Subcontractor recognizes and agrees Ihat as the Project progresses, the Schedule, (including both duration <br /> and sequences of activities shown thereon), may be amended by Contractor to retlect instructions from the <br /> Owner, changes in the Project, ch�nges in construction means or methods,and unanticipated nccurrences <br /> affec:ting progress of the Praject. Subcontractor agrees to comp{y with each and all such amendments to <br /> the Schedule, and to perform the Work in strict accordance with such amendments. At Contractor's <br /> request, and at the times specified in any such rec�uest, Subcontractor shalf submit to Contractor detailed <br /> progress, procurement, performance, manpower, and completion schedules, satisfactory to Contractor. <br /> Subcontractor shall promptly increase its work force, work overtime, work Saturdays, Sundays and <br /> holidays, aN without additional compensation, if. in the opinion of Contractor,such measures are neces�ary <br /> to m�intain proper progress of the Work in accordance with the Schedule. Except as expressly provided in <br /> Sections A(b) and 5 below, Subcontractor waives and disclaims any remedy against Contrartor for any <br /> damages or costs arising from delays, accelerations, interferences, suspensions, oi• changes in the <br /> performance, duration or sequence of Subcontractor's Work. Without hmitation of the fo��egoing, no <br /> premium time will be paid except pursuant to written nuthorization by Cuntractor specifying that prem�um <br /> tirne will be paid,and the amount that will be paid. <br /> 4(b). Delays of tke Work. If Subcontractor is delayed in the commencement, performance, or <br /> completion of the Work Uy• Ch:�nge Orders issued by Contractor in accordance with Sectic7n S below; <br /> extraordin�ry weather conditions that are uncharacteristic for the 1ac11e of the Work and that could not <br /> h�ve been anticipated; unusual and unanticipated delays in transportation; or unavoidable casu�lty loss to, <br /> or destruction of,the Work,then the Schedule described in 4(a)above may be adjusted by Contractor based <br /> on the reasonablc amount of time lost as�result of such occurrence. Otherwise,Subcontractor assumes all <br /> risks of stric� compliance with the Schedule. The �djustment of�he Schedule provided for herein shall be <br /> 5ubcontracror's sole remedy for any and aU interferences, suspensions, and delays. No such adjustment in <br /> the Schedule shall be made unless written notice containing � request therefore is given to Con[ractor <br /> within forty-eight (48) hours atter commencement of the occurrence that cluses such delay, regardless of <br /> whether or not Contractor has actual notice of the delay, �nd provided always that a simillr extension of <br /> time has been allotted to Conh�acror by Owner Contructor shall have no duty, obligation, or liability to <br /> Subcontractor as a result of any delay, interference, suspension,or other event,except to seek an extension <br /> of time from the Owner as provided herein. <br /> 4fcJ. Liqtridate�l Daneages. Subcontractor represents that it hvs s�itisfied itself as ro the extent and <br /> amount of any provision in the Prime Contract impnsing liquidated damages upon Contractor, and <br /> ncknowledges that in the event Subcontrartor fails to comply with the Schedule, and liquidated damages <br /> are imposed by Owner on Contractor, such liquidated damages will constitute one element of the d�m�ges <br /> that Contractor shall be entitled to recover from 5ubcontractor <br /> 5(ci). Changes i�r dte Work. Contractor may at any time, without notice to any surety, direct <br /> changes,additions,and/or deletions in or to Subconhactor's Work,or direct extra wark(all of�he foregoing <br /> being referred to herein as "Change(s)") The Subcontract Price �►nd Schedule shall be adjusted on account <br /> of Changes only as provided in 5{b)-(d} below Otherwise, Subcontractor shall receive no time extension <br /> or additional compens�tion on account of Changes <br /> 5(h). Change Orders. No Change shall result in an adjustment in the Subcontract Price or <br /> Schedule uiiless expressly directed by a Change Order made in strict compliance with this Sf�ction 5(b), <br /> pria� to Subcontractor's commencement of performance of the Change, A Change Order is; (i) a written <br /> order by Contractor, expressly designated as a Change Order, directing a Change in the Work, or (ii) an <br /> oral or wi'itten order (detined to include authorizations, directions, interpretations, or detern�ination) by <br /> Contractor directing a Change in the Work, if, and only if, Subcontractor�ives Contractor written notice <br /> within three(3)calendar days after tirst receiving such order,stating the date,circumstances,and source of <br /> the order, and expressly stating that Subcontr�ctor regards such order as requiring a Change in the Work. <br /> Provided,however, that such nottce by Subcontractor sh�ll not result in a Change Order if the Contractor's <br /> order does not, in fact, require a Change in the Work. No other order by Contractor shall constitute a <br /> Change Order, and Subcontractor shall be entided to no compensation or adjustment in the Schedule on <br /> account of any other order,whether or not it results in a Change. <br /> 5(c). Adjustnte�us i�i Srabcontract Prlce Prior to the issuance of any Change Order,Contractor <br /> may require Subcontractor to furnish promptly a detailed price breakdown showing the difference in value <br /> �3o6-i5-3oo <br /> Page 4 of I;i <br /> Sulxauraa Agrccmcnt(L.ong Fortn) <br /> Rcvised 06/08/10 <br />