PERFORMANCE SPECIFICATION <br />P" <br />w <br />u <br />SECTION I GENERAL CONDITIONS <br />PART 1 - GENERAL <br />1.1 SCOPE OF WORK: THE WORK INCLUDED IN THE CONTRACT FOR THIS PROJECT CONSISTS OF THE FURNISHING OF ALL <br />LABOR, MATERIALS, SERVICES, EQUIPMENT AND APPLIANCES REQUIRED IN CONJUNCTION WITH OR PROPERLY INCIDENTAL <br />TO THE COMPLETE CONSTRUCTION OF A GASOLINE INSTALLATION FOR 7-ELEVEN, INC. <br />PART -AGREEMENT <br />2.1 CONTRACTOR SHALL NOT START WORK WITHOUT CONTRACT AND APPROVED SEALED PLANS. <br />PART 3 - INTENT OF DRAWING AND SPECIFICATIONS <br />3.1 THE INTENT OF THE DRAWINGS AND SPECIFICATIONS IS TO PRESCRIBE A COMPLETE WORK OR IMPROVEMENT WHICH THE <br />CONTRACTOR SHALL PERFORM IN FULL COMPLIANCE WITH THE CONTRACT DOCUMENTS. THE CONTRACTOR SHALL <br />PERFORM ALL WORK NECESSARY TO COMPLETE THE WORK IN A SATISFACTORY AND ACCEPTABLE MANNER. <br />3.2 THE CONTRACTOR SHALL, UPON DISCOVERY, REPORT ANY DISCREPANCIES IN THE DRAWINGS AND SPECIFICATIONS TO <br />THE OWNER'S CONSTRUCTION MANAGER. <br />3.3 THE DRAWINGS AND SPECIFICATIONS ARE INTENDED TO BE COMPLIMENTARY. ANYTHING MENTIONED IN THE <br />SPECIFICATIONS AND NOT SHOWN ON THE DRAWINGS, OR SHOWN ON THE DRAWINGS AND NOT MENTIONED IN THE <br />SPECIFICATIONS, SHALL BE OF LIKE EFFECT AS IF SHOWN OR MENTIONED IN BOTH. GENERALLY, THE SPECIFICATIONS <br />DESCRIBE WORK WHICH CANNOT BE READILY IDENTIFIED ON THE DRAWINGS AND INDICATED TYPES, QUALITIES AND <br />METHODS OF INSTALLATION OF THE VARIOUS MATERIALS AND EQUIPMENT REQUIRED FOR THE WORK. IT IS NOT INTENDED <br />TO MENTION EVERY ITEM OF WORK IN THE SPECIFICATIONS WHICH CAN BE ADEQUATELY SHOWN ON THE DRAWINGS NOR <br />TO SHOW ON THE DRAWINGS ALL ITEMS OF WORK DESCRIBED OR REQUIRED BY THE SPECIFICATIONS EVEN IF THEY ARE <br />OF SUCH NATURE THAT THEY COULD HAVE BEEN SHOWN THEREON. ALL MATERIALS OR LABOR FOR WORK WHICH IS <br />SHOWN ON THE DRAWINGS OR IS REASONABLY INFERABLE AS BEING NECESSARY TO PRODUCE A FINISHED JOB SHALL BE <br />PROVIDED BY THE CONTRACTOR WHETHER OR NOT THE WORK IS EXPRESSLY COVERED IN THE SPECIFICATIONS. <br />3.4 THE CONTRACTOR, SUBCONTRACTORS AND ALL TRADES SHALL EXAMINE THE SITE AND ASCERTAIN EXISTING CONDITIONS <br />PRIOR TO THE START OF THEIR PORTIONS OF THE WORK. BEFORE ORDERING MATERIALS OR DOING ANY WORK, THE <br />CONTRACTOR SHALL VERIFY AND BE RESPONSIBLE FOR THE CORRECTNESS OF ALL MEASUREMENTS AT THE SITE. ANY <br />DIFFERENCES WHICH MAY BE FOUND BETWEEN ACTUAL DIMENSIONS AND DIMENSIONS INDICATED ON THE DRAWINGS OR <br />SHOP DRAWINGS SHALL BE SUBMITTED TO THE OWNER'S CONSTRUCTION MANAGER FOR CONSIDERATION BEFORE <br />PROCEEDING WITH THE ACTUAL DIMENSIONS AND MEASUREMENTS INDICATED ON THE DRAWINGS UNLESS A SUBSTANTIAL <br />ERROR HAS BEEN MADE. IF SUCH AN ERROR SHOULD OCCUR, IT SHALL BE BROUGHT TO THE ATTENTION OF THE OWNER'S <br />CONSTRUCTION MANAGER AND RESOLVED BEFORE PROCEEDING WITH WORK. <br />3.5 THE ORGANIZATION OF SPECIFICATIONS INTO DIVISIONS, SECTIONS AND PARAGRAPHS, AND THE ARRANGEMENT OF THE <br />DRAWINGS ARE NOT INTENDED TO CONTROL THE CONTRACTOR IN DIVIDING THE WORK AMONG SUBCONTRACTORS OR IN <br />THE ESTABLISHING THE EXTENT OF WORK TO BE PERFORMED BY ANY TRADE. <br />3.6 DRAWINGS AND SPECIFICATIONS: DRAWINGS INDICATE GENERAL DESIGN AND ARRANGEMENTS DRAWINGS ARE <br />DIAGRAMMATIC AND ARE NOT SCALED FOR DIMENSIONS. TAKE ALL DIMENSIONS FROM ARCHITECTURAL PLANS AND <br />EQUIPMENT TO BE FURNISHED. VERIFY DIMENSIONS IN THE FIELD. <br />PART 4 - RESPONSIBILITY OF THE CONTRACTOR <br />4.1 CONTRACTOR HEREBY DECLARES HE HAS READ ALL SPECIFICATIONS AND EXAMINED THE DRAWINGS AND <br />THAT HE UNDERSTANDS ALL CONDITIONS. <br />4.2 CONTRACTOR HEREBY DECLARES HE HAS VISITED THE SITE AND IS FAMILIAR WITH THE CONDITIONS <br />AFFECTING THE WORK. NO ALLOWANCES SHALL BE MADE SUBSEQUENTLY ON BEHALF OF THE <br />CONTRACTOR FOR ANY ERROR NEGLIGENCE ON HIS PART. IF IN THE PERFORMANCE OF THE CONTRACT, <br />LATENT CONDITIONS AT THE SITE ARE FOUND TO BE MATERIALLY DIFFERENT FROM THOSE INDICATED <br />BY THE DRAWINGS AND SPECIFICATIONS, OR UNKNOWN CONDITIONS UNUSUALLY INHERENT IN WORK OF <br />THIS CHARACTER SHOWN AND SPECIFIED, THE ATTENTION OF THE OWNER'S CONSTRUCTION MANAGER <br />SHALL BE CALLED IMMEDIATELY TO SUCH CONDITIONS BEFORE THEY ARE DISTURBED. <br />4.3 CONTRACTOR HEREBY DECLARES THAT HE HAS READ AND IS FAMILIAR WITH THE APPLICABLE SOILS <br />REPORT. <br />CONTRACTOR SHALL BE RESPONSIBLE FOR STRICTLY ADHERING TO THE RECOMMENDATIONS OF SAID <br />SOILS REPORT FOLLOWING ALL APPLICABLE PROCEDURES NOTED THEREIN. EXISTING WATER TABLE SHALL <br />POSSIBLY DETERMINE A DIFFERENT UTILIZATION OF THE TANK STRAPS AND TYPE OF BACK FILL <br />MATERIAL. SHOULD GROUND WATER OR CONTAMINATION BE DISCOVERED DURING TANK EXCAVATION, <br />WORK SHALL BE SUSPENDED PENDING REVIEW BY 7-ELEVEN CONSTRUCTION MANAGER. <br />4.4 CONTRACTOR SHALL REPORT ANY OBJECTION TO MATERIALS, APPLIANCES, OR METHODS OF <br />CONSTRUCTION SHOWN OR SPECIFIED TO THE OWNER'S CONSTRUCTION MANAGER AND OBTAIN A <br />DECISION BEFORE PROCEEDING. <br />4.5 PROPOSALS: CONTRACTOR SHALL SUBMIT BID ONLY ON 7-ELEVEN'S FORM THAT WILL BE PROVIDED BY <br />7-ELEVEN'S LOCAL CONSTRUCTION MANAGER, "COST OF CONSTRUCTION" PROPOSALS SUBMITTED ON ANY <br />OTHER FORM SHALL BE REJECTED AND RETURNED. PROPOSALS NOT COMPLETELY AND PROPERLY FILLED <br />OUT SHALL BE REJECTED. PROPOSALS SHALL INCLUDE MONEYS FOR REMOVAL OF ALL EXISTING <br />IMPROVEMENTS AS REQUIRED FOR GASOLINE INSTALLATION. <br />4.6 PERMITS: CONTRACTOR SHALL, AS DIRECTED BY 7-ELEVEN, PAY FOR ALL APPLICABLE PERMITS AND AND FEES. COPIES OF <br />PERMITS AND CERTIFICATES SHALL BE FORWARDED TO LOCAL 7-ELEVEN CONSTRUCTION MANAGER'S OFFICE OR SITE <br />MANAGER PRIOR TO COMMENCEMENT OF WORK. FINAL CERTIFICATION OF ACCEPTANCE BY GOVERNING AUTHORITIES <br />SHALL ALSO BE ON FILE WITH LOCAL CONSTRUCTION OFFICE OR SITE MANAGER PRIOR TO THE PROCESSING OF FINAL <br />PAYMENT REQUEST. <br />4.7 INSPECTIONS: CONTRACTOR SHALL BE REQUIRED TO ADHERE TO ALL REQUIREMENTS OF OWNER'S INSPECTION <br />PROGRAM. CONTRACTOR SHALL COMPLY WITH REQUIREMENTS FOR NOTIFICATION, SITE PREPARATION REQUIREMENTS, <br />COMPLIANCE, ON -SITE PRESENCE DURING INSPECTION AND CORRECTION OF ANY DEFECTS OR RELATED PROBLEMS AS <br />DIRECTED BY INSPECTING REPRESENTATIVE CONTRACTOR SHALL PROVIDE NO LESS THAN 48 HOURS NOTICE PRIOR TO <br />INSPECTION. <br />4.8 COORDINATION: GASOLINE CONTRACTOR SHALL BE RESPONSIBLE FOR SCHEDULING ALL PHASES OF THE GASOLINE <br />INSTALLATION WITH THE GENERAL CONTRACTOR IN CHARGE OF THE BUILDING OR MAJOR PORTION OF THE PROJECT. THE <br />BUILDING GENERAL CONTRACTOR AND THE GASOLINE CONTRACTOR SHALL JOINTLY DEVELOP A MUTUALLY AGREEABLE <br />SCHEDULE AND TIMETABLE FOR COMPLETION ON THE GASOLINE INSTALLATION. TIMETABLE FOR BUILDING AND GASOLINE <br />SHALL COINCIDE AND COMPLIMENT EACH OTHER SO THAT ONE DOES NOT DELAY THE OTHER. <br />SHOULD GASOLINE CONTRACTOR FAIL TO MEET DEADLINES AS ESTABLISHED BY THE SCHEDULE AND/OR HOLD UP THE <br />COMPLETION OF THE OVERALL BUILDING PROJECT, 7-ELEVEN, INC. RESERVES THE RIGHT TO RECTIFY THE SITUATION <br />ACCORDINGLY. <br />4.9 CONTRACTOR SHALL PROVIDE OWNER WRITTEN CERTIFICATION AS TO THE FOLLOWING: <br />4.9.1 CERTIFICATION FROM LOCAL/STATE GOVERNING AUTHORITIES AS APPLICABLE FOR CONTRACTOR <br />CERTIFICATION/LICENSING FOR INSTALLATION OF GASOLINE STORAGE TANK SYSTEM. <br />4.9.2 CERTIFICATION FROM EQUIPMENT MANUFACTURES AND SUPPLIERS (TANKS, PRODUCT LINES, <br />ATG'S, ETC.) AS TO ATTENDING AND ACHIEVING CERTIFICATION FROM APPROPRIATE COMPANY FOR <br />INSTALLATION OF EQUIPMENT. <br />4.9.3 CERTIFICATION ON APPROPRIATE FORMAT AS TO INSTALLATION OF COMPLETE SYSTEM BEING <br />PERFORMED IN COMPLIANCE WITH ALL LOCAL, STATE AND FEDERAL LAWS AND REGULATIONS. <br />4.9.4 CERTIFICATION THAT ALL EQUIPMENT EITHER SUPPLIED BY OWNER OR CONTRACTOR HAS BEEN <br />INSTALLED AS PER MANUFACTURER'S SPECIFICATIONS BY PERSONNEL TRAINED AND QUALIFIED <br />FOR THAT SPECIFIC ITEM. <br />SECTION I GENERAL CONDITIONS - CONTINUED <br />PART 4 - CONTINUED <br />4.11 LIENS: CONTRACTOR SHALL PERMIT NO LIENS OF ANY KIND TO BE FIXED UPON OR AGAINST THE PROPERTY BY ITS <br />LABORERS, MECHANICS OR MATERIAL MEN, AND SHALL INDEMNIFY, PROTECT AND SAVE OWNER HARMLESS FROM AND <br />AGAINST ALL SUCH CLAIMS AND LIENS. <br />4.12 EQUIPMENT RESPONSIBILITY: CONTRACTOR SHALL BE RESPONSIBLE FOR SCHEDULING, RECEIVING, UNLOADING, <br />HANDLING AND PROVIDING PROTECTED INSIDE STORAGE FOR ALL OWNER SUPPLIED EQUIPMENT AND MATERIAL. <br />CONTRACTOR SHALL INSPECT EQUIPMENT UPON RECEIPT AND IMMEDIATELY REPORT ANY DAMAGE DUE TO SHIPPING TO <br />THE OWNER'S REPRESENTATIVE. CONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE DUE TO FAILURE TO COMPLY <br />WITH THESE REQUIREMENTS. DISPENSERS SHALL BE PROTECTED WITH SHIPPING BOXES UNTIL STORE IS TURNED OVER <br />FOR OPENING. CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR ADEQUATE AND LOCKED STORAGE OF OWNER'S <br />MISCELLANEOUS EQUIPMENT, TO INCLUDE GASOLINE CONSOLE, PRIOR TO OPENING OF THE STORE. <br />4.13 GASOLINE CONTRACTOR SHALL BE RESPONSIBLE FOR FILING OF RECEIVING FORMS AND MISCELLANEOUS CONFIRMATION <br />OF EQUIPMENT RECEIVING INFORMATION AS REQUIRED BY LOCAL CONSTRUCTION OFFICE. <br />4.14 GASOLINE CONTRACTOR SHALL PROVIDE ALL PLUMBING, WIRING, MATERIAL AND LABOR AS REQUIRED TO INSTALL OWNER <br />SUPPLIED EQUIPMENT. INCLUDE MONEY IN BID PROPOSAL FOR INSTALLATION OF OWNER SUPPLIED EQUIPMENT UNLESS <br />NOTED OTHERWISE. <br />PART 5 PROTECTION <br />5.1 CONTRACTOR SHALL BE HELD RESPONSIBLE FOR ANY LOSS OR DAMAGE CAUSED BY HIM OR HIS WORKMEN TO THE <br />PROPERTY OR EQUIPMENT OF THE OWNER, OR TO THE WORK OR MATERIALS OF OTHER CONTRACTORS. CONTRACTOR <br />SHALL MAKE GOOD ANY LOSS, DAMAGE OR INJURY WITHOUT COST TO OWNER FOR SUCH LOSS OR DAMAGE. <br />5.2 CONTRACTOR SHALL PROVIDE AND MAINTAIN SUITABLE TEMPORARY SIDEWALKS, FENCES, LIGHTS, SIGNS OR OTHER <br />STRUCTURES AND DEVICES AS REQUIRED BY LAW, DO NOT OBSTRUCT OR INTERFERE WITH TRAFFIC IN PUBLIC STREETS, <br />ALLEYWAYS OR PRIVATE RIGHT-OF-WAYS. IF WORK IS SUSPENDED, KEEP ALL ROADWAYS AND SIDEWALKS IN PROPER <br />CONDITION AND PUT AND LEAVE THEM IN PROPER CONDITION AT TERMINATION OF WORK. <br />5.3 CONTRACTOR SHALL SEND PROPER NOTICES, MAKE NECESSARY ARRANGEMENTS AND PERFORM ALL WORK REQUIRED <br />FOR THE CARE, PROTECTION AND MAINTENANCE OF PUBLIC UTILITIES ON AND AROUND THE BUILDING SITE, ASSUMING ALL <br />RESPONSIBILITY AND PAYING ALL COSTS FOR WHICH THE OWNER MAY BE LIABLE. CONTRACTOR HEREBY DECLARES HE <br />HAS VERIFIED THE LOCATIONS OF THE EXISTING UNDERGROUND UTILITIES ON SITE PRIOR TO THE START OF WORK. <br />CONTRACTOR HEREBY AGREES TO MAKE ARRANGEMENTS FOR AND TO PAY ALL CHARGES IN CON- JUNCTION WITH THE <br />RELOCATION'S OF EXISTING UTILITIES AS REQUIRED. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ANY AND ALL UTILITY <br />EASEMENTS, HOOKUP CHARGES, TAP FEES & SYSTEM DEVELOPMENT FEES OR BONDS AS NECESSARY FOR COMPLETION <br />OF THIS PROJECT. <br />5.4 IF ALL OR PART OF THE WORK IS SUSPENDED FOR ANY REASON, CONTRACTOR SHALL PROPERLY COVER OVER, SECURE <br />AND PROTECT ANY PORTION LIABLE TO SUSTAIN INJURY FROM ANY CAUSE. <br />5.5 PRODUCT PROTECTION: CONTRACTOR SHALL PROVIDE ADEQUATE AND SECURE PROTECTION OF PRODUCT IN TANKS <br />UPON DELIVERY UNTIL TURNED OVER FOR OPERATION. ALL FILL, VENT AND GAUGING CAPS AND/OR OPENINGS SHALL BE <br />SECURED AND PADLOCKED TO PREVENT VANDALISM OR THEFT. <br />PART 6 - SUBSTITUTION OF MATERIALS <br />6.1 MATERIALS AS SPECIFIED REPRESENT REQUIRED STANDARDS. SUBSTITUTION MAY BE PROPOSED IN WRITING WITH <br />ADEQUATE SUPPORTING DATA FURNISHED. USE OF SUBSTITUTE MATERIALS IS DEPENDENT ON RECEIPT OF WRITTEN <br />APPROVAL FROM OWNER'S APPROVED REPRESENTATIVE. <br />PART 7 - COMPLETION OF CONTRACT <br />7.1 THE CONTRACT SHALL BE CONSIDERED FULFILLED, SAVE AS PROVIDED IN ANY MAINTENANCE STIPULATIONS, BOND OR BY <br />LAW, WHEN ALL THE WORK HAS BEEN COMPLETED WITH FINAL INSPECTION AND ACCEPTANCE MADE BY ALL APPLICABLE <br />GOVERNING BUILDING DEPARTMENTS, FIRE MARSHAL'S OR OTHER JURISDICTIONS. <br />7.2 NOT USED <br />7.3 CLEANING: <br />7.3.1 ALL WORK SHALL BE CLEAN AND READY FOR USE UPON COMPLETION. REMOVE TEMPORARY TAPES, <br />WRAPPING, COATING, PAPER LABELS AND OTHER ITEMS. <br />7.3.2 CLEANING METHODS FOR PROPRIETARY MATERIALS SHALL BE IN STRICT ACCORDANCE WITH <br />MANUFACTURER'S INSTRUCTIONS. CLEANING SOLUTIONS, AGENTS, SOLVENTS, WAXES OR OTHER <br />MATERIALS SHALL BE ONLY AS APPROVED BY THE MANUFACTURER OF THE MATERIAL INSTALLED IN <br />THE WORK. <br />7.3.3 CLEANUP: CONTRACTOR SHALL CLEAN UP ALL DEBRIS CAUSED BY THE WORK OF THIS SECTION, <br />KEEPING THE PREMISES NEAT AT ALL TIMES. <br />PART 8-CODES <br />8.1 THE FOLLOWING CODES ARE MADE APART OF THIS SPECIFICATION. SAID CODES SHALL DICTATE MINIMAL ACCEPTABLE <br />STANDARDS. CODE SHALL BE ADHERED TO UNLESS LOCAL GOVERNING AUTHORITIES DICTATE HIGHER OR MORE <br />STRINGENT REQUIREMENTS WHICH SHALL TAKE PRECEDENCE: <br />8.1.1 NFPA 30 FLAMMABLE AND COMBUSTIBLE LIQUIDS CODE <br />8.1.2 PEI MANUAL "RECOMMENDED PRACTICES FOR INSTALLATION OF UNDERGROUND LIQUID STORAGE <br />SYSTEMS." #RP-100-96 (OR LATEST EDITION) <br />8.1.3 OSHA AND LOCAL MUNICIPALITIES <br />PART 9 - WARRANTY / GUARANTEE <br />9.1 EXCEPT WHERE SPECIAL GUARANTEES ARE REQUIRED IN EXCESS OF ONE (1) YEAR, THE CONTRACTOR AGREES TO REPAIR <br />AND RE -CERTIFY OR REPLACE THE DEFECTIVE COMPONENT OR ANY DEFECT IN MATERIAL OR WORKMANSHIP (BEYOND <br />ORDINARY WEAR AND TEAR) TO THE SATISFACTION OF THE OWNER'S CONSTRUCTION MANAGER FOR A PERIOD OF ONE (1) <br />YEAR AFTER DATE OF ACCEPTANCE, WHETHER IN HIS WORK OR IN THAT OF SUBCONTRACTOR'S, WITHOUT COST TO THE <br />OWNER. <br />E'1�►�_1�>�i�llZ[ei%ik1144 <br />T1T1 <br />PART 10 - AS BUILT PLAN AND DOCUMENTATION <br />10.1 UPON COMPLETION OF PROJECT CONTRACTOR SHALL PROVIDE "AS -BUILT " U T SITE PLAN VERIFYING FINAL LOCATION OF <br />IMPROVEMENTS INCLUDING, BUT NOT LIMITED TO, PIPING, PLUMBING AND ELECTRICAL. <br />10.2 CONTRACTOR SHALL KEEP PHOTOGRAPHIC JOURNAL OF ALL PHASES OF THE COMPLETE INSTALLATION. PHOTOGRAPHS <br />ARE TO BE PROPERLY DATED, IDENTIFIED AND FORWARDED TO LOCAL 7-ELEVEN, INC. CONSTRUCTION OFFICE, WITH FINAL <br />INVOICE PACKAGE. <br />SECTION 11 INSPECTIONS / TESTING <br />BEFORE PLACING COMPONENTS IN THE EXCAVATION <br />COMPONENT <br />TEST PROCEDURE <br />Double -walled tank <br />Inspection and 5 psig air/soap test or <br />Sec. 3.3, 3.57 <br />according to manufacturer's <br />recommendations. <br />Piping <br />Careful Inspection <br />Sec. 10.3 <br />Table below lists procedures that may be applied to storage -system components <br />prior to placing them in the excavation. <br />AFTER ASSEMBLY BUT BEFORE BACKFILLING <br />COMPONENT <br />TEST PROCEDURE <br />New primary piping. Piping must <br />be isolated from tank. Sec. 11.1.1 <br />50 psig air/soap test. <br />Secondary piping Sec. 11.2.1 <br />5 or 10 psig air/soap test. <br />Tank -top sumps and dispenser <br />sumps Sec. 8.4-5 <br />y ros a Ic es or manufacturer's <br />recommendations. <br />Table below lists test procedures that may be applied to storage -system <br />components after assembly but before backfilling. <br />TEST BEFORE PLACING THE SYSTEM IN SERVICE <br />COMPONENT <br />TEST PROCEDURE <br />Double -walled storage tank <br />Inspect tank interstice or check vacuum or liquid <br />level (Sec. 3.6-7) <br />Double -walled piping <br />Tightness test primary piping Sec. 11.1.4.). Test <br />Secondary according to Section 11.2.3 or <br />Manufacturer's instructions. <br />Tank shell deflection <br />Compare before/after backfilling vertical <br />diameter. If measurements differ, consult <br />manufacturer's instructions for allowable <br />variation. <br />Leak detection sensor <br />Ensure ability to detect alarm condition (e.g., <br />water, product). <br />Verify set up parameters (e.g., water, product). <br />Automatic tank gauges <br />Overfill prevention devices <br />Verify that device is set at the proper height and <br />ensure proper operation. <br />Spill -containment manholes <br />Check the operation of the liquid drain (if <br />present) and the clearance between the fill -pipe <br />cap and the manway cover. Remove liquids, trash, <br />installation aides, etc. <br />Impact Valves <br />Ensure that the valve is securely anchored and <br />that the valve mechanism operates freely. Check <br />the level of the shear section relative to the <br />pump island surface. <br />Mechanical line leak detectors <br />Test for ability to detect three gallon per hour <br />leak according to manufacturer's instructions. <br />Electronic line leak detectors <br />Verify set up parameters (e.g., piping length, <br />diameter, type). Test for ability to detect three <br />gallon per hour leak according to manufacturer's <br />instructions. <br />PART 1 - GENERAL <br />1.1 SCOPE: THIS SECTION COVERS THE FURNISHING OF ALL LABOR, SERVICES AND EQUIPMENT AS REQUIRED TO PROVIDE <br />INSPECTION SERVICES OF THE GAS INSTALLATION. <br />PART 2 - INSPECTIONS <br />2.1 INSPECTOR: 7-ELEVEN, INC. LOCAL CONSTRUCTION DEPARTMENT AND/OR APPOINTED REPRESENTATIVE SHOULD BE <br />NOTIFIED TO OBSERVE TIGHTNESS TESTING OF PRODUCT PIPING, STAGE I & STAGE II PIPING PRIOR TO BACKFILL. <br />2.2 NOTIFICATION: CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFYING 7-ELEVEN'S CONSTRUCTION DEPARTMENT 48 <br />HOURS PRIOR TO REQUESTED INSPECTION <br />2.3 SPILLAGE: SHOULD SPILLAGE OF PRODUCT OCCUR AT ANY PHASE OF INSTALLATION OR TESTING, LOCAL 7-ELEVEN <br />CONSTRUCTION DEPARTMENT AND ENVIRONMENTAL DEPARTMENT ARE TO BE NOTIFIED IMMEDIATELY, ESTIMATED LOSS <br />OF PRODUCT AS WELL AS ACTION TO BE TAKEN BY CONTRACTOR TO SAFEGUARD THE EVENT FROM FURTHER MISHAP AND <br />TO PROTECT THE GENERAL PUBLIC IS TO BE NOTED AND RECORDED. <br />2.4 REPRESENTATIVE OF CONTRACTOR AND PIPING SUBCONTRACTOR SHALL BE AVAILABLE ON SITE DURING TESTING <br />PROGRAMS. FAILURE TO COMPLY WITH THIS REQUIREMENT WILL RESULT IN ANY CORRECTIONS AND/OR REPAIRS <br />REQUIRED BEING PERFORMED BY OWNER AS REQUIRED. COST OF SAID REPAIRS AND/OR CONNECTIONS SHALL BE <br />DEDUCTED FROM CONTRACT AMOUNT AS REQUIRED TO SATISFY THE SITUATION. <br />2.5 PROHIBITED WORK: CONTRACTOR SHALL SCHEDULE WORK SUCH THAT NO HEAVY EQUIPMENT IS OPERATING ON SITE <br />DURING INSPECTION PROGRAMS. NO WELDING OR OPEN FLAMES SHALL BE ALLOWED ON SITE AT ANY TIME DURING TEST <br />PROCEDURES. <br />2.6 INSTALLATION REPORTS: SHOULD 7-ELEVEN OR THEIR APPOINTED REPRESENTATIVES BE UNABLE TO BE PRESENT AT SITE <br />FOR PURPOSES OF FILING ANY INSPECTION REPORTS, CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLETE INSPECTION <br />AND FILING OF REPORT WITH LOCAL 7-ELEVEN, INC. CONSTRUCTION OFFICE. WRITTEN REPORT SHALL INCLUDE <br />PHOTOGRAPHIC DOCUMENTATION OF ALL PROCEDURES. <br />2.7 TEST FAILURE: SHOULD SYSTEM FAIL ANY PORTION OF TEST PROGRAM, CONTRACTOR SHALL IMMEDIATELY INSTIGATE <br />PROCEDURES AS REQUIRED TO BRING SYSTEM INTO COMPLIANCE SHOULD FAILURE OF TEST DUE TO FACILITY WORK <br />REQUIRE EXPENDITURE OF ADDITIONAL MONIES FOR RESCHEDULING AND/OR RETESTING OF SYSTEM, CONTRACTOR <br />SHALL BE HELD RESPONSIBLE FOR COMPENSATION ACCORDINGLY. <br />2.8 CLEANUP: IN THE EVENT PRODUCT SPILLAGE SHOULD OCCUR DURING CONSTRUCTION OR DURING WARRANTY PERIOD <br />DUE TO WORK PERFORMED BY CONTRACTOR, CONTRACTOR SHALL BE RESPONSIBLE FOR CLEANUP AS MAY BE REQUIRED. <br />2.9 TEST REPORT: UPON COMPLETION OF TESTING PROGRAMS, REPRESENTATIVE OF TESTING/ INSPECTION COMPANY SHALL <br />BE RESPONSIBLE FOR FILING COPIES OF TANK AND PIPING TEST/INSPECTION REPORTS WITH LOCAL 7-ELEVEN, INC. <br />CONSTRUCTION OFFICE OR THE OWNER'S ASSIGNED SITE MANAGER WITH COPY TO JOB SITE. <br />c <br />0 <br />4- <br />.Q- <br />U <br />0 <br />��, <br />M <br />0 <br />0 <br />Proto 2nd Qtr 04-03-15 <br />co <br />c0 <br />O <br />Lo <br />ti <br />Cn <br />X <br />Z <br />CU w <br />0 <br />0 <br />Z Z <br />Q <br />w > <br />Z _ <br />A�a� <br />• W <br />� <br />0 <br />LL <br />W o <br />MOB <br />� m <br />0 <br />i O <br />� <br />IZ <br />W QY <br />a lY <br />U) <br />J <br />O <br />W Ceti�a <br />Z <br />ti m <br />�N <br />W <br />Y <br />� <br />Q <br />LL <br />O <br />O <br />M <br />(0 C <br />N W <br />O P <br />00 Z00 <br />CO <br />00 <br />O <br />cM CO <br />O Q m <br />W m N <br />U <br />M s <br />(n 0 1 CIO <br />54)imM (1)om•c88m <br />C)2z>,wt5JCr-0) 2 <br />7 U o° C.... N C N�V `O <br />>o2Uc3oc0Waoi���' <br />Q °t ° OL O n,2 O ° ai 0 <br />,U:Eo�O3c _ o <br />oN YU �2 <br />CL 000 <br />0 <br />.42wQoa-0NL�Y>3ofjmcu <br />Nil O atNa.62' <br />N dmNo9a <br />OWfn N a0= fa p[gca}.00x°omc;� <br />o N c" 0(3 <br />,`,,111111111,,I <br />`j�0 <br />i <br />P• E � <br />No 68170 <br />- ' STATE OF <br />r®rraear��� <br />d <br />SHEET: <br />G13 <br />FUELING - USA <br />