I <br />UniSpec II- Store Planning 062615 <br />SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION <br />PART 1 - GENERAL <br />1.1 SUMMARY <br />A. Section Includes: <br />1. Progress Schedules and Reports <br />B. Related Requirements: <br />1. Construction Contract Between Walmart and Contractor. Requirements for construction schedules and re- <br />ports. Ref Articles 1.1.15 and 3.8. <br />1.2 CONSTRUCTION SCHEDULE <br />A. Using the Milestone Completion Dates identified in Exhibit 1.1.16 of the Construction Contract; the Contractor <br />shall develop the detailed CPM Construction Schedule with activity time duration in calendar days further describ- <br />ing his method for performing the Work. The Contractor shall review the Contractor's schedule with the Owner's <br />Construction Manager within 3 weeks from award of Contract, or at the Pre -Construction Meeting, whichever is <br />first. Failure of the Contractor to have a construction schedule approved by the Owner's Construction Manager <br />will be considered cause to withhold progress payments. <br />1. The Milestone Completion Dates identified in Exhibit 1.1.16 of the Construction Contract shall not be <br />construed as an indication by the Owner as to means, methods, or techniques of construction to be <br />employed by the Contractor. <br />2. Critical path activities shall be indicated on the Contractor's detailed construction schedule. <br />1.3 CONSTRUCTION PROGRESS CHART <br />A. Progress of the Project will be monitored using charts produced from the CPM Schedule. Requirements herein <br />provide for planning and execution of the Work and are to assist the Wal-Mart Construction Manager in evaluating <br />progress of the Work economically and chronologically. <br />B. The Contractor shall be familiar, in detail, with the Milestone Completion Dates identified in Exhibit 1.1.16 of the <br />Construction Contract. By submitting his bid, the Contractor acknowledges that the Construction milestones are <br />feasible, reasonable, and are a workable schedule for the Work. <br />C. Delivery times for Wal-Mart Furnished Items are specified in Section 01640. Coordinate delivery of these items <br />with progress of the Work. <br />D. Prior to construction, the Contractor may request reasonable changes to the Construction Progress Schedule Chart, <br />provided delivery dates specified in Section 01640 and the contract completion date are not changed. The Wal- <br />Mart Construction Manager will review requested changes. Upon approval by Wal-Mart, Progress Schedule Chart <br />shall become the "Approved Construction Progress Chart" by which the Contractor shall plan, organize, direct, <br />coordinate, and execute the Work, and the basis of evaluating progress of the Work. <br />E. If, in the opinion of the Wal-Mart Construction Manager, any of the dates specified in Section 01640 are not com- <br />pleted by the Contractor on or before the stated time period and after 48 hours written notice to the Contractor, <br />i Wal-Mart may proceed to carry out the work in accordance with Article 2.4 of the Construction Contract. <br />A F. The Contractor shall perform work directed by the Wal-Mart Construction Manager to meet the Wal-Mart contract <br />completion date and shall maintain the original management and supervision team to continue their office and job <br />site duties on a full-time basis through final completion and/or any other time the Contractor has any work being <br />performed on the project regardless of the date or condition of project completion. <br />01320 - 1 <br />0706 - Zephyrhills, Florida - 16592140 February 16, 2017 <br />