Laserfiche WebLink
OPTIONAL MONOLITHIC FOUNDATION AND SLAB <br />1) THE FOOTERS FOR THE FOUNDATION WILL BE A CONTINUOUS <br />MONOLITHIC / 3000 PSI FOOTER WITH (2) *5 HORIZONTAL <br />REBARS ON ROD CHAIRS SPACED NO MORE THAN 48" OC, <br />THE RODS WILL BE TIED TO THE CHAIRS, THE MIN LAP FOR IS <br />25" AND ALL LAPS WILL BE TIED, <br />2) A 4" / 3000 PSI CONCRETE SLAB OVER roxro 10/10 WIRE <br />MESH AND A ro MIL.VISQUEEN VAPOR BARRIER, THE SOIL WILL <br />BE TREATED FOR TERMITES AND BE CLEAN AND COMPACTED, <br />3) THIS FOUNDATION IS BASED ON A 2000 PSF SOIL BEARING <br />CAPACITY, <br />4) THE BUILDING SITE SHALL BE SCRAPED TO REMOVE <br />ALL ORGANIC MATERIALS. ANY ADDITIONAL FILL PLACED ON THE <br />BUILDING PAD AREA SHALL BE COMPACTED SUCH THAT IT CAN <br />ADEQUATELY SUPPORT A 2000 P.S.F. FOUNDATION LOADING. <br />THE SLAB SHALL BE PLACED OVER A roMIL VAPOR BARRIER ON <br />CLEAN ADEQUATELY COMPACTED AND TERMITE POISONED SOIL, <br />THE CONCRETE UTILIZED IN THE FOUNDATION AND SLABS SHALL <br />HAVE A MINIMUM 28 DAY COMPRESSIVE STRENGTH OF 3000 P.S.I. <br />5) REINFORCING STEEL SHALL BE GRADE 40 MINIMUM AND <br />IDENTIFIED IN ACCORDANCE WITH ASTM A -615, LAP SPLICES, WHERE <br />REQUIRED SHALL BE A MINIMUM OF 25" FOR *5 REBAR, 30" FOR *ro <br />REBAR AND 35" FOR *-1 REBAR. <br />2x *2 SPRUCE FRAME WALL <br />FIBERMESH MAY BE USED ONLY IF IT HAS <br />THE roxro 10/10 WIRE MESH REINFORCEMENT, <br />1/2"x8" J-BOLTS 32" OC MAX. <br />*2 PT BOTTOM PLATE <br />------------------ <br />FINISHED GRADE 20 85��-------------------------------- <br />12" CLEAN, COMPACTED <br />MIN ;L 8AND TREATED FILL <br />12" 8" <br />20" <br />4" REINFORCED SLAB <br />MASONRY STEMWALLS <br />*1 CONCRETE MASONARY UNIT SHALL BE HOLLOW UNIT <br />MASONRY IN ACCORDANCE WITH ASTM C-SO AND SHALL <br />HAVE MINIMUM F'M OF 1500 P.S.I. <br />*2 MORTAR SHALL CONFORM TO ASTMC -210 AND SHALL BE <br />EITHER TYPE M OR S. <br />*3 REINFORCING STEEL SHALL BE GAGE 40 MINIMUM AND <br />IDENTIFIED IN ACCORANCE WITH ASTMA-615.LAP SPLICES <br />WHERE REQUIRED SHALL BE A MINIMUM OF 25" FOR *5 REBAR <br />30" FOR *ro REBAR AND 36" FOR *l REBAR. <br />*4 GROUT FOR POURED CELLS AND LINTELS SHALL HAVE A <br />MAXIMUM COURSE AGGREGATE SIZE OF 3/5" PLACED AT 8 TO <br />11 INCH SLUMP AND HAVE A MINIMUM 28 DAY COMPRESSIVE <br />STRENGTH OF 3000 P.S.I, ( WHEN TESTED PER ASTM C-101S) <br />*5 PROVIDE CLEAN OUT OPENINGS (12 SQ IN.) IN CELLS <br />CONTAINING SPLICED REINFORCEMENT, WHEN THE GROUT <br />POUR EXCEEDS 5 FEET IN HEIGHT, <br />USE 1/4" SIMPSON TITEN MASONRY SCREWS <br />1 1/2" EMBEDDMENT 1 1/2" EDGE DISTANCE <br />AND 32" OC. TO ANCHOR THIS INTERIOR WALL. <br />2x *2 PT SYP BOTTOM PLATE <br />4" SLAB <br />- STEP -__--------- <br />------------ <br />roxro 10/10 WIRE 8" 12ro MIL VISQUEEN <br />REINFORCING MESH 8" 8" 12" VAPOR BARRIER <br />0) *5 REBAR <br />GARAGE STEP DOWN WALL DETAIL <br />ALL CONCRETE USED ON THIS JOB WILL BE NO LESS THAN 3000 PSI, <br />ALL REBAR USED ON THIS JOB WILL BE NO LESS THAN *5, <br />WOODEN HEADER <br />SPLICE, <br />ALL WOOD HEADERS WILL BE LAPPED A MIN OF 48" <br />WHEN SPANS ARE LONGER THAN NOMINAL SIZES AND <br />NAILED WITH 12d GALV, COMMONS AT 12" OC IN (3) ROWS <br />FOR HEADERS AND FLOOR BEAMS MADE OF 2x12, 2x10 <br />AND 2x8, ALL OTHERS WILL BE NAILED IN (2) ROWS, NAIL <br />EACH SIDE OF ALL SPLICES, 1/2" SPACERS ARE NOT <br />REQUIRED. <br />THE GABLE END AND EXTERIOR WALL SHEATHING WILL BE 1/2" CDX <br />OR OSB NAILED TO THE EXTERIOR FACE OF THE GABLE ROOF <br />TRUSSES WITH 8d GALV. COMMONS AT roll OC IN ALL AREAS. COVER <br />THE SHEATHING WITH TYVEK WHOLE HOUSE WRAP AND THE FINISHED SIDING. <br />FIBERGLASS SHINGLES <br />SELF ADHERING ROOFING UNDERLAYMENT <br />THE ROOF SHEATHING WILL BE 1/2" CDX OR OSB NAILED TO <br />THE ROOF TRUSSES WITH Sd GALV. COMMONS AT roll OC IN <br />ALL AREAS. USE 1/2" PLYWOOD CLIPS BETWEEN THE SHEETS <br />AND BLOCKING WHERE PLYCLIPS WONT WORK, <br />SIMPSON HURRICANE TIES <br />SEE THE TRUSS LAYOUT PAGE <br />OF THIS PLAN FOR CONNECTIONS <br />METAL OR ALUM. <br />DRIP EAVE 0.024 MIN, <br />PRE FINISHED FASCIA <br />OVER 2X SUB -FASCIA L� <br />NON -VENTED SOFFITT <br />JAMES HARDI PANEL SIDING OVER <br />1/2" CDX OR OSB SHEATHING <br />1/2" THREADED RODS AS PER <br />THE TRUSS LAYOUT UNLESS <br />OTHERWISE NOTED <br />2 x ro *2 PT BOTTOM PLATES <br />OF THE EXTERIOR WALLS WILL <br />BE ATTACHED TO THE TOP OF <br />THE SLAB WITH 1/2" x 8" J-BOLTS <br />AT 32" OC <br />*5 REBAR IN FILLED CELLS IN THE <br />STEMWALL OF THE FOUNDATION. SEE <br />THE FOUNDATION PAGE FOR THE <br />LOCATION OF THE CELLS. <br />EXISTING GRADE <br />12" MIN DISTANCE - <br />INTO EXISTING GROUND <br />ICYNENE INSULATION <br />ICYNENE INSULATION WILL BE USED AS THE ATTIC <br />AND WALL INSULATION. ICYNENE REQUIRES THAT <br />THE ATTIC WILL NOT HAVE VENTILATION THRU THE <br />SOFFITT OR THE RIDGE. THE HOUSE WILL HAVE TO <br />HAVE A FRESH AIR INTAKE VENT. WITH A DAMPER <br />AS PER THE MECHANICAL CONTRACTOR. <br />OPTIONAL FIBERGLASS INSULATION <br />R-30 ROOF AND R-IS WALL INSULATION MAY BE <br />USED, THE HOMEOWNERS CHOICE. <br />THE INSULATION MUST BE DETERMINED BEFORE THE <br />ENGERGY CALCULATIONS ARE DONE, <br />THE ENGINEER DOES NOT NEED TO REVISE THE PLANS <br />FOR THE INSULATION CHOICE, <br />ALL TEMPORARY AND PERMANENT BRACING INFORMATION <br />FOR THE ENGINEERED ROOF TRUSSES WILL BE FURNISHED BY <br />THE TRUSS COMPANY THAT PRODUCES THE TRUSSES. <br />VERT WEBS ARE REQUIRED AT THE GABLE BRACING LOCATIONS <br />PRE-ENG, WOOD TRUSSES <br />*31 MIN TOTAL LOADING 1/2" CEILING DRYWALL ON ALL INTERIOR CEILINGS <br />2xro *2 SPRUCE STUDS AT 1 ro" OC <br />WITH A DBL TOP PLATE ON <br />ALL BEARING WALLS. <br />1/2" x 8" J- BOLTS AT 32" OC <br />EACH SIDE OF ALL SPLICES <br />AND BESIDE ALL OPENINGS <br />CLEAN, TREATED, COMPACT SOIL <br />THE FOOTERS FOR THE FOUNDATION WILL BE A CONTINUOUS <br />8"x Iro" 3000 PSI FOOTER WITH (2) *5 HORIZONTAL REBARS <br />ON ROD CHAIRS SPACED NO MORE THAN 48" OC, THE RODS <br />WILL BE TIED TO THE CHAIRS. THE MIN LAP FOR IS 25" AND ALL <br />LAPS WILL BE TIED, <br />SOIL BEARING CAPACITY <br />THESE PLANS WERE DRAWN BASED UPON AN ALLOWABLE <br />SOIL BEARING CAPACITY OF 2000 P.S.F.(MINIMUM) THE <br />CONTRACTOR / PROPERTY OWNER IS RESPONSIBLE FOR <br />VEIFYING THAT THE SOIL ON THE SITE IS PROPERLY <br />PREPARED AND COMPACTED SUCH THAT IT CAN SUPPORT <br />A 2000 P.S.F. FOUNDATION LOADING. <br />1/2" DRYWALL ON THE INTERIOR <br />OF THE FRAME WALLS. 11 <br />AMIN OFADBL2x *2 <br />SOUTHERN YELLOW PINE <br />HEADERS ON ALL EXTERIOR <br />FRAME OPENINGS II <br />A 4" / 3000 PSI CONCRETE SLAB OVER roxro 10/10 WIRE <br />MESH AND A ro MIL.VISQUEEN VAPOR BARRIER WILL BE <br />POURED , THE SOIL WILL BE TREATED FOR TERMITES AND <br />BE CLEAN AND COMPACTED. FIBERMESH CONCRETE MAY <br />BE USED WITH WIRE MESH, <br />2xro SPLICE BLOCKING 9ro" CENTERLINE <br />FROM THE FINISHED FLOOR, <br />BLOCKING REQUIRED BETWEEN <br />THE STUDS A MAX OF 4'-8" OC. <br />IN ALL BEARING WALLS, <br />ALL CONNECTIONS TO THE PRESSSURE <br />TREATED WOOD WILL BE HOT -DIPPED <br />ZINC COATED GALVANIZED STEEL. <br />THE BUILDING SITE SHALL BE SCRAPED TO REMOVE ALL ORGANIC MATERIALS. ANY ADDITIONAL FILL <br />PLACED ON THE BUILDING PAD AREA SHALL BE COMPACTED SUCH THAT IT CAN ADEQUATELY <br />SUPPORT A 2000 P.S.F. FOUNDATION LOADING. THE SLAB SHALL BE PLACED OVER A roMIL VAPOR <br />BARRIER ON CLEAN ADEQUATELY COMPACTED AND TERMITE POISONED SOIL, THE CONCRETE UTILIZED <br />IN THE FOUNDATION AND SLABS SHALL HAVE A MINIMUM 28 DAY COMPRESSIVE STRENGTH OF 3000 P.S.I. <br />REINFORCING STEEL SHALL BE GRADE 40 MINIMUM AND IDENTIFIED IN ACCORDANCE WITH ASTM A 4015, <br />LAP SPLICES, WHERE REQUIRED SHALL BE A MINIMUM OF 25" FOR *5 REBAR. <br />TREATMENT: ( SOIL CHEMICAL BARRIER METHOD) <br />1) <br />A PERMANENT SIGN TO IDENTIFY THE TERMITE TREATMENT PROVIDER AND <br />S) <br />CONCRETE OVER POUR AND MORTAR ALONG THE FOUNDATION PERIMETER MUST BE <br />NEED FOR RE -INSPECTION AND TREATMENT CONTRACT RENEWAL SHALL BE PROVIDED. <br />REMOVED BEFORE EXTERIOR SOIL TREATMENT <br />THE SIGN SHALL BE POSTED NEAR THE WATER HEATER OR ELECTRIC PANEL <br />10) <br />SOIL TREATMENT MUST BE APPLIED UNDER ALL EXTERIOR CONCRETE OR GRADE WITH 1'-0" <br />2) <br />CONDENSATE AND ROOF DOWN SPOUTS SHALL DISCHARGE AT LEAST 1'-0" AWAY FROM <br />OF THE STRUCTURES SIDEWALLS. <br />THE BUILDING SIDEWALLS <br />11) <br />AN EXTERIOR VERTICAL CHEMICAL BARRIERS MUST BE INSTALLED AFTER <br />3) <br />IRRIGATION SYSTEMS INCLUDING ALL RISERS AND SPRAY HEADS SHALL <br />CONSTRUCTION IS COMPLETE INCLUDING LANDSCAPING AND IRRIGATION. <br />NOT BE INSTALLED WITHIN 1'-0" OF THE BUILDINGS SIDEWALLS <br />ANY SOIL DISTURBED AFTER THE VERTICAL BARRIER IS APPLIED, SHALL BE <br />4) <br />TO PROVIDE FOR INSPECTION FOR TERMITE INFESTATION BETWEEN WALL COVERING <br />RETREATED. <br />AND FINAL EARTH GRADE SHALL NOT BE LESS TPA 6 INCHES ( EXCEPTION PAINT OR <br />12) <br />ALL BUILDINGS ARE REQUIRED TO HAVE PRE -CONSTRUCTION TREATMENT <br />DECORATIVE CEMENTIOUS FINISP LESS THAN 5/8" THICK ADHERED DIRECTLY TO THE <br />13) <br />A CERTIFICATE OF COMPLIANCE MUST BE ISSUED TO THE BUILDING DEPARTMENT BY <br />FOUNDATION WALL.) <br />A LICENSED PEST CONTROL COMPANY BEFORE A CERTIFICATE OF OCCUPANCY WILL <br />5) <br />INITIAL TREATMENT SHALL BE DONE AFTER ALL EXCAVATION AND BACK FILL IS COMPLETED, <br />BE ISSUED. THE CERTIFICATE OF COMPLIANCE SHALL STATE: " THE BUILDING HAS <br />6) <br />SOIL DISTURBED AFTER THE INITIAL TREATMENT SHALL BE RETREATED INCLUDING SPACES BOXED <br />RECEIVED A COMPLETE TREATMENT FOR THE PREVENTION OF SUBTERRANEAN TERMITES. <br />THE TREATMENT IS IN ACCORDANCE WITH THE RULES AND LAWS OF THE <br />OR FORMED, <br />FLORIDA DEPARTMENT OF AGRICULTURE AND CONSUMER SERVICES. <br />1) <br />BOXED AREAS IN CONCRETE FLOORS FOR SUBSEQUENT INSTALLLATION OF TRAPS, ETC. SHALL BE <br />14) <br />AFTER ALL WORK IS COMPLETE LOOSE WOOD AND FILL MUST BE REMOVED FROM <br />MADE WITP PERMANENT METAL OR PLASTIC FORMS. PERMANENT FORMS MUST BE OF A SIZE AND <br />BELOW AND WITHIN 1'-0" OF THE BUILDING. THIS INCLUDES ALL GRADE STAKES,TUB <br />DEPTH THAT WILL ELIMINATE THE DISTURBANCE OF SOIL AFTER THE INITIAL TREATMENT , <br />TRAP BOXES, FORMS,SPORING OR OTHER CELLULOSE CONTAINING MATERIAL. <br />8) <br />A MINIMUM 6 MIL VAPOR RETARDER MUST BE INSTALLED TO PROTECT AGAINST <br />15) <br />NO WOOD , VEGETATION, STUMPS, CARDBOARD ,TRASH ETC. , SHALL BE BURIED WITHIN <br />RAINFALL DILUTION. IF RAINFALL OCCURS BEFORE VAPOR RETARDER PLACEMENT, <br />15'-0" OF ANY BUILDING OR PROPOSED BUILDING <br />RE -TREATMENT IS REQUIRED, <br />DATE NO pA�E 8 <br />3/16/20 SCALE <br />DESIGN SERVICES INC. <br />MOBILE/ OFFICE 352-206-5821 <br />R. S. HANLEY P O BOX 1325 SAN ANTONIO <br />FLA. 33516 <br />EMAIL: hanley0rolmembargmaf l.com <br />CUSTOM HOMES AND BARNS <br />FRAMING NOTES: <br />1) ALL WOOD IN CONTACT WITH CONCRETE, MASONRY, SOIL <br />OR THE WEATHER SHALL BE NO LESS THAN *2 PT SOUTHERN <br />YELLOW PINE. <br />2) ALL INTERIOR AND EXTERIOR WALLS SHALL BE *2 SPRUCE <br />OR SOUTHERN YELLOW PINE OR BETTER. THE MAS SPACING <br />FOR ANY STUDS WILL BE fro" OC, THE EXTERIOR WALLS WILL <br />BE COVERED WITH A SUB -LAYER OF 1/2" SHEATHING AND A <br />VAPOR BARRIER OF TYVEK WHOLE HOUSE WRAP AND SIDING, <br />3) THE SIMPSON PRODUCTS IN THIS PLAN MAY BE SUBSTITUTED <br />WITH THOSE OF GREATER OR EQUAL VALUES. ALWAYS VERIFY <br />THIS WITH THE PLANS DESIGNER. <br />4) ALL ELECTRICAL,PLUMBING AND MECHANICAL ROUGH -INS <br />ARE TO BE COMPLETED, INSPECTED AND APPROVED PRIOR <br />TO REQUESTING A FRAMING INSPECTION. <br />5) ALL INTERIOR FRAME WALL DIMENSIONS ARE GIVEN TO THE <br />CENTER OF THE WALL. UNLESS NOTED OTHERWISE. <br />ro) ALL OF THE EXTERIOR WALL DIMENSIONS ARE GIVEN TO <br />THE OUTSIDE FACE OF THE FRAME OR MASONRY WALLS THAT <br />ALIGN WITH THE OUTSIDE FACE OF THE FOUNDATION. FRAME <br />WALLS ARE HELD IN 1/2" SO THE EXTERIOR SUB -LAYER OF <br />THE WALL SHEATHING WILL ALIGN WITH THE FOUNDATION. <br />1) ALL WOODEN HEADERS ARE TO BE NO LESS THAN A DBL <br />2Xro *2 SOUTHERN YELLOW PINE. SEE THE TRUSS LAYOUT FOR <br />THE HEADERS REQUIRED, (1/2" SPACERS ARE NOT REQUIRED) <br />8) ALL FLOOR JOIST , RAFTERS AND STRUCTURAL BEAMS WILL <br />BE NO LESS THAN *2 SOUTHERN YELLOW PINE LUMBER. <br />S) ALL TEMPORARY AND PERMANENT BRACING INFORMATION <br />FOR THE ENGINEERED ROOF TRUSSES WILL BE FURNISHED BY <br />THE TRUSS COMPANY THAT PRODUCES THE TRUSSES. VERT. <br />WEBS ARE REQUIRED AT ALL GABLE BRACING LOCATIONS. <br />10) NAIL 2x BLOCKING BETWEEN THE ROOF TRUSSES IN ALL <br />AREAS THAT A PLY -CLIP WONT WORK. <br />11) THE WOOD SIDING, SHEATHING AND FRAMING ON THE EXTERIOR <br />OF ANY BUILDING SHALL HAVE A MIN. CLEARANCE OF roll ABOVE <br />THE FINISHED GRADE. <br />12) ALL CONNECTIONS TO THE PRESSSURE TREATED WOOD WILL <br />BE HOT -DIPPED ZINC COATED GALVANIZED STEEL. <br />�• :00 <br />Si <br />NO.53608 t <br />.010 ; $ TE OF40 o see <br />: •• <br />•• ••lop <br />JOB NAME and ADDRESS <br />C4LV IN and LINDSEY DOQUE <br />PARCEL* 10-24-21-0010-09100-0020 <br />8 th AVE ZEPHYRHILLS, FLORIDA <br />33542 <br />MAIN LIVING AREA 21roro SF <br />FRONT ENTRY Sro SF <br />REAR COVERED PORCH 43ro SF <br />GARAGE 4135 SF <br />TOTAL UNDER ROOF 3183 SF <br />DAV ID W. SMITH, MS. PE, <br />FLORIDA LIC.* 53608 <br />352-521-0865 OFFICE 352-521-0861 FAX, <br />SSOS WALLASTON DRIVE DADE CITY ,FLA, 33525 <br />1 HEREBY CERTIFY THAT I HAVE REVIEWED THIS <br />PLAN AND FOUND IT TO BE IN COMPLIANCE WITH <br />ASCE -1-10 AND THE 2011 FLO IDA BUILDING CODE <br />roth EDITION, <br />DAVID W. SMITH, MS. PE, LIC.* 53606 <br />