GENERAL NOTES
<br />1 . ALL INSTALLATIONS AND EQUIPMENT SHALL BE IN STRICT ACCORDANCE WITF
<br />ALL APPLICABLE STATUTES, CODES AND REGULATIONS OF THE GOVERNMENTAL
<br />BODIES HAVING JURISDICTION. THIS SET OF PLANS IS DESIGNED TO BE IN
<br />ACCORDANCE WITH FLORIDA PLUMBING CODE.
<br />2. SEE ARCHITECTURAL DRAWINGS FOR EXACT LOCATIONS OF PLUMBING FIXTURE
<br />MOUNTING HEIGHTS, AND DIMENSIONS.
<br />3. REFER TO ARCHITECTURAL PLANS FOR FIRE RATED FLOOR AND WALL
<br />PENETRATION DETAILS.
<br />4. CONTRACTOR SHALL COORDINATE ALL WORK WITH OTHER TRADES.
<br />5. VALVES AND FITTINGS SHALL BE OF SAME SIZE OF LINE ON WHICH THEY ARE
<br />LOCATED, UNLESS OTHERWISE INDICATED ON DRAWINGS.
<br />6. CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING FIRE RATING AND
<br />WEATHERPROOFING INTEGRITY OF ALL PIPING AND PENETRATIONS. ALL
<br />PENETRATION FOR ALL PIPING THRU FLOOR SLAB SHALL BE WATERPROOFED.
<br />7. CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALL NECESSARY
<br />SUPPORTING DEVICES FOR ALL FIXTURES INCLUDED IN CONTRACT OR HEREIN
<br />SPECIFIED OR OTHERWISE.
<br />8. ROUTE ALL PIPING CONCEALED ABOVE CEILINGS, WITHIN WALLS, OR IN
<br />CHASES. PIPING EXPOSED SHALL BE SLOPED AND PAINTED TO MATCH
<br />ARCHITECTURAL FINISHES. PIPING IN MECHANICAL ROOMS MAY BE EXPOSED.
<br />9. CONTRACTOR SHALL INSTALL DIELECTRIC UNIONS AT CONNECTIONS OF
<br />DISSIMILAR METALS.
<br />10. CONTRACTOR SHALL ROUGH -IN ALL WASTES AND SUPPLIES TO SPECIAL
<br />EQUIPMENT ACCORDING TO MANUFACTURER'S SHOP DRAWINGS AND MAKE
<br />FINAL CONNECTIONS. ALL SUPPLIES SHALL BE VALVED. INSTALL VACUUM
<br />BREAKERS WHERE REQUIRED BY CODE.
<br />11. CONTRACTOR SHALL SUBMIT SHOP DRAWINGS (INCLUDING PIPE ROUTING AND
<br />EQUIPMENT LOCATIONS) TO ARCHITECT/ENGINEER FOR REVIEW AND APPROVAL
<br />PRIOR TO THE INSTALLATION OR PURCHASING OF ANY PIPING AND/OR
<br />EQUIPMENT.
<br />12. CONTRACTOR SHALL FIELD VERIFY ALL GIVEN MEASUREMENTS PRIOR TO LAYING
<br />AND CONNECTING ALL SANITARY AND WASTE PIPING AND NOTIFY ARCHITECT OF
<br />ANY DISCREPANCIES.
<br />13. ALL SANITARY PIPING OVER 2" IN DIAMETER SHALL HAVE A 1/8" PER FOOT
<br />AND ALL SANITARY PIPING 2" OR LESS IN DIAMETER SHALL HAVE A 1/4- PER
<br />FOOT SLOPE UNLESS OTHERWISE NOTED.
<br />14. ALL DRAINAGE PIPING SHALL BE MARKED WITH THE SEAL OF APPROVAL OF
<br />THE NATIONAL SANITATION FOUNDATION.
<br />15. ALL FLOOR DRAINS SHALL BE PROVIDED WITH TRAP PRIMER VALVE AND
<br />FITTINGS UNLESS NOTED OTHERWISE.
<br />16. CONTRACTOR SHALL VERIFY INVERT ELEVATIONS OF SEWERS TO WHICH NEW
<br />SEWER LINES ARE TO BE CONNECTED BEFORE INSTALLATION OF NEW SEWER
<br />LINE.
<br />17. INSTALL WATER HAMMER SHOCK ARRESTORS AT EACH FIXTURE AND BATTERY
<br />OF FIXTURES. ARRESTORS SHALL BE FACTORY -FABRICATED. INSTALL
<br />ARRESTORS AND SIZE PER PLUMBING AND DRAINAGE INSTITUTE STANDARD
<br />P.D.I. WH-2011. ACCEPTABLE MANUFACTURERS - SIOUX CHIEF, PRECISION
<br />PLUMBING PRODUCTS INC., FOR 1-11 F.U.'S PROVIDE PDI-A, 12-32 F.U.'S
<br />PDI-B, 33-60 F.U.'S PDI-C, 61-113 PDI-D.
<br />18. AIR CHAMBERS SHALL NOT BE CONSIDERED AN EQUAL TO WATER ARRESTORS
<br />AS SPECIFIED.
<br />19. PROVIDE ACCESS PANELS TO ALL VALVES WITHIN CHASES OR ABOVE
<br />NON -ACCESSIBLE CEILINGS. REFER TO ARCHITECTURAL DRAWINGS FOR CEILING
<br />TYPES.
<br />20. PROVIDE REDUCED PRESSURE BACKIFLOW PREVENTERS FOR DOMESTIC WArER
<br />SUPPLIES AS REQUIRED BY LOCAL WATER PURVEYORS.
<br />21. PRESSURE REDUCING VALVES SHALL BE INSTALLED ON BRANCH LINES
<br />AND/OR MAINS SERVING FIXTURES AND/OR EQUIPMENT, WHEN THE PRESSURE
<br />IN THE LINE EXCEEDS 80 P.S.I. IT IS RECOMMENDED THAT A VELOCITY
<br />BETWEEN 5 AND 8 PER SECOND BE MAINTAINED.
<br />22. PROVIDE CLEAN OUTS AS REQUIRED BY CODE AND AHJ.
<br />ABBREVIATIONS
<br />AD
<br />ACCESS DOOR
<br />HD
<br />HEAD
<br />AFF
<br />ABOVE FINISHED FLOOR
<br />HW
<br />HOT WATER
<br />APPROX
<br />APPROXIMATELY
<br />HR
<br />HOUR
<br />ARCH
<br />ARCHITECTURAL
<br />INV
<br />INVERT ELEVATION
<br />AUTO
<br />AUTOMATIC
<br />LBS
<br />POUNDS
<br />BLDG
<br />BUILDING
<br />MIN
<br />MINIMUM
<br />CD
<br />CONDENSATE DRAIN
<br />NC
<br />NORMALLY CLOSED
<br />CLG
<br />CEILING
<br />NIC
<br />NOT IN CONTRACT
<br />CO
<br />CLEAN -OUT
<br />NO
<br />NORMALLY OPEN
<br />COND
<br />CONDENSATE
<br />NTS
<br />NOT TO SCALE
<br />CONT
<br />CONTINUATION
<br />PSI
<br />POUNDS PER SQUARE INCH
<br />CMU
<br />CONCRETE MASONRY UNIT
<br />PVC
<br />POLYVINYL CHLORIDE
<br />CW
<br />COLD WATER (CITY)
<br />R
<br />RISE
<br />EL
<br />ELEVATION
<br />REQ'D
<br />REQUIRED
<br />ELEC
<br />ELECTRIC
<br />RM
<br />ROOM
<br />-F
<br />DEGREES FAHRENHEIT
<br />SAN
<br />SANITARY
<br />ECO
<br />EXTERIOR CLEANOUT
<br />SPEC
<br />SPECIFICATION
<br />FCO
<br />FLOOR CLEANOUT
<br />TEMP
<br />TEMPERATURE
<br />FD
<br />FLOOR DRAIN
<br />TYP
<br />TYPICAL
<br />GAL
<br />GALLONS
<br />V
<br />VENT LINE
<br />GPH
<br />GALLONS PER HOUR
<br />VTR
<br />VENT THRU ROOF
<br />GPM
<br />GALLONS PER MINUTE
<br />W/
<br />WITH
<br />HB
<br />HOSE BIBB
<br />WCO
<br />WALL CLEANOUT
<br />PLUMBING LEGEND
<br />COLD WATER SUPPLY
<br />EQUIPMENT
<br />HOT WATER SUPPLY
<br />HOT WATER RETURN
<br />SAN- SANITARY
<br />PLUMBING SPECIFICATIONS
<br />PART 1 GENERAL
<br />1.1 SECTION INCLUDES
<br />A. GENERAL PROVISIONS SPECIFICALLY APPLICABLE TO DIVISION 15 SECTIONS,
<br />IN ADDITION TO DIVISION 1 - GENERAL REQUIREMENTS.
<br />1.2 SCOPE
<br />A. THE WORK SHALL INCLUDE THE PROVISIONS OF SYSTEMS,
<br />EQUIPMENT AND MATERIALS SPECIFIED IN THIS DIVISION AND AS
<br />CALLED FOR ON THE DRAWINGS. WORK SHALL ALSO INCLUDE
<br />SUPERVISION, OPERATION, METHODS AND LABOR FOR THE
<br />FABRICATION, START-UP AND TESTS FOR A COMPLETE OPERATIONAL
<br />PLUMBING INSTALLATION.
<br />B. DRAWINGS FOR THE WORK ARE DIAGRAMMATIC IN NATURE AND ARE
<br />INTENDED TO CONVEY THE SCOPE OF THE INSTALLATION AND TO INDICATE
<br />THE GENERAL ARRANGEMENT AND LOCATIONS OF THE WORK. BECAUSE OF
<br />THE SCALE OF THE DRAWINGS, CERTAIN BASIC ITEMS SUCH AS PIPE
<br />FITTINGS, ACCESS PANELS, AND SLEEVES MAY NOT BE SHOWN. THIS
<br />CONTRACTOR SHALL BE RESPONSIBLE FOR SELECTING THE EQUIPMENT TO
<br />FIT THE SPACE PROVIDED. THE LOCATION AND SIZES FOR PIPE FITTINGS,
<br />SLEEVES, INSERTS, FIRE AND/OR SMOKE DAMPERS, AND OTHER BASIC
<br />ITEMS REQUIRED BY CODE AND OTHER SECTIONS SHALL BE COORDINATED
<br />AND INCLUDED FOR THE PROPER INSTALLAMON OF THE WORK.
<br />C. EQUIPMENT SPECIFICATIONS MAY NOT DEAL INDIVIDUALLY WITH MINUTE
<br />ITEMS REQUIRED SUCH AS COMPONENTS, PARTS, CONTROLS AND DEVICES
<br />WHICH MAY BE REQUIRED TO PRODUCE THE EQUIPMENT PERFORMANCE
<br />SPECIFIED OR AS REQUIRED TO MEET THE EQUIPMENT WARRANTIES. WHERE
<br />SUCH ITEMS ARE REQUIRED, THEY SHALL BE INCLUDED BY THE INSTALLER
<br />OF THE EQUIPMENT, WHETHER OR NOT SPECIFICALLY INDICATED IN THE
<br />CONTRACT DOCUMENTS WITH NO ADDITIONAL COST INCURRED.
<br />D. WHERE NOTED ON THE DRAWINGS OR INDICATED IN OTHER SECTIONS OF
<br />THE SPECIFICATION, THE CONTRACTOR FOR THIS DIVISION SHALL INSTALL
<br />PLUMBING EQUIPMENT FURNISHED BY OTHERS, AND SHALL MAKE ALL
<br />FINAL CONNECTIONS. CONTRACTOR SHALL INSTALL EQUIPMENT AND
<br />SYSTEMS IN STRICT ACCORDANCE WITH MANUFACTURERS
<br />RECOMMENDATIONS.
<br />E. COORDINATE WITH ALL TRADES IN SUBMITTAL OF SHOP DRAWINGS. TIGHT
<br />SPACE CONDITIONS SHALL BE DETAILED TO THE SATISFACTION OF ALL
<br />TRADES, SUBJECT TO THE REVIEW AND FINAL ACCEPTANCE OF THE
<br />ARCHITECT/ENGI NEER. IN THE EVENT THAT THE CONTRACTOR INSTALLS HIS
<br />WORK BEFORE COORDINATING WITH OTHER TRADES OR SO AS TO CAUSE
<br />ANY INTERFERENCE WITH THE WORK OF THE OTHER TRADES THIS
<br />CONTRACTOR SHALL MAKE ALL REQUIRED CHANGES TO CORRECT THE
<br />CONDITION AT NO ADDITIONAL COST TO THE PROJECT.
<br />F. CONTRACTOR SHALL VERIFY ALL EQUIPMENT CONNECTION SIZES PRIOR TO
<br />INSTALLATION OF ANY SYSTEMS. THIS CONTRACTOR SHALL ADJUST PIPING
<br />SYSTEM SIZES AS REQUIRED TO MATCH EQUIPMENT CONNECTIONS. UTILIZE
<br />REDUCERS WHERE EQUIPMENT CONNEC11ONS ARE SMALLER THAN PIPE
<br />SIZES INDICATED ON PLANS, NO PIPING SHALL BE DECREASED IN SIZE (IN
<br />THE DIRECTION OF FLOW).
<br />G. EXAMINATION OF BIDDING DOCUMENTS:
<br />1. EACH BIDDER SHALL EXAMINE THE BIDDING DOCUMENTS CAREFULLY
<br />AND NOT LATER THAN TEN (110) DAYS PRIOR TO THE DATE FOR
<br />RECEIPT OF BIDS, SHALL MAKE WRITTEN REQUEST TO THE ENGINEER
<br />FOR INTERPRETAT10N OR CORRECTION OF ANY AMBIGUITY,
<br />INCONSISTENCY OR ERROR THEREIN. ANY INTERPRETATION OR
<br />CORRECTION WILL BE ISSUED AS AN ADDENDUM BY THE ENGINEER.
<br />ONLY A WRITTEN INTERPRETATION OR CORRECTION TO BID
<br />DOCUMENTS BY ADDENDUM SHALL BE BINDING. NO BIDDER SHALL
<br />RELY UPON ANY INTERPRETATION OR CORRECTION GIVEN BY ANY
<br />OTHER METHOD.
<br />H. SUBSTITUTIONS:
<br />1. EXCEPT AS PROVIDED BELOW, EACH BIDDER REPRESENTS THAT HIS
<br />BID IS BASED UPON THE MATERIALS AND EQUIPMENT DESCRIBED IN
<br />THE BIDDING DOCUMENTS.
<br />2. NO SUBSTITUTIONS FOR OTHER MATERIALS AND EQUIPMENT WILL BE
<br />CONSIDERED UNLESS WRITTEN REQUEST HAS BEEN SUBMITTED TO
<br />THE ENGINEER FOR APPROVAL AT LEAST TEN (10) DAYS PRIOR TO
<br />THE DATE FOR RECEIPT OF BIDS. EACH SUCH REQUEST SHALL
<br />INCLUDE A COMPLETE DESCRIPTION OF THE PROPOSED SUBSTITUTE,
<br />THE NAME OF THE MATERIAL OR EQUIPMENT FOR WHICH IT IS TO
<br />BE SUBSTITUTED, DRAWINGS, CUTS, PERFORMANCE AND TEST DATA
<br />OR INFORMATION NECESSARY FOR A COMPLETE EVALUATION.
<br />3. IF THE ENGINEER APPROVES ANY PROPOSED SUBSTITUTION, SUCH
<br />APPROVAL WILL BE ISSUED AS AN ADDENDUM FORWARDED TO ALL
<br />PARTICIPATING BIDDERS.
<br />4. IF ANY BIDDER IS UNABLE TO PROCURE WRITTEN APPROVAL OF ANY
<br />SUBSTITUTION FROM THE ENGINEER PRIOR TO THE OPENING OF
<br />BIDS, THEN HE SHALL BASE HIS BID ON ITEMS AND SYSTEMS AS
<br />SPECIFIED IN BID DOCUMENTS.
<br />5. SUBSTITUTIONS REQUESTED ON THE BID PROPOSAL FORM WHICH
<br />ARE PRIOR APPROVED BY THE ENGINEER WILL BE INCORPORATED
<br />INTO THE CONTRACT WITH THE SUCCESSFUL BIDDER.
<br />6. REQUESTS FOR ANY SUBSTITUTIONS NOT SUBMITTED AND APPROVED
<br />IN ACCORDANCE WITH THE ABOVE INSTRUCTIONS WILL BE DENIED BY
<br />THE ENGINEER.
<br />1.3 REGULATORY REQUIREMENTS
<br />A. ALL INSTALLATIONS AND EQUIPMENT SHALL BE IN STRICT ACCORDANCE
<br />WITH ALL APPLICABLE STATUTES, CODES AND REGULATIONS OF THE
<br />GOVERNMENTAL BODIES HAVING JURISDICTION.
<br />1.4 CUTTING AND PATCHING
<br />A. SUBMIT WRITTEN REQUEST IN ADVANCE OF CUTTING OR ALTERING
<br />ELEMENTS.
<br />A BALL VALVE
<br />-fZ4- CHECK VALVE, HORIZONTAL SWING
<br />CAPPED LINE
<br />HOSE BIBB
<br />- - - SAN- - - SANITARY UNDERGROUND
<br />------------ VENT
<br />DIRECTION OF FLOW IN PIPE
<br />0 PIPE UP
<br />PIPE DOWN
<br />B. EMPLOY SKILLED AND EXPERIENCED INSTALLER TO PERFORM CUTTING
<br />AND PATCHING WHICH EFFECT:
<br />1. INTEGRITY OF WEATHER PROOFING MATERIALS.
<br />2. EFFICIENCY, MAINTENANCE, OR SAFETY OF ELEMENT.
<br />3. VISUAL QUALITIES OF SIGHT.
<br />4. WORK OF OWNER OR SEPERATE CONTRACTOR.
<br />C. NO STRUCTURAL ELEMENTS TO BE CUT WITHOUT PRIOR APPROVAL OF THE
<br />ARCHITECT.
<br />PART 2 PRODUCTS
<br />2.1 PIPE HANGERS AND SUPPORTS
<br />A. MANUFACTURERS:
<br />1. B-LINE
<br />2. OTHER ACCEPTABLE MANUFACTURERS OFFERING EQUIVALENT
<br />PRODUCTS.
<br />A) MICHIGAN HANGER.
<br />B) PHD.
<br />2.2 HOT WATER WATER PIPING INSULATION
<br />A. MANUFACTURERS:
<br />1. ARMACELL
<br />2. AEROCEL
<br />B. FLEXIBLE CLOSED CELL ELASTOMERIC THERMAL INSULATION TUBULAR FORM.
<br />ASTM C 534 TYPE 1 GRADE 1. 25/50 FLAME SPREAD & SMOKE INDEX.
<br />C. INSULATION THICKNESS 3/4-.
<br />2.3 SANITARY & STORM SEWER PIPING, ABOVE AND BELOW GRADE:
<br />A. PVC: ASTM D2665 SCHEDULE 40 PVC PIPING.
<br />1. FITTINGS: ASTM D2665 SCHEDULE 40 PVC DWV FITTINGS.
<br />2. JOINTS: ASTM D2564 SOLVENT CEMENT. JOINTS SHALL BE
<br />INSTALLED IN ACCORDANCE WITH ASTM D2855.
<br />2.4 WATER PIPING, ABOVE GRADE
<br />A. CPVC PIPING & FITTINGS: ASTM D1784 PIPE COMPOUND CELL CLASS
<br />24448.
<br />1. JOINTS: ASTM F493 SOCKET TYPE WITH SOLVENT CEMENT ASTM F402
<br />NSF INTERNATIONAL APPROVED MFG. COMPATIBLE.
<br />2. FLOWGUARD GOLD CPVC PIPE AS MFG. BY NOVEON INC.
<br />PART 3 INSTALLATION
<br />A. INSTALL IN STRICT ACCORDANCE WITH MANUFACTURER'S
<br />INSTRUCTIONS.
<br />B. PROVIDE NON -CONDUCTING DIELECTRIC CONNECTIONS WHEREVER
<br />JOINTING DISSIMILAR METALS.
<br />C. ROUTE PIPING IN ORDERLY MANNER AND MAINTAIN GRADIENT.
<br />D. INSTALL PIPING TO CONSERVE BUILDING SPACE AND NOT
<br />INTERFERE WITH USE OF SPACE.
<br />E. GROUP PIPING WHENEVER PRACTICAL AT COMMON ELEVATIONS.
<br />F. INSTALL PIPING TO ALLOW FOR EXPANSION AND CONTRACTION
<br />WITHOUT STRESSING PIPE, JOINTS, OR CONNECTED EQUIPMENT.
<br />G. PROVIDE CLEARANCE FOR INSTALLATION OF INSULATION AND ACCESS TO
<br />VALVES AND FITTINGS.
<br />H. PROVIDE ACCESS WHERE VALVES AND FITTINGS ARE NOT EXPOSED.
<br />COORDINATE SIZE AND LOCATION OF ACCESS DOORS WITH APPROPRIATE
<br />ARCHITECTURAL SECTION.
<br />1. ESTABLISH ELEVATIONS OF BURIED PIPING OUTSIDE THE BUILDING TO
<br />ENSURE PROPER SLOPE AND COVER.
<br />J. ESTABLISH ELEVATIONS OF EXISTING BURIED PIPING FOR CONNECTION TO
<br />NEW WORK TO ENSURE PROPER SLOPE AND COVER.
<br />K. WHERE PIPE SUPPORT MEMBERS ARE WELDED TO STRUCTURAL BUILDING
<br />FRAMING, SCRAPE, BRUSH CLEAN, AND APPLY ONE COAT OF ZINC RICH
<br />PRIMER TO WELDING.
<br />L. EXTEND CLEANOUTS TO FINISHED FLOOR OR WALL SURFACE. LUBRICATE
<br />THREADED CLEANOUT PLUGS WITH MIXTURE OF GRAPHITE AND LINSEED
<br />OIL ENSURE CLEARANCE AT CLEANOUT FOR RODDING OF DRAINAGE
<br />SYSTEM.
<br />M. INSTALL WATER HAMMER SHOCK ARRESTORS AT EACH FIXTURE OR BATTERY
<br />OF FIXTURES WHERE REQUIRED. ARRESTORS SHALL BE FACTORY
<br />FABRICATED. INSTALL ARRESTORS AND SIZE PER PLUMBING AND DRAINAGE
<br />INSTITUTE STANDARD P.D.I. WH-201. ACCEPTABLE MANUFACTURERS ZURN,
<br />JOSAM, SIOUX CHIEF. PPP INC. FOR 1-11 FU'S PROVIDE PDI-A, FOR
<br />12-32 FU'S PDI-B, 33-60 FU'S PDI-C, 61-113 FU'S PDI-D.
<br />0- FLOOR CLEANOUT
<br />0 2-WAY EXTERIOR CLEANOUT
<br />--i I WALL CLEANOUT
<br />SHOCK ABSORBER
<br />PLUMBING SPECIALTIES SCHEDULE
<br />FIXTURE
<br />FIXTURE TYPE
<br />WASTE
<br />TRAP
<br />VENT
<br />C.W.
<br />H.W.
<br />MANUFACTURER
<br />DESCRIPTION
<br />NO.
<br />CONN.
<br />CONN.
<br />CONN.
<br />CONN.
<br />/ MODEL #
<br />WC-11
<br />WATER CLOSET
<br />3w
<br />INTEG.
<br />2"
<br />in
<br />-
<br />AMERICAN STANDARD
<br />MADERA 15- RIM HEIGHT, 1.6 GPF, TOP SPUD FLOOR MOUNT VITREOUS CHINA, SIPHON
<br />2234001.020
<br />JET, 6047161.002 MANUAL FLUSH VALVE, BEMIS 1955SSC STATITE SEAT
<br />WC-2
<br />WATER CLOSET
<br />3"
<br />INTEG.
<br />2"
<br />1"
<br />-
<br />AMERICAN STANDARD
<br />MADERA 16 1/2" RIM HEIGHT, 1.6 GPF, TOP SPUD, FLOOR MOUNT VITREOUS CHINA,
<br />ADA
<br />3043001.020
<br />SIPHON JET, AMERICAN STANDARD 6047161.002 MANUAL FLUSH VALVE, BEMIS 1955SSC
<br />STA-TITE SEAT
<br />UR-1
<br />URINAL
<br />2"
<br />2"
<br />1-1/2-
<br />3/4-
<br />-
<br />AMERICAN STANDARD
<br />LIP 17* AFF. VITREOUS CHINA, WHITE, WALL HUNG WASHOUT FLUSH URINAL COMPLETE
<br />ADA
<br />6561.017
<br />WITH 3/4- TOP SPUD AND WALL HANGERS. 'SLOAN' ROYAL FLUSH VALVE #186-0.5
<br />(0.5 GALLON PER FLUSH). 'ZURN' Z1221 CAST IRON, FLOOR MOUNTED CARRIER.
<br />L-1
<br />LAVATORY
<br />1-1/2-
<br />1-1/4-
<br />1-1/2-
<br />1/2-
<br />1/2-
<br />AMERICAN STANDARD
<br />COUNTERTOP TYPE, OVAL, SELF -RIMMING, VITREOUS CHINA LAVATORY WITH CONCEALED
<br />2 HANDLE FAUCET
<br />0419.444
<br />FRONT OVERFLOW. FAUCET: 'BANNER' #311-1.5, 4" CENTERS, METAL TWO -LEVER
<br />HANDLES. POP UP STRAINER WITH TAILPIECE, C.P. BRASS P-TRAP WITH WALL ARM &
<br />ESCUTCHEONS. 'BRASSCRAFT' ANGLE VALVE SUPPLY RISERS W/LOOSE KEY STOPS.
<br />INSULATE P-TRAP AND SUPPLIES WITH 'TRUEBRO' INSULATION KIT. PROVIDE LAWLER
<br />1070 POINT OF USE MIXING VALVE.
<br />L-2
<br />LAVATORY
<br />1-1/2-
<br />1-1/4-
<br />1-1/2-
<br />1/2-
<br />1/2-
<br />AMERICAN STANDARD
<br />LUCERNE 20" x 18" WALL HUNG, VITREOUS CHINA WITH INTEGRAL BACKSPLASH.
<br />ADA
<br />0355.012
<br />'BANNER' #501, 4" CENTERS, C.P. METAL, SINGLE -LEVER HANDLE FAUCET. POP-UP
<br />SINGLE LEVER FAUCET
<br />STRAINER WITH TAILPIECE, C.P. BRASS P-TRAP WITH WALL ARM & ESCUTCHEONS.
<br />'BRASSCRAFT` ANGLE VALVE SUPPLY RISERS W/LOOSE KEY STOPS. INSULATE P-TRAP
<br />AND SUPPLIES WITH 'TRUEBRO' INSULATION KIT. 'ZURN' 1231 CAST IRON FLOOR
<br />MOUNTED CARRIER FITTING WITH CONCEALED ARMS. PROVIDE LAWLER 1070 POINT OF
<br />USE MIXING VALVE.
<br />SH-1
<br />SHOWER
<br />2*
<br />2"
<br />1-1/2-
<br />1/2-
<br />1/2-
<br />SYMMONS
<br />SHOWER ENCLOSURE SPECIFIED ON ARCHITECTURAL DRAWINGS. TEMPTROL PRESSURE
<br />C-96-300-X
<br />BALANCING VALVE WITH SINGLE BLADE LEVER HANDLE, INTEGRAL VOLUME CONTROL, AND
<br />ZURN FD2210
<br />ADJUSTABLE STOP SCREW TO LIMIT HAND TURN. ADJUSTABLE SHOWER HEAD, ARM AND
<br />FLANGE. ADJUSTABLE PVC FLOOR DRAIN WITH NICKEL CHROME PLATED STRAINER.
<br />SH-2
<br />SHOWER
<br />2*
<br />2"
<br />1-1/2-
<br />1/2-
<br />1/2-
<br />SYMMONS
<br />SHOWEROFF SHOWER LIMITER VALVE WITH INTEGRAL STOP, 1/2- IPS BACK CONNECTION
<br />OUTDOOR INSTALLA11ON
<br />3-310-R
<br />AND ESCUTCHEON WITH REAR MOUNTING. FRE-FLO INSTITUTIONAL SHOWER HEAD WITH
<br />ADJUSTABLE SPRAY. BACK PLATE AND THRU BOLTS FOR EXTRA THICK WALL. ALL
<br />MOUNTING FASTENERS FOR VALVE AND HEAD ARE VANDAL RESISTANT HEX SOCKET TYPE.
<br />PROVIDE 1.5 GPM FLOW RESTRICTOR.
<br />EWC-1
<br />ELECTRIC WATER COOLER
<br />2"
<br />1-1/2-
<br />1-1/2-
<br />1/2-
<br />ELKAY
<br />LOWER BUBBLER 36"AFF; UPPER 417AFF. WALL/FLUSH MOUNTED CAPACITY TO DELIVER
<br />DUAL LEVEL
<br />EZSTL8C
<br />8 GPH OF 50*F. WATER WITH INLET TEMP. OF 80*F AND ROOM TEMP. OF 90*F.,
<br />STAINLESS STEEL BASIN & PEWTER VINYL W/ 1/5 HP.,120V, 60 CYCLE, 1 PH. W/
<br />OVERLOAD PROTECTION 1 1/2- P-TRAP STOP VALVE, CORD & PLUG. ZURN #Z1225-BL
<br />CAST IRON FLOOR MOUNTED CARRIER FITTING WITH BEARING PLATE.
<br />MS_ 1
<br />MOP SINK
<br />SO
<br />3"
<br />1-1/2-
<br />3/4-
<br />3/4'
<br />FIAT
<br />24"x24"xlO* HIGH MOLDED STONE RECEPTOR, W/ FIAT #830-AA FAUCET MOUNTED IN
<br />MSB 2424
<br />WALL ABOVE FIXTURE. COMPLETE WITH VACUUM BREAKER, HOSE THREAD OUTLET &
<br />BUCKET HOOK, INTEGRAL STOPS AND MOUNTING BRACKET. PROVIDE COMBINATION
<br />STAINLESS STEEL DOME STRAINER AND LINT BASKET, 3-CAULKED OUTLET, CAULK WITH
<br />SILICONE SEALANT AS REQUIRED.
<br />HB-1
<br />HOSE BIBB
<br />3/4"
<br />-
<br />WOODFORD
<br />HOSE CONNECTION FOR NON-FREEZING AREAS WITH VACUUM BREAKER ENCLOSED IN A
<br />B24
<br />FLUSH MOUNTED WALL BOX.
<br />HB-2
<br />HOSE BIBB
<br />3/4-
<br />-
<br />WOODFORD
<br />HOSE CONNECTION FOR NON-FREEZING AREAS WITH VACUUM BREAKER.
<br />ANTI -SIPHON
<br />24
<br />SA
<br />SHOCK ARRESTOR
<br />-
<br />-
<br />SIOUX CHIEF
<br />SIZE PER MANUFACTURER'S RECOMMENDATIONS. PD1 CERTIFIED.
<br />650 SERIES
<br />TPV_i
<br />TRAP PRIMER VALVE
<br />1/2-
<br />-
<br />PRECISION PLUMBING
<br />CORROSION RESISTAN BRASS TRAP PRIMER, 1/2" COLD WATER INLET AUTOMATICALLY
<br />PRODUCTS
<br />OPERATED BY PRESSURE DROP OF 10 PSIG.
<br />PR-500
<br />AAV- 1
<br />AIR ADMITTANCE VALVE
<br />1-1/2-
<br />-
<br />-
<br />STUDOR
<br />AUTOMATIC AIR ADMITTANCE VALVE WITH VENTED ACCESS PANEL. LOCATE FULLY
<br />TEC-VENT
<br />ACCESSIBLE.
<br />FD-11
<br />FLOOR DRAIN
<br />SEE PLAN
<br />1/2
<br />-
<br />ZURN
<br />DURA-COATED CAST IRON BODY WITH BOTTOM OUTLET, COMBINATION INVERTIBLE
<br />STANDARD ROUND
<br />ZN411513-CP
<br />MEMBRANE CLAMP AND ADJUSTABLE COLLAR WITH SEEPAGE SLOTS AND TYPE 'B'
<br />POLISHED NICKEL BRONZE STRAINER. PROVIDE 1/2" COLD WATER TRAP PRIMER
<br />CONNECTION AND CHROME PLATED BRONZE TOP.
<br />FCO
<br />FINISHED FLOOR CLEANOUT
<br />SEE PLAN
<br />-
<br />-
<br />ZURN
<br />"LEVEL-TROL" ADJUSTABLE FINISHED FLOOR CLEANOUT, DURA-COATED CAST IRON BODY
<br />Z1400
<br />WITH GAS AND WATERTIGHT ABS TAPERED THREADED PLUG, AND ROUND SCORIATED
<br />SECURED TOP. ADJUST TO FINISHED FLOOR (COORDINATE TOP FINISH WITH ARCHITECT).
<br />WCO
<br />WALL CLEAN -OUT
<br />SEE PLAN
<br />-
<br />-
<br />ZURN
<br />CAST IRON CLEAN -OUT TEE, DURA COATED BODY, GAS AND WATERTIGHT ARS TAPERED
<br />Z1446
<br />THREAD PLUG AND ROUND, SMOOTH STAINLESS STEEL WALL ACCESS COVER WITH
<br />SECURING SCREW.
<br />ECO
<br />EXTERIOR CLEANOUT
<br />SEE PLAN
<br />-
<br />-
<br />-
<br />ZURN
<br />HEAVY TRAFFIC AREA EXTERIOR CLEANOUT WITH ACCESS COVER AND TWO-WAY FITTING.
<br />Z-1400-HD
<br />SEE PLANS FOR PIPE SIZE CONNECTION.
<br />IMB- 1
<br />ICE MAKER BOX
<br />1/2"
<br />-
<br />OATEY
<br />VALVE 24"AFF. HIGH IMPACT PLASTIC BOX W/ DIMENSION OF 9" HIGH x 10 3/4" WIDE.
<br />#38811
<br />PROVIDE 1/2" FIP INLET x 1/4* OD OUTLET COMPRESSION ANGLE VALVE. SUPPLY
<br />CONNECTION SIZE SHALL BE 1/2- OD. COORDINATE ALL VALVE BOX LOCATIONS WITH
<br />ARCHITECT PROIR TO INSTALLATION.
<br />S-2
<br />SINK
<br />2n
<br />1-1/2-
<br />1-1/2-
<br />1/2-
<br />1/2-
<br />ELKAY
<br />LUSTERTONE ADA COMPLIANT 33x22 DOUBLE COMPARTMENT SINK, 6" DEEP, 18 GAUGE,
<br />2 COMPARTMENT
<br />LRAD33226
<br />3HOLE, TYPE 304 SS, SELF RIMMING, T&S B2731 SINGLE CONTROL LEVER HANDLE,
<br />DAYTON D1125 BASKET STRAINER, TAILPIECE, P-TRAP & CONTINUOUS DRAIN FITTING.
<br />PROVIDE ANGLE STOPS, SUPPLIES & ESCUTCHEONS. GARBAGE DISPOSAL: ISE BADGER
<br />5XP 3/4 H.P. QUIET DURA-DRIVE INDUCTION MOTOR.
<br />HD- 1
<br />HUB DRAIN
<br />SEE PLAN
<br />-
<br />WATTS
<br />EPDXY -COATED CAST IRON BODY WITH BOTTOM OUTLET, COMBINATION INVERTIBLE
<br />BACKWATER VALVE
<br />FD100-A7-Gl-8
<br />MEMBRANE CLAMP AND ADUSTABLE COLLAR WITH SEEPAGE SLOTS AND 7" TYPE "A"
<br />NICKEL BRONZE STRAINER, OVAL FUNNEL, BACKWATER VALVE
<br />DW
<br />DISHWASHER
<br />1/2*
<br />1/2-
<br />BY OTHERS
<br />REFER TO ARCHITECTURAL DRAWINGS FOR DETAILS.
<br />BFP- 1
<br />BACKIFLOW PREVETER
<br />-
<br />1-1/4-
<br />-
<br />WATTS #LFOO7
<br />3/4- REDUCED PRESSURE ZONE ASSEMBLY W/ (2) ISOLATION VALVES AND (2) BRONZE
<br />BODY TEST COCKS. CAST IRON BODY WITH BRONZE SEATS.
<br />NOTE: ALL PLUMBING FIXTURES SHALL BE SUPPLIED WITH WATTS "FLOODSAFE" AUTO -SHUT OFF CONNECTOR TYPE SUPPLY RISERS WITH BRAIDED STAINLESS STEEL CONNECTORS. THIS SHALL
<br />INCLUDE ALL FAUCETS, TOILETS, WASHING MACHINES, DISHWASHERS & ICE MAKERS. PROVIDE FULLY ACCESSIBLE SHOCK ARRESTORS ON SUPPLIES TO WASHING MACHINES, ICE MAKERS AND
<br />DISHWASHERS.
<br />RECIRCULATING PUMP SCHEDULE
<br />UNIT #
<br />TYPE
<br />GPM
<br />HEA?0FT.
<br />H
<br />CONN. SIZE
<br />MOTOR DATA
<br />SELECTION BASED ON:
<br />REMARKS
<br />INLET
<br />OUTLET
<br />WATTS
<br />RPM
<br />VOLT
<br />PH.
<br />MANUFACTURER
<br />MODEL
<br />HWRP-1
<br />IN -LINE
<br />5
<br />15
<br />3/4-
<br />3/4-
<br />92
<br />2940
<br />120
<br />1PH
<br />BELL & GOSSETT
<br />NBF-18S
<br />PROVIDE AQUASTAT
<br />ELECTRIC WATER HEATER SCHEDULE
<br />FIRST HOUR
<br />VOLTAGE/
<br />APPROX.
<br />MANUFACTURER
<br />UNIT #
<br />LOCATION
<br />GALLONS
<br />KW
<br />RATE
<br />PHASE
<br />DIMENSIONS
<br />SHIP WT.
<br />NOTES
<br />(LBS)
<br />MFG
<br />MODEL #
<br />EWH- 1
<br />JAN 108
<br />30
<br />4.5
<br />48
<br />208V - 10
<br />47-1/2" H x 119-1/4"0
<br />92
<br />RHEEM
<br />PROE30 T2 RH95
<br />SEE BELOW
<br />NOTES:
<br />1. PROVIDE EACH WATER HEATER WITH PROPERLY SIZED WATTS PLT-5 THRU 20 EXPANSION TANK OR WATTS
<br />SERIES 530C CALIBRATED PRESSURE RELIEF VALVE, AND
<br />ALL GAUGES, HEAT TRAPS, THERMOSTATS, THERMO EXPANSION VALVE, TEMPERATURE AND PRESSURE RELIEF VALVE AND SHUT-OFF VALVES AS REQUIRED BY LOCAL
<br />CODES AND MFG'S RECOMMENDATIONS.
<br />2. PROVIDE MINIMUM 2-1/2- DEEP 28 GAUGE ALUMINUM DRAIN PAN.
<br />3. WATER HEATERS, AS SPECIFIED, COMPLY WITH FLORIDA BUILDING CODE. CONTRACTOR SHALL INSTALL PER
<br />MANUFACTURER'S SPECIFICATIONS.
<br />Z
<br />W
<br />0
<br />z
<br />00
<br />w
<br />10
<br />:2
<br />'45
<br />E
<br />ca
<br />z
<br />2
<br />n_
<br />_j
<br />LL
<br />U)
<br />_j
<br />w
<br />N
<br />SHEET INFORMATION
<br />DATE: 10/19/2021
<br />DRAWN BY: AM
<br />PROJECT NO: 20-6001
<br />REVEWED BY: SAS
<br />7 Plan Revisions Date:
<br />06/04/2021 ISSUED FOR PERMIT
<br />1 10/18/2021 OWNER REVISION
<br />Sheet Name
<br />PLUMBING
<br />LEGEND,NOTES
<br />CA# 26308 121270.00 &
<br />AlkINGENUITY ABBREVIATIONS
<br />ENGINEERS,INC. Sheet No.
<br />14pp "PROACTIVE ENGINEERING SOLUTIONS" P0. 1
<br />4798 NEW BROAD ST. SUITE 300 1 ORLANDO, FLORIDA 1407.398.6007
<br />
|