<br />... r---'-- <br /> <br /> <br />such work shall be executed under the applicable conditions. of the <br />Contract Documents. If any Change Order causes an increase or <br />decrease in the Contract Price or an extension or shortening of the <br />Contract Time, an equitable adjustment will be made. " <br /> <br />The RPR may authorize changes or alterations in the work not involving <br />extra cost and not inconsistent with the overall intent of the Contract <br />Documents. These may be accomplished by a Field Order. If the <br />Contractor believes that any minor change or alteration authorized by <br />the RPR entitled him to an increase in the Contract Price, he may make a <br />claim in writing. <br /> <br />The Contractor shall not start work on any alteration requiring an increase <br />or decrease in price or extension of time until a Change Order setting <br />forth the adjustments is executed by the City. <br /> <br />It is the Contractor's responsibility to notify his Surety of any changes <br />affecting the general scope of the work or change in the Contract Price <br />and the amount of the applicable Bonds shall be adjusted accordingly. <br />The Contractor shall furnish proof of such adjustment to the City. <br /> <br />Change of Contract Time: The Contract Time may only be changed by a <br />Change Order. Any claim for an extension in the Contract Time, shall be <br />in writing delivered to the City within five days of the occurrence of the <br />event giving rise to the claim. All claims for adjustment in the Contract <br />Time shall be determined by the Engineer if the City and the Contractor <br />cannot otherwise agree. Any change in the Contract Time resulting from <br />any such claim shall be incorporated in a Change Order. <br /> <br />The Contract Time will be extended in an amount equal to time lost due <br />to delays beyond the control of the Contractor if he makes a claim <br />therefore as prOVided for. Such delays shall include, but not be restricted <br />to, acts or neglect by any separate Contractor employed by the City, <br />fires, floods, labor. disputes, epidemics, abnormal weather conditions, or <br />acts of God. . <br /> <br />All time limits stated in the Contract Docume/')ts are of the essence of the <br />Agreement. <br /> <br />Where delays are not justified and actual damages are impossible of <br />agreed determination, and when so required by a statement in the <br />section "Special Conditions", the Contractor and his Sureties shall be <br />liable for and shall pay to the City the sum stated in "Special Conditions", <br /> <br />19 <br />