE ATRIUM SMOKE -CONTROL SYSTEM. <br />1. SMOKE -CONTROL SYSTEM AUTOMATIC ACTIVATION. <br />2. TYPE OF SIGNAL THAT ACTIVATES A SMOKE -CONTROL SYSTEM I.E. SMOKE DETECTOR. <br />3. FANS "ON" AS REQUIRED TO IMPLEMENT THE SMOKE -CONTROL SYSTEM. <br />4. FAN(S) "OFF" AS REQUIRED TO IMPLEMENT THE SMOKE CONTROL SYSTEM. <br />5. DAMPERS "OPEN" WHERE MAXIMUM AIRFLOW MUST BE ACHIEVED. <br />6. DAMPER(S) "CLOSED" WHERE NO AIRFLOW SHOULD TAKE PLACE, <br />7. AUXILIARY FUNCTIONS TO ACHIEVE THE SMOKE -CONTROL SYSTEM CONFIGURATION SUCH AS <br />CHANGES OR OVERRIDE OF NORMAL OPERATING PRESSURE AND TEMPERATURE -CONTROL SET <br />POINTS. <br />8. IF STANDBY POWER IS PROVIDED FOR THE SMOKE -CONTROL SYSTEM, TEST TO VERIFY THAT THE <br />SYSTEM FUNCTIONS WHILE OPERATING UNDER BOTH NORMAL AND STANDBY POWER. <br />9. CONDUCT ADDITIONAL TEST REQUIRED BY AUTHORITIES HAVING JURISDICTION. UNLESS REQUIRED <br />BY AUTHORITIES HAVING JURISDICTION, PERFORM TESTING WITHOUT THE USE OF MOKE OR <br />PRODUCTS THAT SIMULATE SMOKE. <br />10. PREPARE A COMPLETE REPORT OF OBSERVATIONS, MEASUREMENTS, AND DEFICIENCIES. <br />SMOKE SYSTEM CONTROL VERIFICATION <br />1. CHECK FREE TRAVEL AND PROPER OPERATION OF CONTROL DEVICES SUCH AS DAMPER OPERATORS. <br />2. CHECK THE SEQUENCE OF OPERATION OF CONTROL DEVICES. NOTE AIR PRESSURES AND DEVICE <br />OSITIONS AND CORRELATE WITH AIRFLOW MEASUREMENTS. NOTE THE SPEED OF RESPONSE TO INPUT <br />HANGES. <br />3. CHECK THE INTERACTION OF ELECTRICALLY OPERATED SWITCH TRANSDUCERS. <br />4. CHECK THE INTERACTION OF INTERLOCK AND LOCKOUT SYSTEMS, <br />5. RECORD VOLTAGES OF POWER SUPPLY AND CONTROLLER OUTPUT. DETERMINE WHETHER THE SYSTEM <br />OPERATES ON A GROUNDED OR NONGROUNDED POWER SUPPLY. <br />6. NOTE OPERATION OF ELECTRIC ACTUATORS USING SPRING RETURN FOR PROPER FAIL-SAFE OPERATIONS. <br />TOLERANCES <br />1 SET HVAC SYSTEM AIRFLOW RATES WITHIN THE FOLLOWING TOLERANCES: <br />a. FANS: 0 TO PLUS 10 PERCENT <br />INSPECTIONS <br />2 FINAL INSPECTION <br />a. AFTER INITIAL INSPECTION IS COMPLETE AND CHECKS VERIFIES THAT TESTING AND <br />BALANCING ARE COMPLETE AND ACCURATELY DOCUMENTED IN THE FINAL REPORT, <br />REQUEST THAT A FINAL INSPECTION BE MADE BY THE OWNER. <br />b. SMOKE TESTING FIRM TEST AND BALANCE ENGINEER SHALL CONDUCT THE INSPECTION <br />IN THE PRESENCE OF THE OWNER AND THE ARCHITECT AND CODE OFFICIALS. <br />C. SMOKE TESTING FIRM SHALL RECHECK ALL MEASUREMENTS AND MAKE <br />ADJUSTMENTS. REVISE THE FINAL REPORT AND BALANCING DEVICE SETTINGS TO <br />INCLUDE ALL CHANGES AND RESUBMIT THE FINAL REPORT. <br />FINAL REPORT <br />1 GENERAL: TYPEWRITTEN, OR COMPUTER PRINTOUT IN LETTER -QUALITY FONT, ON STANDARD BOND <br />PAPER, IN THREE-RING BINDER, TABULATED AND DIVIDED INTO SECTIONS BY TESTING AND BALANCED <br />SYSTEMS. <br />2 INCLUDE A CERTIFICATION SHEET IN FRONT OF BINDER SIGNED AND SEALED BY THE CERTIFIED TESTING <br />NO BALANCING ENGINEER. <br />a. NCLUDE A LIST OF INSTRUMENTS USED FOR PROCEDURES, ALONG WITH PROOF OF <br />CALIBRATION. <br />3 FINAL REPORT CONTENTS: IN ADDITION TO CERTIFIED FIELD REPORT DATA, INCLUDE THE FOLLOWING: <br />a. FAN CURVES <br />b. MANUFACTURER'S TEST DATA. <br />C. FIELD TEST REPORTS PREPARED BY SYSTEM AND EQUIPMENT INSTALLERS. <br />d. OTHER INFORMATION RELATIVE TO EQUIPMENT PERFORMANCE, BUT DO NOT <br />INCLUDE SHOP DRAWINGS AND PRODUCT DATA. <br />4 GENERAL REPORT DATA: IN ADDITION TO FORM TITLES AND ENTRIES, INCLUDE THE FOLLOWING DATA IN <br />HE FINAL REPORT, AS APPLICABLE: <br />a. TITLE PAGE <br />b. NAME AND ADDRESS OF TAB FIRM <br />C. PROJECT NAME <br />d. PROJECT LOCATION <br />e. ARCHITECT'S NAME AND ADDRESS <br />f. ENGINEER'S NAME AND ADDRESS <br />9. CONTRACTOR'S NAME AND ADDRESS <br />h. REPORT DATE <br />i. SIGNATURE OF TAB FIRM WHO CERTIFIES THE REPORT <br />j. TABLE OF CONTENTS WITH THE TOTAL NUMBER OF PAGES DEFINED FOR EACH <br />SECTION OF THE REPORT. NUMBER EACH PAGE IN THE REPORT. <br />k. SUMMARY OF CONTENTS INCLUDING THE FOLLOWING: <br />1 INDICATED VERSUS FINAL PERFORMANCE <br />2 NOTABLE CHARACTERISTICS OF SYSTEMS <br />3 DESCRIPTION OF SYSTEM OPERATION SEQUENCE IF IT VARIES FROM THE <br />CONTRACT DOCUMENTS <br />I. NOMENCLATURE SHEETS FOR EACH ITEM OF EQUIPMENT <br />M. DATA FOR TERMINAL UNITS, INCLUDING MANUFACTURER, TYPE SIZE, AND FITTINGS <br />n. NOTES TO EXPLAIN WHY CERTAIN FINAL DATA IN THE BODY OF REPORTS VARIES FROM <br />INDICATED VALUES <br />o. TEST CONDITIONS FOR FANS INCLUDING THE FOLLOWING: <br />1 SETTINGS FOR OUTSIDE AIR AND SMOKE DAMPERS <br />2 FAN DRIVE SETTINGS INCLUDING SETTINGS AND PERCENTAGE OF MAXIMUM PITCH <br />DIAMETER <br />5 OTHER SYSTEMS OPERATING CONDITIONS THAT AFFECT PERFORMANCE <br />6 FAN TEST REPORTS: INCLUDE THE FOLLOWING: <br />a. FAN DATA: <br />1 SYSTEM IDENTIFICATION <br />2 LOCATION <br />3 MAKE AND TYPE <br />4 MODEL NUMBER AND SIZE <br />5 MANUFACTURER'S SERIAL NUMBER <br />6 ARRANGEMENT AND CLASS <br />7 SHEAVE MAKE, SIZE IN INCHES, AND BORE <br />8 SHEAVE DIMENSIONS, CENTER -TO -CENTER, AND AMOUNT OF ADJUSTMENTS IN <br />INCHES <br />b. MOTOR DATA: <br />1 MAKE AND FRAME TYPE AND SIZE <br />2 HORSEPOWER AND RPM <br />3 VOLTS, PHASE, AND HERTZ <br />4 FULL -LOAD AMPERAGE AND SERVICE FACTOR <br />5 SHEAVE MAKE, SIZE IN INCHES, AND BORE <br />6 SHEAVE DIMENSIONS, CENTER -TO -CENTER, AND AMOUNT OF ADJUSTMENTS IN <br />INCHES <br />7 NUMBER OF BELTS, MAKE, AND SIZE <br />C. TEST DATA (INDICATED AND ACTUAL VALUES): <br />1 TOTAL AIRFLOW RATE IN CFM <br />2 TOTAL SYSTEM STATIC PRESSURE IN INCHES WG <br />3 FAN RPM <br />4 DISCHARGE STATIC PRESSURE IN INCHES WG <br />5 SUCTION STATIC PRESSURE IN INCHES WG <br />SMOKE REMOVAL SEQUENCE: <br />1. ATRIUM SMOKE DETECTOR DETECTS SMOKE. <br />2. FIRST FLOOR LOBBY DOORS C109, C109A, C10913, C109C, C100, C100A AND <br />Cl 10 OPEN. <br />3. MAKE-UP AIR UNIT (MUA-1) SHUTS DOWN AND MOTORIZED AIR DAMPER <br />CLOSES. RELIEF VENT (RV-1)MOTORIZED DDAMPER CLOSES. <br />4, KITCHEN SUPPLY FAN (KSF-1) SHUTS DOWN. <br />5. KITCHEN EXHAUST FAN (KEF/1) REMAINS ON. UNIT SHALL SHUT DOWN VIA <br />EMERGENCY CUT-OUT SWITCH IN KITCHEN, <br />6. SMOKE REMOVAL FANS (SEF-1 AND SEF-2) MOTORIZED DAMPERS OPEN. <br />PROVIDE END SWITCH TO INDICATE DAMPER OPEN POSITION FOR SMOKE <br />FAN START. <br />7. SMOKE REMOVAL FANS (SEF-1 AND SEF-2) ARE ACTIVATED. SMOKE <br />REMOVAL FANS SHALL OPERATE UNTILL SHUT DOWN BY THE FIRE <br />DEPARTMENT. <br />8. THE FIRE ALARM PANEL SHALL HAVE A SMOKE OVERRIDE COMMAND TO <br />ACTIVATE THE SMOKE REMOVAL SEQUENCE MANUALLY. THE FIRE ALARM <br />PANEL SHALL DEACTIVATE THE SMOKE REMOVAL SYSTEM AND SET THE <br />HVAC CONTROLS TO NORMAL OPERATION. <br />PROVIDE CONTROLS, RELAYS, SWITCHES, POWER AND ACCESSORIES FOR <br />AN OPERATIONAL SMOKE CONTROL SYSTEM, COORDINATE WITH F.A. <br />CONTRACTOR FOR INTERFACE COMPONENTS. <br />FREDERICK MUSCATELLO, PE <br />FL. PE # 62451 <br />PO Box 941168 <br />MAITLAND, FL 32794-1168 <br />PH. 407-748-4348 <br />EMAIL: frecIftmengineering.com <br />t <br />U <br />V) <br />z <br />0 <br />V) <br />5 <br />w <br />Irf <br />0 <br />z <br />o <br />P4 <br />o <br />,2 <br />O <br />O <br />� <br />A <br />A <br />U <br />� <br />� <br />O <br />N <br />c <br />00 <br />oo <br />�D <br />0 <br />I <br />o <br />� <br />w <br />a <br />J <br />U <br />le <br />U <br />•• <br />w <br />J <br />0 <br />W <br />Q <br />W <br />N <br />A��18. <br />drawn by: <br />00 <br />dfte: �'S, tDA <br />checked by: <br />z9! <br />Qx <br />sca <br />pproved by: <br />sheet no. <br />`f$ <br />Ml m3m <br />