PART 1- GENERAL <br />1.01 SUMMARY <br />A. RELATED DOCUMENTS: PROVISIONS OF THE CONTRACT, INCLUDING CONDITIONS OF THE CONTRACT, <br />DRAWINGS AND DIVISION 1 - GENERAL REQUIREMENTS OF THE SPECIFICATION, APPLY TO THIS SECTION. <br />B. DESCRIPTION: WATER -BASED FIRE SUPPRESSION SYSTEMS ARE INDICATED BY CONTRACT DOCUMENTS AND <br />SHALL INCLUDE WORK NECESSARY AND INCIDENTAL TO COMPLETION AND PERFORMANCE OF THE WORK. <br />C. INCLUDED: WATER -BASED FIRE SUPPRESSION SYSTEMS INCLUDE, BUT IS NOT LIMITED TO, FOLLOWING: <br />1. WATER -BASED FIRE SUPPRESSION SYSTEM WATER SERVICE FROM EXISTING INTERIOR SUPPLY MAIN WITHIN <br />BUILDING. <br />2.100 PERCENT SPRINKLERED PROTECTED BUILDING. <br />3. WET PIPE SPRINKLER SYSTEMS. <br />4. PIPE AND FITTINGS. <br />5. SPRINKLERS. <br />6. CHECK VALVES. <br />7. RISER CHECK VALVES. <br />8. BUTTERFLY VALVES. <br />9. DRAIN VALVES. <br />10. INSPECTORS TEST VALVES ASSEMBLIES. <br />11. HANGERS AND SUPPORTS. <br />12. CABINETS. <br />13. ALARM DEVICES. <br />14. SLEEVES. <br />15. FIRE EXTINGUISHERS. <br />16. SIGNS. <br />D. RELATED WORK: <br />1. ELECTRICAL: <br />a. ELECTRICAL POWER FOR LOCAL ALARM BELLS AND ASSOCIATED WIRING. <br />b. WIRING OF FLOW ALARM SWITCHES, TAMPER SWITCHES, AND BELLS TO REMOTE ANNUNCIATOR PANELS. <br />1.02 SYSTEM DESCRIPTION <br />A. CODES AND STANDARDS: MEET REQUIREMENTS OF FOLLOWING, EXCEPT TO EXTENT OF MOST STRINGENT <br />REQUIREMENTS OF CONTRACT DOCUMENTS AND OF CODES AND REGULATIONS OF PUBLIC AUTHORITIES <br />HAVING JURISDICTION OVER THE WORK: <br />2. NFPA 10 - PORTABLE FIRE EXTINGUISHERS. <br />3. NFPA 13 - STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS. <br />4. NFPA 70 - NATIONAL ELECTRIC CODE. <br />5. NFPA 72 - NATIONAL FIRE ALARM CODE. <br />B. PERFORMANCE BASIS: <br />1. GENERAL: PLANS HAVE BEEN PREPARED TO PROVIDE GENERAL GUIDANCE FOR BIDDING. THE WORK THAT IS <br />INDICATED BY THE CONTRACT DOCUMENTS IS AN OVERVIEW, INTENDED TO ESTABLISH THE SCOPE OF <br />RESPONSIBILITIES OF THE CONTRACTOR. THE CONTRACTOR SHALL BE ENGINEER OF RECORD AND SHALL BE <br />RESPONSIBLE FOR A COMPLETE AND FULLY OPERABLE WATER -BASED FIRE SUPPRESSION SYSTEM. PRIOR TO <br />BID, THE CONTRACTOR SHALL CONSULT LOCAL AUTHORITIES HAVING JURISDICTION OVER THE WORK FOR <br />ADDITIONAL REQUIREMENTS. WORK SHALL MEET BASIC ARRANGEMENTS, PERFORMANCE, AND LIKE <br />REQUIREMENTS INDICATED BY CONTRACT DOCUMENTS, AND SHALL INCLUDE COMPONENTS NOT INDICATED <br />BUT NECESSARY FOR PERFORMANCE, FUNCTION, OPERATION AND LIKE REQUIREMENTS, AND TO BE A <br />COMPLETE SYSTEM, PERMANENT AND SAFE OPERATING SYSTEM. ALL PARTS OF THE SYSTEM, INCLUDING <br />EQUIPMENT, SHALL BE INCLUDED AND VALIDATED AS NECESSARY BY THE CONTRACTOR. THE CONTRACTOR <br />SHALL SUBMIT COMPLETE CERTIFIED AND SEALED SET OF WORKING DRAWINGS, EQUIPMENT, SPECIFICATIONS <br />AND HYDRAULIC CALCULATIONS TO OWNER'S REPRESENTATIVE AND AUTHORITIES HAVING JURISDICTION OVER <br />THE WORK FOR REVIEW AND APPROVAL PRIOR TO FABRICATION AND INSTALLATION. <br />2. CERTIFICATION: WORK SHALL BE DESIGNED, CERTIFIED, REVIEWED AND INSPECTED BY ENGINEER OF <br />CONTRACTOR. <br />1.03 QUALITY ASSURANCE <br />A. PRODUCT QUALIFICATIONS: PRODUCTS SHALL BE: <br />1. UL LABELED AND LISTED. <br />2. FMRC - APPROVED LABELS AND LISTED IN FMRC - APPROVAL GUIDE. <br />B. MANUFACTURER QUALIFICATIONS: MANUFACTURER SHALL SPECIALIZE IN PRODUCTION OF PRODUCTS OF <br />TYPES AND CAPABILITIES REQUIRED, WHOSE PRODUCTS HAVE BEEN IN SATISFACTORY USE IN SIMILAR SERVICE <br />FOR 5 YEARS MINIMUM. UPON REQUEST, PROVIDE PROOF OF QUALIFICATIONS <br />C. INSTALLER QUALIFICATIONS: INSTALLER SHALL SPECIALIZE IN PERFORMING WORK OF THIS SECTION, HAVE 5 <br />YEARS MINIMUM DOCUMENTED EXPERIENCE IN DESIGN, ENGINEERING, DETAILING, FABRICATION, INSTALLATION <br />AND MAINTENANCE OF TYPE AND QUALITY REQUIRED FOR WORK AND SHALL BE LICENSED TO PERFORM <br />WATER -BASED FIRE SUPPRESSION WORK BY PUBLIC AUTHORITIES HAVING JURISDICTION OVER THE WORK. <br />UPON REQUEST, PROVIDE PROOF OF QUALIFICATIONS. <br />D. ENGINEER OF CONTRACTOR QUALIFICATIONS: <br />1. GENERAL: PROFESSIONAL ENGINEER OF CONTRACTOR LICENSED TO PRACTICE AS A WATER -BASED FIRE <br />SUPPRESSION ENGINEER IN JURISDICTION WHERE THE WORK IS LOCATED AND EXPERIENCED IN PROVIDING <br />WATER -BASED FIRE SUPPRESSION ENGINEERING SERVICES THAT HAVE RESULTED IN SUCCESSFUL <br />INSTALLATION AND PERFORMANCE OF WORK SIMILAR IN EXTENT, DESIGN AND PRODUCTS TO THAT REQUIRED <br />FOR THE WORK. <br />2. STRUCTURAL: WHEN WORK REQUIRES STRUCTURAL ENGINEERING SERVICES, ENGINEER SHALL BE LICENSED <br />TO PRACTICE AS A STRUCTURAL ENGINEER. <br />F. ACCEPTANCE TESTS: NOTIFY INSURANCE UNDERWRITER OF OWNER AND LOCAL AUTHORITIES HAVING <br />JURISDICTION 2 WEEKS PRIOR TO ACCEPTANCE TESTING. CONTRACTOR SHALL PRE -TEST PRIOR TO WITNESSED <br />TESTS TO ASSURE SYSTEMS OPERATE AS REQUIRED. <br />1.04 SUBMITTALS <br />A. PRODUCT DATA: SUBMIT PRODUCT SPECIFICATIONS, TECHNICAL DATA, STANDARD DETAIL DRAWINGS AND <br />INSTALLATION INSTRUCTIONS OF MANUFACTURERS FOR EACH PRODUCT. INCLUDE PUBLISHED DATA, CERTIFIED <br />CONFORMANCE REPORT OR CERTIFIED LABORATORY TEST REPORT OF MANUFACTURER SUBSTANTIATING <br />EACH PROPOSED PRODUCT MEETS REQUIREMENTS OF CONTRACT DOCUMENTS. MAKE SIMULTANEOUS <br />SUBMITTAL DIRECTLY TO INSURANCE UNDERWRITER OF OWNER AND AUTHORITIES HAVING JURISDICTION OVER <br />THE WORK. <br />B. SHOP DRAWINGS: <br />1. GENERAL: SUBMIT DIMENSIONED SHOP DRAWINGS SHOWING LAYOUT OF PIPING AND EQUIPMENT, ACCURATELY <br />SCALED, INCLUDING SPACE RELATIONSHIPS TO ASSOCIATED PIPING AND EQUIPMENT. PROVIDE HYDRAULIC <br />CALCULATIONS ON CALCULATED SYSTEMS. ELECTRICAL DATA SHALL INDICATE TERMINAL -TO -TERMINAL <br />SYSTEM CONNECTIONS. MAKE SIMULTANEOUS SUBMITTAL DIRECTLY TO INSURANCE UNDERWRITER OF OWNER <br />AND AUTHORITIES HAVING JURISDICTION OVER THE WORK. <br />2. CERTIFICATION: SHOP DRAWINGS FOR WORK SHALL BE CERTIFIED AND SEALED BY ENGINEER OF <br />CONTRACTOR WHO PERFORMED DESIGN WORK COVERED BY CONTENT OF SHOP DRAWINGS, STATING WORK <br />MEETS MOST STRINGENT REQUIREMENTS OF CONTRACT DOCUMENTS.. <br />C. INSURANCE SHOP DRAWINGS: SUBMIT TO ARCHITECT 2 COPIES OF SHOP DRAWINGS WHICH HAVE BEEN <br />REVIEWED, STAMPED AND ACCEPTED BY APPROVING AGENCY OF INSURANCE UNDERWRITER OF OWNER AND <br />AUTHORITIES HAVING JURISDICTION OVER THE WORK. <br />E. PERFORMANCE CERTIFICATION: SUBMIT PERFORMANCE CERTIFICATION PREPARED, CERTIFIED AND SEALED BY <br />ENGINEER OF CONTRACTOR. CERTIFICATION SHALL SPECIFICALLY INDICATE WORK MEETS MOST STRINGENT <br />REQUIREMENTS OF CONTRACT DOCUMENTS AND OF CODES AND REGULATION OF PUBLIC AUTHORITIES HAVING <br />JURISDICTION OVER THE WORK. <br />F. CERTIFICATE OF INSTALLATION: SUBMIT CERTIFICATE UPON COMPLETION OF FIRE SPRINKLER PIPING WORK <br />STATING THAT WORK HAS BEEN COMPLETED, TESTED IN ACCORDANCE WITH NFPA 13, AND THERE ARE NO <br />DEFECTS IN SYSTEM, AND SYSTEM IS OPERATIONAL. MAKE SIMULTANEOUS SUBMITTAL DIRECTLY TO <br />INSURANCE UNDERWRITER OF OWNER AND AUTHORITIES HAVING JURISDICTION. <br />1.01 PRODUCT HANDLING <br />G. DELIVERY: <br />1. GENERAL: DELIVER MATERIALS AND EQUIPMENT WITH FACTORY INSTALLED PROTECTIVE WRAPPING AND <br />SHIPPING SKIDS AND SHIMS; PACKAGE ACCESSORIES IN FACTORY FABRICATED FIBERBOARD TYPE <br />CONTAINERS. <br />H. STORAGE: STORE EQUIPMENT AND PIPING IN A CLEAN, DRY AREA, OFF GROUND. <br />I. DAMAGED: <br />1. GENERAL: DO NOT INSTALL DAMAGED, DENTED OR CRACKED EQUIPMENT; REPLACE AND RETURN DAMAGED <br />UNITS TO EQUIPMENT MANUFACTURER. <br />2. SPRINKLER HEADS: EXTREME CARE SHALL BE TAKEN NOT TO EXPOSE SPRINKLER HEADS TO HIGH <br />TEMPERATURE OR PHYSICAL DAMAGE. <br />1.05 PROJECT CONDITIONS <br />A. SPRINKLER PIPING SCHEDULE: SCHEDULE INSTALLATION SO THAT SPRINKLER PIPING IN AREAS WITH <br />SUSPENDED CEILINGS WILL BE INSTALLED AND TESTED BEFORE CEILING IS ERECTED. <br />1.06 MAINTENANCE <br />A. MAINTENANCE PRODUCTS: FURNISH FOLLOWING PRODUCTS FOR MAINTENANCE: <br />1. SPARE HEADS: FURNISH SPARE HEADS EQUAL TO 1 PERCENT OF TOTAL NUMBER OF HEADS INSTALLED, OR A <br />MINIMUM OF 24 HEADS, WHICHEVER IS LARGER. HEADS SHALL BE PACKED IN A SUITABLE CONTAINER, AND <br />SHALL BE REPRESENTATIVE, AND IN PROPORTION TO QUANTITY OF EACH TYPE AND TEMPERATURE RATING <br />HEADS INSTALLED. <br />2. WRENCHES: FURNISH 2 MINIMUM SPECIAL SPRINKLER HEAD WRENCHES. <br />1.07 WARRANTY <br />A. GENERAL: WARRANTY WORK MEETING PROVISIONS OF CONDITIONS OF THE CONTRACT, EXCEPT WARRANTY <br />SHALL INCLUDE ADDITIONAL PROVISIONS OF THIS ARTICLE. <br />B. COVERAGE: UPON SUCCESSFUL COMPLETION OF REQUIRED TESTS AND SYSTEM BEING PLACED IN SERVICE, <br />CONTRACTOR SHALL WARRANTY SYSTEM FREE OF DEFECTS IN MATERIALS AND WORKMANSHIP. <br />PART2- PRODUCTS <br />2.01 PIPE <br />A. BLACK PIPE: BLACK STEEL SCHEDULE 40 MEETING REQUIREMENTS OF ASTM A53, ASTM A795 AND ASTM A135 <br />WITH MANUFACTURER NAME AND BRAND ON EACH LENGTH OF PIPE. PIPE SHALL BE UL LISTED AND FM <br />APPROVED. PIPE 4 INCHES AND SMALLER SHALL BE BUTT WELDED. LARGER SHALL BE SEAMLESS OR ERW, <br />ASTM A135, GRADE A. <br />B. SCHEDULE 10: WHERE PERMITTED BY BOTH UL AND AUTHORITIES HAVING JURISDICTION OVER THE WORK, PIPE <br />UP TO 5 INCH MAY BE SCHEDULE 10; 6 INCH WITH WALL THICKNESS OF 0.134 INCHES AND 8 INCH WITH WALL <br />THICKNESS OF 0.188 INCHES. SCHEDULE 10 PIPING SHALL NOT BE THREADED OR CUT GROOVED. <br />C. SCHEDULE 5: SCHEDULE 5 PIPE IS NOT ACCEPTABLE IN THE WORK. <br />D. ENDS: <br />1. PIPE LESS THAN SCHEDULE 40 SHALL NOT BE THREADED. <br />2. PLAIN END PIPE AND FITTINGS IS NOT ACCEPTABLE IN THE WORK. <br />F. WELDED JOINTS: FIELD WELDING OF SPRINKLER PIPING IS PERMITTED. HEADERS, SECTIONS OF FEED MAINS, <br />CROSS MAINS, BRANCHLINES OR RISERS MAY BE SHOP WELDED MEETING REQUIREMENTS OF NFPA 13 AND <br />FMRC REQUIREMENTS. <br />G. CORROSIVE AREAS: PIPING LESS THEN SCHEDULE 40 IS NOT ACCEPTABLE IN CORROSIVE AREAS. <br />2.02 FITTINGS <br />A. SCREWED FITTINGS: BLACK CAST IRON, 175 PSI MINIMUM WORKING PRESSURE, MEETING REQUIREMENTS OF <br />ANSI B16.4. <br />B. GROOVED FITTINGS AND COUPLINGS - GENERAL: MALLEABLE OR DUCTILE IRON WITH 300 PSI MINIMUM <br />WORKING PRESSURE. <br />F. PLAIN END FITTINGS: NOT ACCEPTABLE IN THE WORK. <br />2.03 SPRINKLERS <br />A. GENERAL: <br />1. DESCRIPTION: SPRINKLER HEADS SHALL BE OF A TEMPERATURE RATING AND ORIFICE SIZE AS INDICATED ON <br />DRAWINGS, AS REQUIRED BY NFPA STANDARDS AND BE UL LISTED AND MARKED AND FMRC APPROVED. <br />2. ACCEPTABLE MANUFACTURERS: <br />a.TYCO FIRE & BUILDING PRODUCTS. <br />b. RELIABLE. <br />c. VIKING. <br />B. SPRINKLER HEAD TYPES: <br />1. FINISHED CEILING AREAS: <br />d.DESCRIPTION: SPRINKLER HEADS IN FINISHED CEILING AREAS SHALL BE FULLY RECESSED AUTOMATIC AND <br />WITH WHITE COVER. <br />1) ACCEPTABLE PRODUCTS: <br />a) TYCO FIRE & BUILDING PRODUCTS, MODEL RFII. <br />2. HEATING EQUIPMENT: SPRINKLER HEADS IN VICINITY OF HEATING EQUIPMENT SHALL BE OF TEMPERATURE <br />RATING AS REQUIRED BY NFPA 13 ACCORDING TO DISTANCE FROM EQUIPMENT. <br />2.05 HANGERS AND SUPPORTS <br />A. HANGERS AND SUPPORTS USED IN WATER -BASED FIRE SUPPRESSION SYSTEM SHALL BE FM APPROVED AND <br />MEET REQUIREMENTS OF NFPA 13. <br />B. C-CLAMPS SHALL HAVE RETAINING STRAPS. <br />2.07 FIRE EXTINGUISHERS: <br />A. DESCRIPTION: 10LB ABC, SURFACE MOUNTED WITH WALL BRACKET. <br />B. ACCEPTABLE MANUFACTURERS: <br />a. LARSEN. <br />b. FIRE -END & CROKER. <br />c. POTTER-ROEMER. <br />2.08 SIGNS AND TAGS <br />A. SIGNS: SIGNS SHALL BE 6" X 6", 20 GAGE STEEL, PUNCHED, PAINTED FIRE RED WITH WHITE LETTERING AND <br />SUPPORTED WITH CHAINS OR DIRECT MOUNTED. PROVIDE LETTERING STYLE AND SIZE SELECTED BY <br />ARCHITECT FROM NFPA SUGGESTED STYLES. <br />B. TAGS: PROVIDE 1 INCH VALVE TAGS AND VALVE TAG SCHEDULE FOR ALL TYPES OF VALVES. <br />C. PLACARDS: <br />1. PROVIDE METAL HYDRAULIC INFORMATION PLACARDS AT EACH RISER MEETING REQUIREMENTS OF NFPA 13. <br />HYDRAULIC DATA SHALL BE HAND DIE SET ONTO PLACARD. <br />D. ADHESIVE STYLE HYDRAULIC INFORMATION PLACARDS SHALL NOT BE ACCEPTED. <br />PART 3 - EXECUTION <br />3.01 EXAMINATION <br />A. GENERAL: EXAMINE AREAS AND CONDITIONS UNDER WHICH WORK IS TO BE INSTALLED FOR COMPLIANCE WITH <br />REQUIREMENTS OF CONTRACT DOCUMENTS AND TO DETERMINE IF CONDITIONS AFFECTING PERFORMANCE OF <br />WORK ARE SATISFACTORY. DO NOT PROCEED WITH INSTALLATION UNTIL UNSATISFACTORY CONDITIONS HAVE <br />BEEN RESOLVED. COMMENCEMENT OF INSTALLATION SHALL CONSTITUTE ACCEPTANCE OF CONDITIONS. <br />3.02 INSTALLATION - GENERAL <br />A. GENERAL: INSTALL WORK MEETING REQUIREMENTS OF CONTRACT DOCUMENTS, INCLUDING REQUIREMENTS <br />SPECIFIED IN PART 2 OF THIS SECTION AND APPLICABLE REFERENCE SPECIFICATION SECTIONS, AS INDICATED <br />BY FINAL REVIEWED SUBMITTALS FOR WORK AND MEETING INSTRUCTIONS AND RECOMMENDATIONS OF <br />PRODUCT MANUFACTURERS. CONSULT WITH MANUFACTURER FOR CONDITIONS NOT COVERED BY PRINTED <br />INSTRUCTIONS. <br />B. INSTALL IN LOCATIONS AND AT MOUNTING HEIGHT TO MEET REGULATIONS OF AUTHORITIES HAVING <br />JURISDICTION OVER THE WORK. SECURELY FASTEN TO STRUCTURE, SQUARE AND PLUMB; IN ACCORDANCE <br />WITH RECOGNIZED INDUSTRY PRACTICES AND MEETING REQUIREMENTS OF NFPA 13. <br />C. HANGERS AND SUPPORTS: <br />1. HANGER RODS AND INTERMEDIATE HEADERS SHALL BE SIZED MEETING REQUIREMENTS OF NFPA 13. <br />2. COORDINATE HANGER LOCATIONS WITH STRUCTURAL LAYOUT. ADJUST PER PROJECT CONDITIONS, INCLUDING <br />PROVIDING TRAPEZE HANGER, SWAY BRACES, EXPANSION JOINTS, OFFSETS, ADDITIONAL SUPPORTS AND <br />CLOSER SPACING OF HANGERS AS PROJECT CONDITIONS REQUIRE. <br />3. C-CLAMPS SHALL NOT BE USED FOR BRACING OF ANY KIND. <br />4. PROVIDE SEISMIC REQUIREMENTS AND EARTHQUAKE BRACING MEETING REQUIREMENTS OF NFPA 13. <br />D. SPRINKLER HEADS IN FINISHED CEILING TILE AREAS SHALL BE INSTALLED AT A MINIMUM OF 6 INCHES FROM <br />GRID LINE. LOCATE SPRINKLERS IN A SYMMETRICAL PATTERN COORDINATED WITH LIGHTS, DIFFUSERS AND <br />LIKE ITEMS. REFER TO ARCHITECTURAL DRAWINGS, REFLECTED CEILING PLAN, FOR SPRINKLER ARRANGEMENT. <br />E. COORDINATE WORK AS NECESSARY TO INTERFACE PROPERLY WITH OTHER WORK. <br />F. SPRINKLER HEADS SHALL BE PLACED WITH DEFLECTORS PARALLEL TO CEILING OR ROOF SLOPE. CLEARANCE <br />BETWEEN DEFLECTORS AND ROOF CONSTRUCTION MEMBERS SHALL MEET REQUIREMENTS OF NFPA 13. <br />G. SPRINKLER MAIN PIPING RUNNING PARALLEL TO JOISTS SHALL BE LOCATED MIDWAY BETWEEN JOISTS AND <br />SUPPORTED BY INTERMEDIATE HANGERS LOCATED AT PANEL POINTS OF JOISTS. <br />H. PROVIDE AUXILIARY DRAINS FOR TRAPPED PORTIONS OF PIPING MEETING REQUIREMENTS OF NFPA 13. <br />I. RUN NO SPRINKLER PIPING AND DRAIN PIPING IN OR THROUGH ELEVATOR MACHINE ROOMS, ELECTRICAL <br />ROOMS AND CLOSETS, SWITCHBOARD ROOMS, SWITCHGEAR ROOMS, TELEPHONE ROOMS AND LIKE SPACES, <br />EXCEPT INDIVIDUAL BRANCH PIPING SERVING SPRINKLER HEADS. <br />J. SPRINKLER SYSTEMS SHALL BE PROVIDED WITH FLUSHING CONNECTIONS MEETING REQUIREMENTS OF NFPA <br />13. <br />K. KEEP OPEN ENDED PIPING FREE OF DIRT AND DEBRIS BUILD-UP ON INSIDE. SEAL OPEN ENDS OF PIPE DURING <br />CONSTRUCTION USING PLASTIC PIPE OR DUCT TAPE TO INSURE THIS QUALITY. <br />L. PROVIDE PROTECTION OF SPRINKLER HEADS FROM PAINT OVERSPRAY. REMOVE PROTECTIVE COVERING <br />AFTER PAINTING HAS BEEN COMPLETED, COORDINATE WITH PAINTING WORK. <br />M. INSTALL PERMANENT OR TEMPORARY SPRINKLERS IN UNOCCUPIED AREAS DURING CONSTRUCTION PERIOD AS <br />REQUIRED BY LOCAL AUTHORITIES. <br />N. PROVIDE INSPECTOR TEST CONNECTION ON PIPING SYSTEM AT POINT FURTHEST FROM SUPPLY. TEST VALVE <br />SHOULD BE LOCATED 7 FEET ABOVE FLOOR AND DISCHARGE TO OUTSIDE. DISCHARGE SHOULD BE PIPED TO <br />SAFE POINT AND SPLASH BLOCK PROVIDED. PROVIDE SIGHT GLASS. <br />0. BE RESPONSIBLE FOR PROPER FILLING AND VENTING OF WET SPRINKLER AND STANDPIPE SYSTEMS AFTER <br />SYSTEMS HAVE BEEN TESTED AND ACCEPTED. ALSO, AFTER FILLING, SYSTEM SHALL BE REVIEWED FOR LEAKS <br />AND ALL LEAKS AND DRIPS SHALL BE REPAIRED. BE RESPONSIBLE FOR DAMAGED WORK AND WORK OF <br />OTHERS REPLACED, INCLUDING CEILING TILE, WALL COVERINGS, FIXTURES, FURNITURE AND EQUIPMENT. <br />MEP / FP Engineer Design Architect <br />EPSTEIN <br />600 West Fulton <br />Chicago, IL 60661 <br />312.454.9100 <br />EPSTEIN <br />600 West Fulton <br />Chicago, IL 60661 <br />312.454.9100 <br />3.02 IDENTIFICATION <br />A. PROVIDE SIGNS TO CONTROLS, DRAINS, TEST AND ALARM VALVES, EQUIPMENT AND OTHER ITEMS REQUIRING <br />IDENTIFICATION WHICH IDENTIFY THEIR PURPOSE AND FUNCTION OF RESPECTIVE ITEM. <br />B. PIPING IDENTIFICATION SHALL BE PLACED IN CLEARLY VISIBLE LOCATIONS. LABELS AND TAPES OF GENERAL <br />PURPOSE, TYPE, AND COLOR MAY BE USED IN LIEU OF PAINTING, EXCLUDING CORROSIVE ENVIRONMENTS. <br />COLOR SHALL MEET REQUIREMENTS OF ANSI A13.1. PROVIDE ARROW MARKINGS TO INDICATE DIRECTION OF <br />FLOW. SPACING OF IDENTIFICATION MARKING SHALL NOT EXCEED 50 FT. PIPE MARKINGS SHALL BE PROVIDED <br />FOR RISERS AND EACH CHANGE OF DIRECTION FOR PIPING. <br />3.05 TESTING <br />A. TEST SYSTEM MEETING REQUIREMENTS OF NFPA STANDARDS AND REGULATIONS OF AUTHORITIES HAVING <br />JURISDICTION OVER THE WORK. TESTS SHALL BE WITNESSED BY ARCHITECT, INSURANCE UNDERWRITER OF <br />OWNER AND LOCAL AUTHORITIES. SUBMIT REPORTS OF TEST ON NFPA - CONTRACTOR'S MATERIAL AND TEST <br />CERTIFICATE FOR ABOVEGROUND PIPING. FORMS SHALL BE SIGNED BY THOSE WITNESSING TESTS. <br />B. REPAIR OR REPLACE EQUIPMENT AS REQUIRED TO ELIMINATE LEAKAGE MEETING REQUIREMENTS OF NFPA <br />STANDARDS, AND RETEST AS SPECIFIED TO DEMONSTRATE COMPLIANCE. <br />C. BE RESPONSIBLE FOR ASSISTING IN TESTING OF ALARMS AND ADJUSTING RETARD CIRCUIT AFTER COMPLETION <br />OF WIRING. <br />3.06 ADJUSTING AND CLEANING <br />A. REMOVE DEBRIS AND FOREIGN MATERIAL FROM INSIDE OF PIPING PRIOR TO INSTALLATION. AFTER FIRE <br />SPRINKLER PIPING INSTALLATION HAS BEEN COMPLETED AND BEFORE PIPING IS PLACED IN SERVICE, FLUSH <br />ENTIRE SPRINKLER SYSTEM, AS REQUIRED TO REMOVE FOREIGN SUBSTANCES. CONTINUE FLUSHING UNTIL <br />WATER IS CLEAR, AND CHECK TO ENSURE THAT DEBRIS HAS NOT CLOGGED SPRINKLER PIPING. CLEAN <br />EXTERIOR OF PIPE AND EQUIPMENT FROM OIL, SCALE AND OTHER FOREIGN MATERIAL. <br />END OF SECTION <br />E NStC�'�4` <br />TM <br />Nestle Waters North America ' <br />o < <br />Nestle Waters North America <br />�� •?= <br />4330 20th Street = <br />< STATE OF <br />Zephyrhills, Florida 33542-6703 4- <br />972.462.3663 ' o'�i�►' L o RI p <br />NORTH AMERICA 0W,AB 1Le� <br />4 <br />3 <br />09.18.2013 <br />09.11.2013 <br />ISSUE FOR PERMIT <br />ISSUE FOR BIDS <br />2 <br />1 <br />NO. <br />09.03.2013 <br />08.16.2013 <br />DATE <br />CD REVIEW PACKAGE <br />DD REVIEW PACKAGE <br />REVISIONS/ISSUANCES <br />PSTEIN <br />Architecture <br />Chicago <br />Interiors <br />New York <br />Engineering <br />Bucharest <br />Construction <br />Warsaw <br />600 W. Fulton Street <br />Chicago, IL 60661-1259 <br />T 312.454.9100 <br />www.epsteinglobal.com <br />PROJECT NUMBER: <br />12386 <br />PROJECT MANAGER: <br />JK <br />ARCH/ENG: <br />PV <br />SCALE: <br />NTS <br />DRAWN BY: <br />PV <br />CHECKED BY: <br />VD <br />FIRE PROTECTION <br />SPECIFICATIONS <br />FP-002 <br />A. Epstein and Sons Interwhonal, Inc. AN rights reserved. <br />