PERFORMANCE SPECIFICATION - CONT. <br />E <br />I <br />0 <br />N <br />0 <br />0 <br />cl- <br />SECTION 11 INSPECTIONS / TESTING -CONTINUED <br />PART 3 - TANK INSTALLATION INSPECTION <br />3.1 SCHEDULE: CONTRACTOR SHALL BE RESPONSIBLE FOR ADJUSTING SCHEDULE SO TANKS ARE TESTED AND SET IN TANK <br />HOLE SAME DAY OF DELIVERY. <br />3.2 EXCAVATION: ALL EXCAVATIONS SHALL BE COMPLETED WITH BEDDING MATERIAL IN PLACE AND READY FOR INSTALLATION <br />PRIOR TO TANK DELIVERY. <br />3.3 ANCHORS: CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLETE INSTALLATION OF CONCRETE ANCHORS (DEAD MAN). <br />3.4 STRAPS: HOLD DOWN STRAPS TO BE INSTALLED AS PER MANUFACTURER'S SPECIFICATIONS - MINIMUM OF 4 - MORE IF <br />REQUIRED BY MANUFACTURER (STRAPS SHALL BE SHIPPED WITH APPROPRIATE PADDING MATERIAL. <br />3.5 AIR TEST: TANKS SHALL BE AIR TESTED AS PER MANUFACTURER'S SPECIFICATIONS PRIOR TO PLACEMENT. CONTRACTOR <br />SHALL BE RESPONSIBLE FOR PROVIDING ALL MATERIALS TO PROVIDE COMPLETE AIR TEST INCLUDING, BUT NOT LIMITED <br />TO, AIR COMPRESSOR OF SUFFICIENT SIZE AND CAPACITY, SPECIFIED SOAP MATERIAL AND ACCEPTABLE SOAP <br />APPLICATION EQUIPMENT. <br />3.6 MINIMUM TESTING: DOUBLE WALL FIBERGLASS TANKS SHOULD ARRIVE AT THE JOB SITE WITH A MINIMUM OF 4" HG ON THE <br />INTERSTICE. OBSERVE THE VACUUM HOLD TEST FOR AT LEAST ONE (1) HOUR PRIOR TO SETTING THE TANKS. SHOULD THE <br />INTERSTICE NOT HOLD A MINIMUM 4" HG VACUUM, THEN CONTACT THE TANK MANUFACTURER IMMEDIATELY. <br />3.7 OBSERVATION: 7-ELEVEN'S CONSTRUCTION DEPARTMENT AND/OR REPRESENTATIVE SHALL BE RESPONSIBLE FOR <br />INSPECTION OF AIR OR VACUUM TEST, OBSERVATION OF LIFTING, SETTING AND BURIAL OF TANKS. <br />3.8 TANK INSPECTION REPORT: WRITTEN REPORT SHALL INCLUDE PHOTOGRAPHIC DOCUMENTATION OF ALL PROCEDURES. <br />PART 4 - TANK AND LINE TESTING <br />4.1 CONTRACTOR SHALL COMPLETE AND BE RESPONSIBLE FOR THE FOLLOWING PRIOR TO FINAL PLACEMENT OF CONCRETE <br />AND FINAL SYSTEM TEST: <br />4.1.1 PIPING: ALL PIPING SHALL BE COMPLETED EXCEPT INSTALLATION OF OVERFILL PROTECTION. <br />OVERFILL PROTECTION SHALL BE INSTALLED UPON COMPLETION OF TEST. <br />4.1.2 VENTS: VENT LINES SHALL BE COMPLETED UNDERGROUND AND STUBBED UP MINIMUM OF 12'ABOVE <br />FINISHED GRADE. <br />4.1.3 PRODUCT LINES: ALL PRODUCT LINES SHALL BE COMPLETE WITH EMERGENCY SHUTOFF IMPACT VALVE <br />INSTALLED AT DISPENSER BOX WITH MECHANICAL LEAK DETECTOR IN PLACE. <br />4.1.4 PUMPS: SUBMERSIBLE PUMPS AND LINES SHALL BE COMPLETELY INSTALLED. <br />4.1.6 SITE PREPARATION: CONTRACTOR SHALL PREPARE TANK AREA FOR WATER OR PRODUCT DELIVERY AND <br />TANK TESTING PROCEDURES. <br />4.1.7 FILL: CONTRACTOR SHALL PROVIDE 42" MINIMUM BACK FILL OVER TANKS. <br />4.1.8 WATER: SHOULD WATER BE PRESENT IN TANK HOLE, CONTRACTOR SHALL VERIFY AND NOTIFY 7-ELEVEN <br />CONSTRUCTION MANAGER OF STATUS. <br />4.2 AFTER PLACEMENT OF CONCRETE, A COMPLETE SYSTEM TIGHTNESS TEST INCLUDING TANKS, PRODUCT LINES, STAGE II <br />VAPOR RECOVERY LINES, SECONDARY CONTAINMENT PIPING AND VENT LINES SHALL BE PERFORMED. TESTING SYSTEM <br />SHALL BE AS APPROVED BY 7-ELEVEN. 7-ELEVEN WILL BE BILLED DIRECTLY FOR TESTS. CONTRACTOR TO COORDINATE & <br />SCHEDULE. RETEST OR STAND AROUND TIME BY THE TESTING COMPANY TO BE BILLED TO CONTRACTOR. DETAILS FOR <br />THIRD PARTY TESTING REQUIREMENTS LISTED ON G9.X SHEETS. <br />4.2.1 AFTER ALL UNDERGROUND PIPING AND ELECTRIC CONDUITS ARE INSTALLED AND DURING EXCAVATION <br />BACKFILLING AND CONCRETE POURING, A CONTINUOUS HYDROSTATIC TEST SHALL BE PERFORMED ON <br />ALL SUMPS & SPILL BUCKETS TO ENSURE TIGHTNESS AND PROPER INSTALLATION. <br />4.3 PRODUCT DELIVERY: CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFICATION TO 7-ELEVEN REPRESENTATIVE OF TEST <br />DATE AND VERIFICATION OF NEED FOR TANKS TO BE FILLED WITH PRODUCT AND TANK MONITORING SYSTEM TO BE <br />OPERATIONAL FOR TESTING PROCEDURES. A MINIMUM OF 72 HOURS ADVANCE NOTIFICATION WILL BE REQUIRED FOR <br />PRODUCT DELIVERY. CHECK WITH LOCAL REGULATORY AGENCIES FOR ANY FURTHER REQUIREMENTS. <br />4.4 CONTRACTOR SHALL HAVE REPRESENTATIVES ON SITE TO ACCEPT AND RECORD ALL PRODUCT DELIVERIES. <br />CONTRACTOR'S REPRESENTATIVE SHALL REMIND DELIVERY COMPANY THAT NO OVERFILL PROTECTION IS INSTALLED AND <br />TO FOLLOW PROCEDURES FOR DELIVERY AS SITUATION DICTATES. <br />4.5 PRODUCT REMOVAL: ANY REMAINING PRODUCT IN VENT LINES UPON COMPLETION OF TEST SHALL BE REMOVED BY <br />TESTING COMPANY. <br />PART 5 - STARTUP INSPECTION <br />5.1 SCHEDULING: CONTRACTOR SHALL BE RESPONSIBLE FOR FINAL SCHEDULING STARTUP AND CHECK-OUT. CONTRACTOR <br />SHALL NOTIFY LOCAL CONSTRUCTION DEPARTMENT AND APPLICABLE MAINTENANCE DEPARTMENT OFFICE A MINIMUM OF <br />48 HOURS PRIOR TO INTENDED FINAL STARTUP AND CHECK-OUT DATE AND TIME. <br />5.2 PERSONNEL: CONTRACTOR, PLUMBING SUBCONTRACTOR AND ELECTRICAL SUBCONTRACTOR SHALL BE AVAILABLE <br />ON -SITE DURING STARTUP, AS APPROVED BY 7-ELEVEN, INC. ALL STARTUPS ARE TO BE DONE BY AN AUTHORIZED <br />MANUFACTURER'S CONTRACTOR FOR THAT PIECE OF EQUIPMENT. <br />5.3 STARTUP: PHYSICAL STARTUP AND CHECK-OUT OF SYSTEMS AND EQUIPMENT SHALL BE DONE BY AND AT THE DIRECTION <br />OF 7-ELEVEN REPRESENTATIVE ONLY. CONTRACTOR SHALL NOT START OR ACTIVATE ANY EQUIPMENT WITHOUT THE <br />SPECIFIC DIRECTIVE OF 7-ELEVEN REPRESENTATIVE. DAMAGE TO ANY 7-ELEVEN EQUIPMENT DUE TO IMPROPER <br />INSTALLATION AND/OR UNAUTHORIZED STARTUP WILL BE THE RESPONSIBILITY OF THE CONTRACTOR. <br />5.4 SITE COMPLETION: ALL SITE WORK, INCLUDING CONCRETE/ASPHALT PAVEMENTS, SHALL BE COMPLETE. ALL UTILITIES <br />SHALL BE CONNECTED AND OPERATIONAL. ALL LANDSCAPING, INCLUDING SPRINKLER SYSTEMS, SHALL BE COMPLETE. <br />5.5 VERIFICATION: PRIOR TO SCHEDULING OF STARTUP, CONTRACTOR SHALL OBSERVE AND VERIFY CORRECTNESS AND <br />COMPLIANCE TO 7-ELEVEN'S DRAWINGS AND SPECIFICATIONS FOR THE FOLLOWING, BUT THESE SHALL NOT COMPRISE <br />THE TOTAL LIMIT OF THE CONTRACTOR'S VERIFICATION: <br />5.5.1 MAN WELLS SHALL BE PROPERLY CENTER/INSTALLED AT OVERFILLS, SUBMERSIBLES, VAPOR <br />RECOVERY, AUTO GAUGING, OBSERVATION WELLS AND SUMP/RISER. <br />5.5.2 PROPER HEIGHT OF GRAVEL BACK FILL AROUND SUMP/RISERS. <br />5.5.3 TANK I.D. MARKERS INSTALLED IN CONCRETE AT PROPER LOCATIONS. <br />SECTION <br />11 INSPECTIONS / TESTING -CONTINUED <br />PART 5 - <br />STARTUP INSPECTION - CONTINUED <br />5.5.4 <br />ALL BRASS GOODS AND FITTINGS PROPERLY INSTALLED, TIGHT AND SECURE. <br />5.5.5 <br />LEAK DETECTORS INSTALLED. <br />5.5.6 <br />PROTECTED FLEX LINES PROPERLY INSTALLED WITHOUT TWIST IN INSTALLATION. <br />5.5.7 <br />MANHOLE EXTENDERS PROPERLY INSTALLED AND SCREWED IN FRAME OF MANHOLE SUMP/RISERS, <br />PROPERLY SET AND SEALED TO TANK MAN WAY OR FITTINGS AND CLEANED OUT FREE OF DEBRIS AND <br />CONCRETE. <br />5.5.8 <br />TANKS CLEAN AND FREE OF WATER. <br />5.5.9 <br />ISLAND FORM INNER BOXES PROPERLY CLEANED OUT FREE OF DEBRIS AND CONCRETE. <br />5.5.10 <br />DISPENSERS PROPERLY SET AND SECURED TO ISLAND BOX FRAME AND DISPENSER SUMPS PROPERLY <br />CLEANED OUT FREE OF DEBRIS AND CONCRETE. <br />5.5.11 <br />SHEAR VALVES SECURED TO FRAME WITH PROPER HARDWARE. <br />5.5.12 <br />PHASE II VAPOR RECOVERY LINES STUBBED UP AND SECURED IN PROPER LOCATION. <br />5.513 <br />ELECTRICAL CONDUITS SECURED WITH ALL CONNECTIONS COMPLETED. VERIFY COMPLIANCE WITH <br />REQUIREMENTS FOR ISOLATED GROUND WIRING TO JUNCTION BOX CASING. <br />5.5.14 <br />DISPENSER CANOPIES INSTALLED AND LIFTING LUGS REMOVED WITH PROPER PLUGS INSERTED. <br />5.5.15 <br />ALL NOZZLES AND SWIVELS AVAILABLE ON -SITE, INSTALLED PRIOR ONLY IF REQUIRED BY GOVERNING <br />AUTHORITIES FOR INSPECTION PURPOSES. <br />5.5.16 <br />ALL INSPECTIONS BY GOVERNING AUTHORITIES COMPLETED AND SIGNED. SIGNED AND COMPLETED <br />PERMIT CARD ON SITE. <br />5.5.17 <br />ELECTRICAL DEVICES INCLUDING LIGHTS, SIGNS AND INTERCOMS PROPERLY INSTALLED, SECURED AND <br />PLUMB. <br />5.5.18 <br />ANY WIRING INSPECTION PORTS IN CANOPY COLUMNS COVERED WITH ACCEPTABLE PLATES. <br />5.5.19 <br />VENT LINES PROPERLY SECURED, PROTECTED AND INSTALLED AT PROPER HEIGHT <br />5.5.20 <br />VERIFICATION OF COMPLIANCE FOR TANK AND LINE TEST AVAILABLE ON SITE. <br />5.5.21 <br />ALL MANHOLES FREE OF CONCRETE AND DEBRIS. <br />5.5.22 <br />MANHOLE COVERS PROPERLY PAINTED. <br />5.5.23 <br />ALL PAINTING COMPLETE INCLUDING CANOPY, DOWN SPOUTS, METALS AND MISCELLANEOUS METALS. <br />5.5.24 <br />CONCRETE AT ISLANDS AND TANK PAD TRUE, PROPERLY SLOPED AND FINISHED WITH ACCEPTABLE RISE <br />TO MANHOLES. <br />5.5.25 <br />ELECTRICAL PANELS PROPERLY COMPLETED TO INCLUDE: <br />(A) ONE BREAKER FOR EACH SUBMERSIBLE PUMP, DISPENSER, CONSOLE AUTO GAUGING, DISPENSER LIGHTS <br />(ALL) AND CANOPY LIGHTS (ALL). <br />(B) GAS PANEL CONTROLLED BY A MAIN BREAKER. <br />(C) CONTROL BOXES AND DISTRIBUTION BOXES INSTALLED AND WIRED. <br />(D) INTERCOM INSTALLATION COMPLETE AND PROPERLY WORKING. <br />(E) ALL APPLICABLE CONSOLE INSTALLATION COMPLETE AND FUNCTIONAL. <br />(F) ALL WIRING PROPERLY IDENTIFIED WITH COLOR CODED WIRING. <br />(G) CONDUITS PROPERLY IDENTIFIED. (H) ALL BREAKERS IN "OFF" POSITION. <br />5.6 <br />NOTIFICATION: CONTRACTOR SHALL VERIFY ITEMS AS INDICATED ABOVE PRIOR TO SCHEDULING OF STARTUP <br />MONIES AND/OR TIME LOST AT STARTUP DUE TO NOW COMPLIANCE SHALL BE CHARGED TO CONTRACTOR <br />ACCORDINGLY. <br />5.7 <br />EQUIPMENT SHALL BE TESTED PER SPECIFICATIONS ON SHEET G9.2. <br />5.8 <br />CLEANUP: CLEAN UP ALL DEBRIS CAUSED BY WORK OF THIS SECTION, KEEPING PREMISES CLEAN AND NEAT AT <br />ALL TIMES. <br />SECTION <br />III EARTHWORK <br />PART 1 - GENERAL <br />1.1 SCOPE: THIS SECTION COVERS THE FURNISHING OF ALL LABOR, MATERIALS, SERVICES, EQUIPMENT AND APPLIANCES <br />REQUIRED IN CONJUNCTION WITH OR PROPERLY INCIDENTAL TO EARTHWORK. <br />PART 2 - PRODUCTS <br />2.1 FILL MATERIAL: SHALL BE MATERIAL IN COMPLIANCE WITH TANK AND LINE MANUFACTURER'S SPECIFICATIONS. <br />2.1.1 PEA GRAVEL: SHALL BE CLEAN, NATURALLY ROUNDED AGGREGATE WITH A MIX OF PARTICLE SIZE <br />NOT LESS THAN 1/8" OR MORE THAN 3/4". <br />2.1.2 STONE OR GRAVEL CRUSHING: SHALL BE WASHED MATERIAL WITH ANGULAR PARTICLE SIZE NOT <br />LESS THAN 1/8" OR MORE THAN 1/2". <br />2.1.3 BACKFILL OR OTHER MATERIAL MUST BE APPROVED BY TANK MANUFACTURER. <br />NOTE: MATERIALS MUST MEET ASTM C-33 PARAGRAPH 7.1 FOR QUALITY AND SOUNDNESS. FILL MATERIAL <br />SHALL NOT HAVE MORE THAN 3% PASSING A #8 SIEVE. DRY GRAVEL DENSITY MUST BE A MINIMUM <br />OF 95 POUNDS PER CUBIC FOOT. <br />SECTION III EARTH WORK- CONTINUED <br />PART 3 - EXECUTION <br />3.1 PROTECTIONS: PROVIDE ADEQUATE SHORING, BRACING, PILING AND CRIBBING. COMPLY WITH ALL OSHA AND LOCAL <br />REGULATIONS AS IT PERTAINS TO SAFETY. <br />3.2 LAYOUT: CONTRACTOR SHALL BE RESPONSIBLE FOR LAYOUT AS PRESENTED IN PERMITTED PLANS AND SPECIFICATIONS. <br />3.3 EXCAVATION: EXCAVATE TO LINES, ELEVATIONS AND LIMITS REQUIRED BY THE DRAWINGS, PLUS SUFFICIENT DISTANCE <br />AND SPACE TO PERMIT INSTALLATION OF TANKS. EXCAVATE AS REQUIRED, REGARDLESS OF TYPE, CONDITION OR <br />MOISTURE CONTENT OF THE MATERIAL ENCOUNTERED. HAUL EXCESS MATERIAL OFF THE SITE AND DISPOSE OF SAME. <br />DIMENSIONS OF TANK EXCAVATION SHALL BE MINIMAL AS ESTABLISHED BY 7-ELEVEN DRAWINGS UNLESS TANK <br />MANUFACTURER REQUIREMENTS ARE GREATER. IF EXCAVATION MATERIAL IS FROM AN EXISTING GASOLINE FACILITY ALL <br />MATERIALS MUST BE TESTED PRIOR TO REMOVAL. <br />3.4 SAW CUTTING: IF PAVING MUST BE REMOVED, THE PERIMETER OF THE TANK HOLE AND ALL TRENCHES SHALL BE CUT WITH <br />A CONCRETE SAW. NOTE: PAVING TO BE CUT 2' BEYOND EDGES OF TANK HOLE IN ALL DIRECTIONS IN ORDER TO GIVE <br />PROPER SUPPORT TO NEW SLAB TO AVOID SETTLING. <br />3.5 HAZARDOUS MATERIAL: SHOULD ROCK, WATER OR OTHER HAZARDOUS MATERIALS NOT SHOWN ON SOILS TEST BE <br />ENCOUNTERED, LOCAL CONSTRUCTION OFFICE SITE MANAGER SHALL BE IMMEDIATELY CONTACTED FOR APPROVAL TO <br />PROCEED. <br />3.6 PROTECTION: CONTRACTOR SHALL PROVIDE SUFFICIENT PROTECTION WITH EARTHEN BERMS AT ALL TIMES TO PROTECT <br />TANK HOLE AND TRENCHES FROM DRAINAGE OF SURFACE WATERS. EXCAVATIONS SHALL BE PROPERLY MARKED, <br />PROTECTED AND BARRICADED FOR SAFETY UNTIL BACK FILL IS COMPLETE AND SURFACING FINISHED. <br />3.7 SHORING: CONTRACTOR SHALL BE RESPONSIBLE FOR DETERMINING REQUIREMENTS FOR SHORING AND PROVIDING SAME <br />SHOULD SITE AND/OR SOIL CONDITIONS WARRANT SAME. REFERENCE SOIL REPORT FOR CONDITIONS WARRANTING <br />SPECIAL REQUIREMENTS. <br />3.8 FILLING AND BACK FILLING: PLACE APPROVED FILL MATERIAL IN STRICT ACCORDANCE WITH TANK AND PIPING <br />MANUFACTURER'S SPECIFICATIONS. PROVIDE A 12" BED OF APPROVED BACK FILL OVER BOTTOM OF EXCAVATION PRIOR <br />TO TANK PLACEMENT. BACK FILL SHALL BE PLACED AND COMPACTED IN MAXIMUM 12" LIFTS. <br />3.9 CLEANUP: CLEAN UP ALL DEBRIS CAUSED BY WORK OF THIS SECTION, KEEPING PREMISES CLEAN AND NEAT AT ALL TIMES. <br />SECTION IV TANK INSTALLATION <br />PART 1 - GENERAL <br />1.1 SCOPE: THIS SECTION COVERS THE FURNISHING OF ALL LABOR, MATERIALS, SERVICES, EQUIPMENT AND RELATED <br />APPLIANCES REQUIRED IN CONJUNCTION WITH OR PROPERLY INCIDENTAL TO THE INSTALLATION OF GASOLINE STORAGE <br />TANKS. <br />PART 2 - PRODUCTS <br />2.1 TANKS: SHALL BE DESIGNED AND MANUFACTURED SO AS TO BE CORROSION PROTECTED PER EPA REQUIREMENTS. <br />APPROVED TANKS SHALL BE: <br />2.1.1 DOUBLE WALL FIBERGLASS TANKS <br />2.2 HOLD DOWN STRAPS: SHALL BE SUPPLIED BY TANK MANUFACTURER ONLY. FIELD FABRICATED UNITS ARE NOT <br />PART 3 - INSTALLATION <br />3.1 MANUFACTURING: REFER TO TANK MANUFACTURER'S CRITERIA AND SPECIFICATIONS FOR TANK INSTALLATION AND <br />ADHERE TO AS REQUIRED. <br />3.2 CLEARANCES: MINIMUM CLEARANCE FOR TANKS SHALL BE AS FOLLOWS: SHOULD REQUIREMENTS OF TANK <br />MANUFACTURER OR SOIL CONDITIONS DICTATE GREATER CLEARANCE, ADHERE TO ACCORDINGLY. <br />3.2.1 BOTTOM: PROVIDE MINIMUM OF 12" BEDDING MATERIAL BETWEEN BOTTOM OF EXCAVATION OR PAD <br />AND BOTTOM OF TANK. <br />3.2.2 SIDES: PROVIDE MINIMUM OF 2'0" BETWEEN TANKS AND 3' FROM SIDE/END OF TANK TO WALL OF <br />EXCAVATION. <br />3.2.3 TOP: PROVIDE 42" FILL MATERIAL OVER TANK PLUS 8" OF CONCRETE <br />3.3 TESTING: PRIOR TO INSTALLATION OF TANKS, TESTING PER MANUFACTURER'S INSTRUCTIONS SHALL BE PERFORMED ON <br />TANK(S). ON DUAL WALL TANKS, CONSULT TANK MANUFACTURER FOR TESTING CRITERIA BUT MINIMUM 4" HG VACUUM <br />MUST BE HELD ON INTERSTITIAL SPACE FOR AT LEAST ONE (1) HOUR. <br />3.4 PLACEMENT: <br />3.4.1 REFER TO SITE PLAN FOR TANK PLACEMENT AND PRODUCT ROTATION. <br />3.4.2 PRIOR TO SETTING OF TANKS, REMOVE ALL FOREIGN DEBRIS, ROCKS, CLODS, GARBAGE, ETC. FROM <br />EXCAVATION.3.4.3 PLACE TANKS ONLY ON APPROVED FILL. DO NOT SET ON CONCRETE OR WOOD. <br />3.4.4 NOT USED. <br />3.4.5 TANKS SHALL BE BURIED TO MINIMUM DEPTH AS PER ABOVE AND AS SHOWN ON GASOLINE <br />DRAWINGS. TANKS MAY REQUIRE GREATER BURIAL DEPTH IF INSTALLED IN REMOTE POSITION TO <br />ALLOW FOR PROPER SLOPE ON VENT LINES,VAPOR LINES, SECONDARY CONTAINMENT PRODUCT <br />LINES. VERIFY DEPTH AS REQUIRED. (IF BURIAL DEPTH EXCEEDS 5'-0" (60"), NOTIFY 7-ELEVEN <br />MANAGER) <br />c <br />0 <br />:b.. <br />CL <br />a� <br />cv <br />0 <br />a� <br />Proto 2nd Qtr 04-03-15 <br />cM <br />0 <br />0 <br />LO <br />r• <br />QW <br />X <br />dW <br />H <br />0 It <br />Lf) Er. LA J <br />Z <br />Z <br />qqt�� <br />Z <br />w <br />J <br />� j LL <br />W <br />0 <br />_j <br />O <br />W <br />a� <br />w <br />�,qa. <br />i` <br />W <br />Y <br />~ N <br />U <br />Q <br />0 <br />0 <br />N <br />M <br />W <br />Z <br />O <br />Q <br />U <br />LL <br />W <br />U) <br />Z <br />J <br />Lu <br />Z) <br />LL <br />WIgo <br />m <br />Wm a <br />WOOL- MEMNONd o <br />r- (6 <br />�C00 <br />Oti <br />o 0)o� <br />�ita� <br />co 0 co <br />LO N H a0 U <br />0 o <br />0 Z o <br />Q m <br />w m M <br />N <br />U) 0 Q U <br />0(L)MM moc"ac��m <br />V 2t >,o6 42 .2 WE 2 <br />a� c �- a� m •- U <br />�� °� �°-, os o �w no <br />N O aO C >,.- O'-- mL N m <br />m,por4)'a3c�Ym= O <br />O (AL 3 <br />C a0 O Nt ca <br />vai=CWL �N3t>ju� <br />w2amu,Q2_-d.2o_ OE <br />a�NM`NN`c0 <br />U N� O� p >`� O W O r C1 <br />O M >,y 0 c ao >I- c <br />0 7ECL..0OX Ncoc� <br />o m c•. 0Um 3-cn <br />Q ; 6, • :�,� <br />ftb <br />No 68170 <br />STATE OFAWP <br />SHEET: <br />G14 <br />FUELING - USA <br />