SECTION 011000 - SUMMARY <br />PART 1 GENERAL <br />1.01 PROJECT <br />A. PROJECT NAME: PET SUPPLIES PLUS - ZEPHYRHILLS, FL. <br />B. THE PROJECT CONSISTS OF RENOVATIONS TO AN EXISTING VACANT <br />BUILDING AND SITE FOR A NEW PET SUPPLIES RETAIL STORE. <br />1.02 CONTRACT DESCRIPTION <br />A. CONTRACT TYPE: A SINGLE PRIME CONTRACT BASED ON A <br />STIPULATED PRICE AS DESCRIBED IN AIA OWNER - CONTRACTOR <br />AGREEMENT. <br />1.03 DESCRIPTION OF ALTERATIONS WORK <br />A. SCOPE OF DEMOLITION AND REMOVAL WORK IS SHOWN ON <br />DRAWINGS. <br />B. RENOVATE THE ENTIRE SPACE, COMPLETE AS INDICATED ON THE <br />DRAWINGS AND SPECIFIED HEREIN: <br />1.04 WORK BY OWNER <br />A. THE OWNER HAS AWARDED CONTRACTS FOR THE SUPPLY, <br />INSTALLATION OR THE SUPPLY AND INSTALLATION OF ITEMS <br />SCHEDULED ON THE DRAWINGS, WHICH WILL COMMENCE ON DATES <br />PRIOR TO TURNOVER FOR OWNER OCCUPANCY. <br />1.05 OWNER OCCUPANCY <br />A. THE OWNER INTENDS TO OCCUPY PORTIONS OF THE BUILDING PRIOR <br />TO THE COMPLETION DATE FOR INSTALLATION OF OWNER PROVIDED <br />MATERIALS. <br />B. SCHEDULE THE WORK TO ACCOMMODATE THE OWNER AND THE <br />OWNERS CONTRACTORS OCCUPANCY. <br />1.06 CONTRACTOR USE OF SITE <br />A. CONSTRUCTION OPERATIONS: LIMITED TO AREAS NOTED ON <br />DRAWINGS. <br />B. ARRANGE USE OF SITE TO ALLOW: <br />1. WORK BY OTHERS. <br />C. PROVIDE ACCESS TO AND FROM SITE AS REQUIRED BY LAW AND BY <br />THE OWNER: <br />1. EMERGENCY BUILDING EXITS DURING CONSTRUCTION: KEEP <br />ALL EXITS AT ADJACENT BUILDING OPERATING TENANTS AND <br />AS REQUIRED BY CODE OPEN DURING CONSTRUCTION PERIOD, <br />PROVIDE TEMPORARY EXIT SIGNS IF EXIT ROUTES ARE <br />TEMPORARILY ALTERED. <br />2. DO NOT OBSTRUCT ROADWAYS, SIDEWALKS, OR OTHER <br />PUBLIC WAYS WITHOUT PERMIT. <br />3. MAINTAIN ACCESS TO ADJACENT PROPERTY, COORDINATE <br />WITH CONSTRUCTION LIMITS ACCESS. <br />D. EXISTING BUILDING SPACES MAY NOT BE USED FOR STORAGE. <br />1.07 WORK SEQUENCE <br />A. COORDINATE CONSTRUCTION SCHEDULE AND OPERATIONS WITH THE <br />ARCHITECTS. <br />PART 2 PRODUCTS - NOT USED <br />PART 3 EXECUTION - NOT USED <br />END OF SECTION <br />SECTION 013000 - ADMINISTRATIVE REQUIREMENTS <br />PART 1 GENERAL <br />1.01 SECTION INCLUDES <br />A. <br />PROGRESS REPORTING. <br />B. <br />CONSTRUCTION PROGRESS SCHEDULE. <br />C. <br />PROGRESS PHOTOGRAPHS. <br />D. <br />COORDINATION DRAWINGS. <br />E. <br />SUBMITTALS FOR REVIEW, INFORMATION, AND PROJECT CLOSEOUT. <br />F. <br />SUBMITTAL PROCEDURES. <br />PART 2 PRODUCTS - NOT USED <br />PART 3 EXECUTION <br />3.01 PROGRESS REPORTING <br />A. <br />SCHEDULE AND ADMINISTER REPORTING THROUGHOUT PROGRESS <br />OF THE WORK AT MAXIMUM WEEKLY INTERVALS OR AS REQUESTED <br />BY PET SUPPLIES PLUS REPRESENTATIVES. <br />B. <br />REPORT ITEMS: <br />1. REVIEW OF WORK PROGRESS. <br />2. FIELD OBSERVATIONS, PROBLEMS, AND DECISIONS. <br />3. IDENTIFICATION OF PROBLEMS WHICH IMPEDE PLANNED <br />PROGRESS. <br />4. REVIEW OF SUBMITTALS SCHEDULE AND STATUS OF <br />SUBMITTALS. <br />5. REVIEW OF OFF -SITE FABRICATION, OWNER PROVIDED ITEMS <br />AND DELIVERY SCHEDULES. <br />6. MAINTENANCE OF PROGRESS SCHEDULE. <br />7. CORRECTIVE MEASURES TO REGAIN PROJECTED SCHEDULES. <br />8. PLANNED PROGRESS DURING SUCCEEDING WORK PERIOD. <br />9. MAINTENANCE OF QUALITY AND WORK STANDARDS. <br />10. EFFECT OF PROPOSED CHANGES ON PROGRESS SCHEDULE <br />AND COORDINATION. <br />11. PROGRESS PHOTOS, REFER TO REQUIREMENTS BELOW. <br />12. OTHER BUSINESS RELATING TO WORK. <br />C. <br />PREPARE REPORT AND DISTRIBUTE VIA EMAIL ON THURSDAY <br />MORNING OF EACH WEEK. DISTRIBUTION TO INCLUDE OWNER, <br />ARCHITECT. <br />3.02 CONSTRUCTION PROGRESS SCHEDULE <br />A. <br />CONSTRUCTION SCHEDULE SHALL BE ORGANIZED IN BAR CHART <br />FORMAT WITH SEPARATE BAR FOR EACH SUBSTRATE CATEGORY OF <br />WORK, ORGANIZE IN CHRONOLOGICAL ORDER ACCORDING TO THE <br />START DATE FOR EACH ACTIVITY OF WORK. IDENTIFY EACH ACTIVITY <br />BY APPLICABLE SPECIFICATION REFERENCE NUMBER. <br />B. <br />WITHIN 3 DAYS AFTER DATE ESTABLISHED IN NOTICE TO PROCEED, <br />SUBMIT PRELIMINARY SCHEDULE FOR CONSTRUCTION OPERATIONS <br />FOR THE DURATION OF THE PROJECT. INCLUDE SCHEDULE FOR <br />ORDERING AND DELIVERY OF OWNER SUPPLIED ITEMS. <br />C. <br />IF PRELIMINARY SCHEDULE REQUIRES REVISION AFTER REVIEW, <br />SUBMIT REVISED SCHEDULE WITHIN 2 DAYS. <br />D. <br />WITHIN 10 DAYS AFTER JOINT REVIEW, SUBMIT COMPLETE SCHEDULE. <br />E. <br />SUBMIT UPDATED SCHEDULE WITH EACH APPLICATION FOR PAYMENT. <br />3.03 PROGRESS PHOTOGRAPHS <br />A. <br />PROVIDE PHOTOGRAPHS OF SITE AND CONSTRUCTION THROUGHOUT <br />PROGRESS OF WORK PRODUCED BY AN EXPERIENCED <br />PHOTOGRAPHER, ACCEPTABLE TO PET SUPPLIES PLUS AND <br />ARCHITECT. <br />B. <br />PHOTOS SHALL BE DIGITAL .JPG IMAGES ASSEMBLED IN .ZIP FILE AND <br />EMAILED WITH WEEKLY PROGRESS REPORT. <br />C. <br />TAKE PHOTOGRAPHS FOR SUBMITTAL WITH WEEKLY PROGRESS <br />REPORT OF MINIMUM ITEMS AS FOLLOWS AND APPLICABLE TO <br />WORKSCOPE OF PROJECT: <br />1. DEMOLITION <br />2. EXCAVATION AND UNDERGROUND PLUMBING <br />3. ROUGH FRAMING INCLUDING ALL CONCEALED BLOCKING <br />4. PLUMBING WALL ROUGH IN <br />5. ELECTRICAL WALL ROUGH IN <br />6. HVAC ROUGH IN <br />7. ELECTRICAL OVERHEAD <br />8. WALLS PRIOR TO GYPSUM BOARD <br />9. WALLS AFTER GYPSUM BOARD <br />10. CEILING GRID INSTALLATION <br />11. FLOOR TILE <br />12. OWNER SUPPLIED CABINETRY AND KITCHEN EQUIPMENT AT <br />DELIVERY <br />13. OWNER SUPPED CABINETRY AND KITCHEN EQUIPMENT AT <br />INSTALLATION <br />14. PAINTING <br />15. INTERIOR FINISHES AND DECOR <br />16. EXTERIOR DRIVE THRU RELATED WORK <br />17. EXTERIOR LIFT, LOADING AREA AND RELATED WORK <br />18. ADDITIONAL ITEMS AS REQUESTED BY OWNER, ARCHITECT <br />AND PET SUPPLIES PLUS <br />3.04 COORDINATION <br />DRAWINGS AND FIELD DIMENSIONS <br />A. <br />PROVIDE INFORMATION REQUIRED BY OWNER, ARCHITECT OR PET <br />SUPPLIES PLUS VENDOR FOR PREPARATION OF COORDINATION <br />DRAWINGS. <br />3.05 SUBMITTALS FOR REVIEW <br />A. <br />WHEN THE FOLLOWING ARE SPECIFIED IN INDIVIDUAL SECTIONS, <br />SUBMIT THEM FOR REVIEW: <br />1. PRODUCT DATA. <br />2. SHOP DRAWINGS. <br />3. SAMPLES FOR SELECTION. <br />4. SAMPLES FOR VERIFICATION. <br />B. <br />SUBMIT TO ARCHITECT FOR REVIEW FOR THE LIMITED PURPOSE OF <br />CHECKING FOR CONFORMANCE WITH INFORMATION GIVEN AND THE <br />DESIGN CONCEPT EXPRESSED IN THE CONTRACT DOCUMENTS. <br />C. <br />SAMPLES WILL BE REVIEWED ONLY FOR AESTHETIC, COLOR, OR <br />FINISH SELECTION. <br />D. <br />AFTER REVIEW, PROVIDE COPIES AND DISTRIBUTE IN ACCORDANCE <br />WITH SUBMITTAL PROCEDURES ARTICLE BELOW AND FOR RECORD <br />DOCUMENTS PURPOSES DESCRIBED IN SECTION 017700 - CLOSEOUT <br />SUBMITTALS. <br />3.06 SUBMITTALS FOR INFORMATION <br />A. <br />WHEN THE FOLLOWING ARE SPECIFIED IN INDIVIDUAL SECTIONS, <br />SUBMIT THEM FOR INFORMATION: <br />1. DESIGN DATA. <br />2. CERTIFICATES. <br />3. TEST REPORTS. <br />4. INSPECTION REPORTS. <br />5. MANUFACTURER'S INSTRUCTIONS. <br />6. MANUFACTURER'S FIELD REPORTS. <br />7. OTHER TYPES INDICATED. <br />B. <br />SUBMIT FOR ARCHITECTS KNOWLEDGE AS CONTRACT <br />ADMINISTRATOR OR FOR OWNER. NO ACTION WILL BE TAKEN. <br />3.07 SUBMITTALS FOR PROJECT CLOSEOUT <br />A. <br />WHEN THE FOLLOWING ARE SPECIFIED IN INDIVIDUAL SECTIONS, <br />SUBMIT THEM AT PROJECT CLOSEOUT: <br />1. PROJECT RECORD DOCUMENTS. <br />2. OPERATION AND MAINTENANCE DATA. <br />3. WARRANTIES. <br />4. OTHER TYPES AS INDICATED. <br />B. <br />SUBMIT FOR OWNER'S BENEFIT DURING AND AFTER PROJECT <br />COMPLETION. <br />END OF SECTION <br />SECTION 014000 - QUALITY REQUIREMENTS <br />PART 1 GENERAL. <br />1.01 REFERENCES AND STANDARDS <br />A. <br />FOR PRODUCTS AND WORKMANSHIP SPECIFIED BY REFERENCE TO A <br />DOCUMENT OR DOCUMENTS NOT INCLUDED IN THE PROJECT MANUAL, <br />ALSO REFERRED TO AS REFERENCE STANDARDS, COMPLY WITH <br />REQUIREMENTS OF THE STANDARD, EXCEPT WHEN MORE RIGID <br />REQUIREMENTS ARE SPECIFIED OR ARE REQUIRED BY APPLICABLE <br />CODES. <br />B. <br />CONFORM TO REFERENCE STANDARD OF DATE OF ISSUE CURRENT <br />ON DATE OF CONTRACT DOCUMENTS, EXCEPT WHERE A SPECIFIC <br />DATE IS ESTABLISHED BY APPLICABLE CODE. <br />C. <br />OBTAIN COPIES OF STANDARDS WHERE REQUIRED BY PRODUCT <br />SPECIFICATION SECTIONS. <br />D. <br />MAINTAIN COPY AT PROJECT SITE DURING SUBMITTALS, PLANNING, <br />AND PROGRESS OF THE SPECIFIC WORK, UNTIL SUBSTANTIAL <br />COMPLETION. <br />E. <br />SHOULD SPECIFIED REFERENCE STANDARDS CONFLICT WITH <br />CONTRACT DOCUMENTS, REQUEST CLARIFICATION FROM THE <br />ARCHITECTS BEFORE PROCEEDING. <br />F. <br />NEITHER THE CONTRACTUAL RELATIONSHIPS, DUTIES, OR <br />RESPONSIBILITIES OF THE PARTIES IN CONTRACT NOR THOSE OF THE <br />ARCHITECTS SHALL BE ALTERED FROM THE CONTRACT DOCUMENTS <br />BY MENTION OR INFERENCE OTHERWISE IN ANY REFERENCE <br />DOCUMENT. <br />PART 2 PRODUCTS - NOT USED <br />PART 3 EXECUTION <br />3.01 CONTROL OF INSTALLATION <br />A. <br />MONITOR QUALITY CONTROL OVER SUPPLIERS, MANUFACTURERS, <br />PRODUCTS, SERVICES, SITE CONDITIONS, AND WORKMANSHIP, TO <br />PRODUCE WORK OF SPECIFIED QUALITY. <br />B. <br />COMPLY WITH MANUFACTURERS' INSTRUCTIONS, INCLUDING EACH <br />STEP IN SEQUENCE. <br />C. <br />SHOULD MANUFACTURERS' INSTRUCTIONS CONFLICT WITH <br />CONTRACT DOCUMENTS, REQUEST CLARIFICATION FROM THE <br />ARCHITECTS BEFORE PROCEEDING. <br />D. <br />COMPLY WITH SPECIFIED STANDARDS AS MINIMUM QUALITY FOR THE <br />WORK EXCEPT WHERE MORE STRINGENT TOLERANCES, CODES, OR <br />SPECIFIED REQUIREMENTS INDICATE HIGHER STANDARDS OR MORE <br />PRECISE WORKMANSHIP. <br />E. <br />HAVE WORK PERFORMED BY PERSONS QUALIFIED TO PRODUCE <br />REQUIRED AND SPECIFIED QUALITY. <br />F. <br />VERIFY THAT FIELD MEASUREMENTS ARE AS INDICATED ON SHOP <br />DRAWINGS OR AS INSTRUCTED BY THE MANUFACTURER. <br />G. <br />SECURE PRODUCTS IN PLACE WITH POSITIVE ANCHORAGE DEVICES <br />DESIGNED AND SIZED TO WITHSTAND STRESSES, VIBRATION, <br />PHYSICAL DISTORTION, AND DISFIGUREMENT. <br />3.02 TOLERANCES <br />A. <br />MONITOR FABRICATION AND INSTALLATION TOLERANCE CONTROL OF <br />PRODUCTS TO PRODUCE ACCEPTABLE WORK. DO NOT PERMIT <br />TOLERANCES TO ACCUMULATE. <br />B. <br />COMPLY WITH MANUFACTURERS' TOLERANCES. SHOULD <br />MANUFACTURERS' TOLERANCES CONFLICT WITH CONTRACT <br />DOCUMENTS, REQUEST CLARIFICATION FROM THE ARCHITECTS <br />BEFORE PROCEEDING. <br />C. <br />ADJUST PRODUCTS TO APPROPRIATE DIMENSIONS, POSITION BEFORE <br />SECURING PRODUCTS IN PLACE. <br />3.03 DEFECT ASSESSMENT <br />A. <br />REPLACE WORK OR PORTIONS OF THE WORK NOT CONFORMING TO <br />SPECIFIED REQUIREMENTS. <br />B. <br />IF, IN THE OPINION OF THE ARCHITECTS, IT IS NOT PRACTICAL TO <br />REMOVE AND REPLACE THE WORK, THE ARCHITECTS WILL DIRECT AN <br />APPROPRIATE REMEDY OR ADJUST PAYMENT. <br />END OF SECTION <br />SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS <br />PART 1 GENERAL <br />1.01 TEMPORARY UTILITIES <br />A. USE TRIGGER -OPERATED NOZZLES FOR WATER HOSES, TO AVOID <br />WASTE OF WATER. <br />1.02 TEMPORARY SANITARY FACILITIES <br />A. PROVIDE AND MAINTAIN REQUIRED FACILITIES AND ENCLOSURES. <br />PROVIDE AT TIME OF PROJECT MOBILIZATION. <br />B. USE OF EXISTING FACILITIES IS PERMITTED. <br />C. MAINTAIN DAILY IN CLEAN AND SANITARY CONDITION. <br />1.03 BARRIERS <br />A. PROVIDE BARRIERS TO PREVENT UNAUTHORIZED ENTRY TO <br />CONSTRUCTION AREAS, TO ALLOW FOR OWNER'S USE OF SITE AND <br />TO PROTECT EXISTING FACILITIES AND ADJACENT PROPERTIES FROM <br />DAMAGE FROM CONSTRUCTION OPERATIONS AND DEMOLITION. <br />B. PROVIDE BARRICADES AND COVERED WALKWAYS REQUIRED BY <br />GOVERNING AUTHORITIES FOR PUBLIC RIGHTS -OF -WAY AND FOR <br />PUBLIC ACCESS TO EXISTING BUILDING. <br />C. PROTECT NON -OWNED VEHICULAR TRAFFIC, STORED MATERIALS, <br />SITE, AND STRUCTURES FROM DAMAGE. <br />1.04 EXTERIOR ENCLOSURES <br />A. PROVIDE TEMPORARY INSULATED WEATHER TIGHT CLOSURE OF <br />EXTERIOR OPENINGS TO ACCOMMODATE ACCEPTABLE WORKING <br />CONDITIONS AND PROTECTION FOR PRODUCTS, TO ALLOW FOR <br />TEMPORARY HEATING AND MAINTENANCE OF REQUIRED AMBIENT <br />TEMPERATURES IDENTIFIED IN INDIVIDUAL SPECIFICATION SECTIONS, <br />AND TO PREVENT ENTRY OF UNAUTHORIZED PERSONS. PROVIDE <br />ACCESS DOORS WITH SELF -CLOSING HARDWARE AND LOCKS. <br />1.05 SECURITY <br />A. PROVIDE SECURITY AND FACILITIES TO PROTECT WORK, EXISTING <br />FACILITIES, AND THE OWNER'S OPERATIONS FROM UNAUTHORIZED <br />ENTRY, VANDALISM, OR THEFT. <br />1.06 VEHICULAR ACCESS AND PARKING <br />A. COORDINATE ACCESS AND HAUL ROUTES WITH GOVERNING <br />AUTHORITIES AND THE OWNER. <br />B. PROVIDE AND MAINTAIN ACCESS TO FIRE HYDRANTS, FREE OF <br />OBSTRUCTIONS. <br />C. PROVIDE MEANS OF REMOVING MUD FROM VEHICLE WHEELS BEFORE <br />ENTERING STREETS. <br />D. PROVIDE TEMPORARY PARKING AREAS TO ACCOMMODATE <br />CONSTRUCTION PERSONNEL. WHEN SITE SPACE IS NOT ADEQUATE, <br />PROVIDE ADDITIONAL OFF -SITE PARKING. <br />1.07 WASTE REMOVAL <br />A. PROVIDE WASTE REMOVAL FACILITIES AND SERVICES AS REQUIRED <br />TO MAINTAIN THE SITE IN CLEAN AND ORDERLY CONDITION. <br />B. PROVIDE CONTAINERS WITH LIDS. REMOVE TRASH FROM SITE <br />PERIODICALLY. <br />C. IF MATERIALS TO BE RECYCLED OR RE -USED ON THE PROJECT MUST <br />BE STORED ON -SITE, PROVIDE SUITABLE NON-COMBUSTIBLE <br />CONTAINERS, LOCATE CONTAINERS HOLDING FLAMMABLE MATERIAL <br />OUTSIDE THE STRUCTURE UNLESS OTHERWISE APPROVED BY THE <br />AUTHORITIES HAVING JURISDICTION. <br />D. OPEN FREE -FALL CHUTES ARE NOT PERMITTED. TERMINATE CLOSED <br />CHUTES INTO APPROPRIATE CONTAINERS WITH LIDS. <br />1.08 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS <br />A. REMOVE TEMPORARY UTILITIES, EQUIPMENT, FACILITIES, MATERIALS, <br />PRIOR TO SUBSTANTIAL COMPLETION INSPECTION. <br />B. REMOVE UNDERGROUND INSTALLATIONS TO A MINIMUM DEPTH OF 2 <br />FEET (600 MM) OR AS INDICATED ON DRAWINGS. GRADE SITE AS <br />INDICATED. <br />C. CLEAN AND REPAIR DAMAGE CAUSED BY INSTALLATION OR USE OF <br />TEMPORARY WORK. <br />D. RESTORE EXISTING FACILITIES USED DURING CONSTRUCTION TO <br />ORIGINAL CONDITION. <br />PART 2 PRODUCTS - NOT USED <br />PART 3 EXECUTION - NOT USED <br />END OF SECTION <br />SECTION 016000 - PRODUCT REQUIREMENTS <br />PART 1 GENERAL <br />1.01 REFERENCES <br />A. <br />NFPA 70 - NATIONAL ELECTRICAL CODE, NATIONAL FIRE PROTECTION <br />ASSOCIATION, 2002. <br />1.02 SUBMITTALS <br />A. <br />PROPOSED PRODUCTS LIST: SUBMIT LIST OF MAJOR PRODUCTS <br />PROPOSED FOR USE, WITH NAME OF MANUFACTURER, TRADE NAME, <br />AND MODEL NUMBER OF EACH PRODUCT. <br />1. SUBMIT WITHIN 15 DAYS AFTER DATE OF AGREEMENT. <br />B. <br />PRODUCT DATA SUBMITTALS: SUBMIT MANUFACTURER'S STANDARD <br />PUBLISHED DATA. MARK EACH COPY TO IDENTIFY APPLICABLE <br />PRODUCTS, MODELS, OPTIONS, AND OTHER DATA. SUPPLEMENT <br />MANUFACTURERS' STANDARD DATA TO PROVIDE INFORMATION <br />SPECIFIC TO THIS PROJECT. <br />C. <br />SHOP DRAWING SUBMITTALS: PREPARED SPECIFICALLY FOR THIS <br />PROJECT. <br />D. <br />SAMPLE SUBMITTALS: ILLUSTRATE FUNCTIONAL AND AESTHETIC <br />CHARACTERISTICS OF THE PRODUCT, WITH INTEGRAL PARTS AND <br />ATTACHMENT DEVICES. COORDINATE SAMPLE SUBMITTALS FOR <br />INTERFACING WORK. <br />1. FOR SELECTION FROM STANDARD FINISHES, SUBMIT SAMPLES <br />OF THE FULL RANGE OF THE MANUFACTURER'S STANDARD <br />COLORS, TEXTURES, AND PATTERNS. <br />E. <br />INDICATE UTILITY AND ELECTRICAL CHARACTERISTICS, UTILITY <br />CONNECTION REQUIREMENTS, AND LOCATION OF UTILITY OUTLETS <br />FOR SERVICE FOR FUNCTIONAL EQUIPMENT AND APPLIANCES. <br />PART 2 PRODUCTS <br />2.01 EXISTING PRODUCTS <br />A. <br />EXISTING MATERIALS AND EQUIPMENT INDICATED TO BE REMOVED, <br />BUT NOT TO BE RE -USED, RELOCATED, REINSTALLED, DELIVERED TO <br />THE THE OWNER, OR OTHERWISE INDICATED AS TO REMAIN THE <br />PROPERTY OF THE THE OWNER, BECOME THE PROPERTY OF THE, <br />REMOVE FROM SITE. <br />2.02 NEW <br />PRODUCTS <br />A. <br />PROVIDE NEW PRODUCTS UNLESS SPECIFICALLY REQUIRED OR <br />PERMITTED BY THE CONTRACT DOCUMENTS. <br />B. <br />DO NOT USE PRODUCTS HAVING ANY OF THE FOLLOWING <br />CHARACTERISTICS: <br />1. MADE USING OR CONTAINING CFC'S OR HCFC'S. <br />2.03 PRODUCT OPTIONS <br />A. <br />PRODUCTS SPECIFIED BY REFERENCE STANDARDS OR BY <br />DESCRIPTION ONLY: USE ANY PRODUCT MEETING THOSE <br />STANDARDS OR DESCRIPTION. <br />B. <br />PRODUCTS SPECIFIED BY NAMING ONE OR MORE MANUFACTURERS: <br />USE A PRODUCT OF ONE OF THE MANUFACTURERS NAMED AND <br />MEETING SPECIFICATIONS, NO OPTIONS OR SUBSTITUTIONS <br />ALLOWED. <br />C. <br />PRODUCTS SPECIFIED BY NAMING ONE OR MORE MANUFACTURERS <br />WITH A PROVISION FOR SUBSTITUTIONS: SUBMIT A REQUEST FOR <br />SUBSTITUTION FOR ANY MANUFACTURER NOT NAMED. <br />2.04 SPARE PARTS AND MAINTENANCE PRODUCTS <br />A. <br />PROVIDE SPARE PARTS, MAINTENANCE, AND EXTRA PRODUCTS OF <br />TYPES AND IN QUANTITIES SPECIFIED IN INDIVIDUAL SPECIFICATION <br />SECTIONS. <br />B. <br />DELIVER TO PROJECT SITE, OBTAIN RECEIPT PRIOR TO FINAL <br />PAYMENT. <br />PART 3 EXECUTION <br />3.01 SUBSTITUTION PROCEDURES <br />A. <br />INSTRUCTIONS TO BIDDERS SPECIFY TIME RESTRICTIONS FOR <br />SUBMITTING REQUESTS FOR SUBSTITUTIONS DURING THE BIDDING <br />PERIOD. COMPLY WITH REQUIREMENTS SPECIFIED IN THIS SECTION. <br />B. <br />THE ARCHITECTS AND THE OWNER WILL CONSIDER REQUESTS FOR <br />SUBSTITUTIONS ONLY WITHIN 15 DAYS AFTER DATE OF AGREEMENT. <br />C. <br />SUBSTITUTIONS WILL NOT BE CONSIDERED WHEN A PRODUCT <br />BECOMES UNAVAILABLE THROUGH NO FAULT OF THE OWNER. <br />D. <br />DOCUMENT EACH REQUEST WITH COMPLETE DATA SUBSTANTIATING <br />COMPLIANCE OF PROPOSED SUBSTITUTION WITH CONTRACT <br />DOCUMENTS. <br />E. <br />A REQUEST FOR SUBSTITUTION CONSTITUTES A REPRESENTATION <br />THAT THE SUBMITTER: <br />1. HAS INVESTIGATED PROPOSED PRODUCT AND DETERMINED <br />THAT IT MEETS OR EXCEEDS THE QUALITY LEVEL OF THE <br />SPECIFIED PRODUCT. <br />2. WILL PROVIDE THE SAME WARRANTY FOR THE SUBSTITUTION <br />AS FOR THE SPECIFIED PRODUCT. <br />3. WILL COORDINATE INSTALLATION AND MAKE CHANGES TO <br />OTHER WORK, WHICH MAY BE REQUIRED FOR THE WORK TO <br />BE COMPLETE WITH NO ADDITIONAL COST TO THE OWNER. <br />4. WAIVES CLAIMS FOR ADDITIONAL COSTS OR TIME EXTENSION, <br />WHICH MAY SUBSEQUENTLY BECOME APPARENT. <br />5. WILL REIMBURSE THE OWNER AND THE ARCHITECTS FOR <br />REVIEW OR REDESIGN SERVICES ASSOCIATED WITH <br />RE -APPROVAL BY AUTHORITIES. <br />F. <br />SUBSTITUTIONS WILL NOT BE CONSIDERED WHEN THEY ARE <br />INDICATED OR IMPLIED ON SHOP DRAWING OR PRODUCT DATA <br />SUBMITTALS, WITHOUT SEPARATE WRITTEN REQUEST, OR WHEN <br />ACCEPTANCE WILL REQUIRE REVISION TO THE CONTRACT <br />DOCUMENTS. <br />G. <br />SUBSTITUTION SUBMITTAL PROCEDURE: <br />1. SUBMIT THREE COPIES OF REQUEST FOR SUBSTITUTION FOR <br />CONSIDERATION. LIMIT EACH REQUEST TO ONE PROPOSED <br />SUBSTITUTION. <br />2. SUBMIT SHOP DRAWINGS, PRODUCT DATA, AND CERTIFIED <br />TEST RESULTS ATTESTING TO THE PROPOSED PRODUCT <br />EQUIVALENCE. BURDEN OF PROOF IS ON PROPOSER. <br />3. THE ARCHITECTS WILL NOTIFY IN WRITING OF DECISION TO <br />ACCEPT OR REJECT REQUEST. <br />3.02 OWNER -SUPPLIED PRODUCTS <br />A. <br />REFER TO DRAWINGS FOR IDENTIFICATION OF OWNER -SUPPLIED <br />PRODUCTS. <br />B. <br />OWNER'S RESPONSIBILITIES: <br />1. ARRANGE FOR AND DELIVER APPLICABLE OWNER REVIEWED <br />SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, TO <br />CONTRACTOR. <br />2. ARRANGE AND PAY FOR PRODUCT DELIVERY TO SITE. <br />3. ARRANGE FOR MANUFACTURERS' WARRANTIES, INSPECTIONS, <br />AND SERVICE. <br />C. <br />CONTRACTOR'S RESPONSIBILITIES: <br />1. REVIEW OWNER REVIEWED SHOP DRAWINGS, PRODUCT DATA, <br />AND SAMPLES. <br />2. RECEIVE AND UNLOAD PRODUCTS AT SITE, INSPECT FOR <br />COMPLETENESS OR DAMAGE. ALL DAMAGED OR MISSING <br />MATERIALS SHALL BE DOCUMENTED TO OWNER & SUPPLIER <br />WITHIN THREE DAYS OF RECEIVING DELIVERY OF MATERIALS. <br />DAMAGED OR MISSING MATERIALS IDENTIFIED AFTER THREE <br />DAYS FROM DELIVERY ARE THE CONTRACTORS <br />RESPONSIBILITY TO REPLACE AT CONTRACTORS COST FOR <br />MATERIAL AND SHIPPING. COORDINATE REPLACEMENT WITH <br />OWNER AND SUPPLIER. <br />3. ALL MATERIALS SHALL BE STORED IN A SECURE LOCATION, <br />PROTECT FROM DAMAGE & THEFT. <br />4. HANDLE, STORE, INSTALL AND FINISH PRODUCTS. <br />3.03 TRANSPORTATION AND HANDLING <br />A. <br />COORDINATE SCHEDULE OF PRODUCT DELIVERY TO DESIGNATED <br />PREPARED AREAS IN ORDER TO MINIMIZE SITE STORAGE TIME AND <br />POTENTIAL DAMAGE TO STORED MATERIALS. <br />B. <br />TRANSPORT AND HANDLE PRODUCTS IN ACCORDANCE WITH <br />MANUFACTURER'S INSTRUCTIONS. <br />C. <br />TRANSPORT MATERIALS IN COVERED TRUCKS TO PREVENT <br />CONTAMINATION OF PRODUCT AND LITTERING OF SURROUNDING <br />AREAS. <br />D. <br />PROMPTLY INSPECT SHIPMENTS TO ENSURE THAT PRODUCTS <br />COMPLY WITH REQUIREMENTS, QUANTITIES ARE CORRECT, AND <br />PRODUCTS ARE UNDAMAGED. <br />E. <br />PROVIDE EQUIPMENT AND PERSONNEL TO HANDLE PRODUCTS BY <br />METHODS TO PREVENT SOILING, DISFIGUREMENT, OR DAMAGE. <br />F. <br />ARRANGE FOR THE RETURN OF PACKING MATERIALS, SUCH AS WOOD <br />PALLETS, WHERE ECONOMICALLY FEASIBLE. <br />3.04 STORAGE AND PROTECTION <br />A. <br />DESIGNATE RECEIVING/STORAGE AREAS FOR INCOMING PRODUCTS <br />SO THAT THEY ARE DELIVERED ACCORDING TO INSTALLATION <br />SCHEDULE AND PLACED CONVENIENT TO WORK AREA IN ORDER TO <br />MINIMIZE WASTE DUE TO EXCESSIVE MATERIALS HANDLING AND <br />MISAPPLICATION. <br />B. <br />STORE AND PROTECT PRODUCTS IN ACCORDANCE WITH <br />MANUFACTURERS' INSTRUCTIONS. <br />C. <br />STORE WITH SEALS AND LABELS INTACT AND LEGIBLE. <br />D. <br />STORE SENSITIVE PRODUCTS IN WEATHER TIGHT, CLIMATE <br />CONTROLLED, ENCLOSURES IN AN ENVIRONMENT FAVORABLE TO <br />PRODUCT. <br />E. <br />FOR EXTERIOR STORAGE OF FABRICATED PRODUCTS, PLACE ON <br />SLOPED SUPPORTS ABOVE GROUND. <br />F. <br />COVER PRODUCTS SUBJECT TO DETERIORATION WITH IMPERVIOUS <br />SHEET COVERING. PROVIDE VENTILATION TO PREVENT <br />CONDENSATION AND DEGRADATION OF PRODUCTS. <br />G. <br />PREVENT CONTACT WITH MATERIAL THAT MAY CAUSE CORROSION, <br />DISCOLORATION, OR STAINING. <br />H. <br />PROVIDE EQUIPMENT AND PERSONNEL TO STORE PRODUCTS BY <br />METHODS TO PREVENT SOILING, DISFIGUREMENT, OR DAMAGE. <br />I. <br />ARRANGE STORAGE OF PRODUCTS TO PERMIT ACCESS FOR <br />INSPECTION. PERIODICALLY INSPECT TO VERIFY PRODUCTS ARE <br />UNDAMAGED AND ARE MAINTAINED IN ACCEPTABLE CONDITION. <br />END OF SECTION <br />Z <br />0 <br />0 <br />W <br />Q <br />W <br />ce- <br />II01.4fe,,,.Ills OFr <br />,0. <br />J (n <br />Z <br />D0 <br />UQ <br />WV <br />F_ LL <br />=U <br />UW <br />w♦♦� <br />VJ <br />ISSUED FOR: <br />PERMIT <br />03.14.19 <br />BID <br />03.14.19 <br />CONSTRUCTION <br />00.00.00 <br />REVIEW SET <br />03.14.19 <br />JOB NO. <br />18390 <br />AS1 00 <br />