My WebLink
|
Help
|
About
|
Sign Out
Browse
Search
7631 Gall Blvd (36)
Zephyrhills
>
Building Department
>
Building Plans
>
7631 Gall Blvd (36)
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
2/26/2025 12:05:23 PM
Creation date
2/18/2025 4:18:07 PM
Metadata
Fields
Template:
Building Plans
Street #
7631
Location
Gall Blvd
Building Plans - Permit #
18385
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
512
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
1.4 SCHEDULE UPDATES <br />A. The Contractor shall provide to the Wal-Mart Construction Manager regular updated reports on the Construction <br />Schedule as determined by the Wal-Mart Construction Manager. The Contractor shall maintain a current weekly <br />updated detailed construction schedule in the site construction field office. <br />1. Construction Schedule Updating: Progress information to be included in schedule updates includes actual <br />start and finish dates, percentage complete, remaining duration or projected finish dates for all activities in <br />progress during reporting period. Schedule updates may also include approved added activity descriptions. <br />1.5 RECOVERY PLAN <br />A. Should the updated approved Construction Schedule show the Contractor to be behind schedule, the Contractor <br />shall immediately devise a plan for recovery of lost time within one week and submit it to the Wal-Mart Construc- <br />tion Manager for approval. Once approved by the Wal-Mart Construction Manager, the Contractor shall immedi- <br />ately put the recovery plan into action. <br />B. During the period covered by the recovery plan, the Contractor's progress will continue to be monitored against the <br />Approved Construction Progress Chart. If the Contractor does not recover from delay as detailed in the recovery <br />plan, Wal-Mart may exercise the option to carry out the work as specified above. <br />C. The Contractor shall bear all costs and expenses related to recovery from the Contractor's delays, including costs, <br />expenses, and lost sales incurred by Wal-Mart. <br />PART2-PRODUCTS <br />Not Used. <br />PART 3 - EXECUTION <br />Not Used. <br />END OF SECTION <br />01320 - 2 <br />1 <br />1 <br />I,] <br />1 <br />1 <br />1� <br />0706 - Zephyrhills, Florida - 16592140 February 16, 2017 <br />1 <br />
The URL can be used to link to this page
Your browser does not support the video tag.