Subcontractor recognizes and agrees that as the Project progresses,the Schedule,(including both duration <br /> 1nd sequences of activities shown thereon), may be amended by Contractor to reflect instructions from the <br /> Owner, changes in the Pro,{ec:t,changes in construction means or methods,and unanticipated occurrences <br /> affecting progress of the Project. Subcontractor agrees to comply with each and all such amendments to <br /> the Schedule, and to perform the Work in strict accordance wi[h such amendments. At Contractor:s <br /> request, and at the times specified in any such request, Subcontractor shall submit to Contractor det�iled <br /> progress, procurement, performance, mAnpower, and completion schedules, satisfactory to Contractor. <br /> Subcontractor shaU promptly increase its work force, work overtime, work SaturdAys, Sundays and <br /> holidAys,al1 without additional compensation,if,in the opinioo of Contractor,such measures are necessary <br /> to maintAin proper progress of the Work in accordance with the Schedule. Except as expressiy provided in <br /> Sections 4(b) and 5 below, Subcontractor waives and discl�ims any remedy against Contractor for any <br /> dam�ges or costs arising from delays, accelerations, interferences, suspensions, or changes in the <br /> performance, duration or sequence of Subcontr�ctor's Work. Without limitation of the foregoing, no <br /> premium time wi11 be paid except pursuant to written authorization by Contractor specifying thAt premium <br /> time will be paid,and the amount that will be paid. <br /> 4{G). Delays of tJie Work. If Subcontractor is delayed in the commencement, performance, or <br /> comple[ion of the Work by: Cht�nge Ordets issued by Contractor in accordance with Section 5 below; <br /> exrraordinAry weather conditions thut are uncharacteristic for the locnle of the Work and that could not <br /> h�ve been anticipated; unusual and unanticipated delays in transportation; or unavoidable casualty loss to, <br /> or destrt�ction of,the Work,then the Schedule described in 4(a)above may be adjusted by Contractor based <br /> on the reasonablc amount of time lost as a result of such occurrence. Otherwise,Subcontractor assumes all <br /> risks of strict compliance with the Schedule. The adjustment of the Schedule provided for herein shall be <br /> Subc:ontractor's sole remedy for any and All interferences,suspensions,and delays. No such adjustment in <br /> the Schedule shall be mude unless written notice containing A request therefore is given to Contractor <br /> within forty-eight (48) hours after commencement of the occuirenc;e that causes such delay, regardless of <br /> whether or not Contractor has actual notice of the delay,and provided always thttt a similar extension of <br /> time has been apotted to CantrACtor by Owner. Contrs�ctor shall have no dury,obligation, or liability to <br /> Subcontractor as a result of any delay, interference,suspension,or other event,except to seek an extension <br /> of time From the Owner as provided herein. <br /> 4(c). Liqr�idated Danrages, Subcontractor represents that it has satisfied itself as to the extent and <br /> amount of any provision in the Prime Contruct imposing liquidated damages upon Contractor, And <br /> ackrx�wtedges thAt in the event Subcuntractor fnils to eomply with the Seheciule, and liquidated damAges <br /> are imposed by Owner on Contractor, such liquidated damages will constitute one element of the damt�ges <br /> that Contractor shuU be entitled to recover f'rom Subcontractor. <br /> S(n}. Cl:a�iges in tlie Work. Contractor may at any time, without notice to any surety, direct <br /> ch�nges,additions,and/or deletions in or to Subcontractor's Work,or direct extra work(all of the foregoing <br /> being referred to herein as"Change(s)"). The Subcontract Price and Schedule shal{be adjusted on account <br /> of Changes only as pt•ovided in 5(b)-(d}below. Otherwise, Subcontraclar shall receive no time extension <br /> or additional compensation on account of Changes. <br /> S(b). Change Orders. No Change shall result in An adjustment in the Subcontract Price or <br /> Schedule unless expressly directed by a Change Order made in strict compliance with this Section 5(b), <br /> prior to Stibcontractor's commencement of performunce of the Change. A Change Order is: (i) a written <br /> order by Contractor, expressly designated as a Change Order, directing a Change in the Work, or (ii) an <br /> oral or written order (defined to include authorizations, directions, interpretations, or determination) by <br /> Contructor directing a Change in the Work, if,and only if, Subcontractor gives Contraetor written notice <br /> within three(3)calendar days after first receiving s�ich o►•der,stating the date,circumstances,and source of <br /> the order, and expressly stating that Subcontractor regards such order as requiring a Change in the Work. <br /> Provided,however, that such iiotice by Subcontractor shAll not result in a Change Order if the Contractor's <br /> order does not, in fact, require a Change in the Worfc. Na other order by Contr�ctor shall constitute � <br /> Change Order, and Subcontracror shall be entided to no compensation or adjustment in the Schedule on <br /> account of any other order,whether or not it results in a Change <br /> S(c). A�justments i�e Sribcontract Price. Prior to the issuance of any Change Order,Contractor <br /> may require Subcontractor to furnish promptly a detailed price breakdo�vn showing the difference in value <br /> �3o6-ig-3oo <br /> Page 4 of l3 <br /> Sulx�antrac�Agrecrtx:nt(L.ong Fonn) <br /> Rcvised 06/OS/10 <br />