8. ACOUSTICAL CEILINGS. 4 DAYS <br /> 9. ROUGH MECHANICAL 2 DAYS <br /> 10.PAINT RESTROOM/FLOORING 1 DAY <br /> 11.COMPLETE ELECTRICAL/PLUMBING <br /> TRIM OUT. 3 DAYS <br /> 12.COMPLETE MECHANICAL/LOWER SPRINKLER <br /> HEADS. 3 DAYS <br /> 13.COMPLETE VENT THRU ROOF/INSTALL GRAB <br /> BARS/RESTROOM ACCESSORIES. 3 DAYS <br /> 14.CLEAN JOB SITE/HAUL DEBIS. 1 DAY <br /> TOTAL 34 DAYS BASED ON A 5 DAY WEEK. <br /> 2 <br />